Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka with Fujii-san:
   * We attempted to measure the tilt sensitivity of the accelerometers by adding shims under the legs but gave up when we discovered that picking up and putting down the accelerometer perturbs the zero point even without shims. We will probably need a special tilt stage to do this properly.
   * We took some frequency and Q measurements. The results were amplitude dependent. Joris thinks that this is due to not operating the accelerometers close enough to zero DC output.
   * We set up for a test of the geophone noise. One geophone is reading half the output of the others - one of the adapter cables is broken.
  * Hirata-san:
   * Received extra compensation masses and washed them.
   * Received PI guides, assembled them and shipped them to Kamioka.
   * Received backup set of pillar for security structure (with M10 instead of M12 holes at top).
   * Removed adhesive from base of BS flags in preparation for regluing.
   * Did assembly drawings for cable clamps and other add-on parts for BF and SF.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Feedthrough Adapters
   * Connectors RECEIVED.
  * SR machining test ONGOING.
  * Installation stuff
   * "Ceiling" work in BS clean booth (removal of second floor section) scheduled for Fri 7/1.
   * Assembly frame construction scheduled for 7/4
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - ordered with assembly frame, will arrive next week.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 7/30 ====
 * We set up an OL outside the tank and checked the SR3 pitch - it was OK.
 * We ran power to the SR3 pico and stepper drivers and tested them.
 * We tried to offload a 700 µm discrepancy between the BF GAS zero position and the IM-V zero position but ended up scrambling the IRM-IM alignment, probably through sending a command to the wrong pico driver. We mostly fixed the BF/IRM pitch/roll, but we have some more work to do to fix the IM/RM/TM pitch/roll.
 * We debugged a problem with the SR2 alignment - the chain was offset by about 5 mm to +T, leading to fouling at the IM and RM levels. Some 2 mm of the offset was due to the F0 keystone being off center, apparently due to some combination of different-strength blades and the CuBe auxiliary spring, but the rest is a mystery.
 * We fixed a problem with the levelness of the PI due to the feet of the IP being set at uneven heights into the PI weldment, and it got the IP very closed to centered but it didn't fix the fouling problem.
 * We eventually fixed the fouling by setting the security structure at a slight angle so it remains slightly off at the SF level but is good at the bottom.
 * We installed the SR2 SF damper Cu segments and magnet ring.
 * Enzo and team debugged a malfunctioning bit in the SR3 IP BIO which turned out to be a defective 37-pin gender changer.

==== Plan for week of 8/6 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Do TFs with temporary OL.
 * Install final OL.
 * Hook LBB, add ballast mass.

===== SR2 =====
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 
===== SRM =====
 * Assemble metal mass.
 * Glue prisms, flags.
 * Reconfigure, align assembly frame.
 * Tune F0 for SRM.
 * Add LBB blade units, cable clamps etc.
 * Check PI coil connections, IP LVDT magnets.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/30

  • We set up an OL outside the tank and checked the SR3 pitch - it was OK.
  • We ran power to the SR3 pico and stepper drivers and tested them.
  • We tried to offload a 700 µm discrepancy between the BF GAS zero position and the IM-V zero position but ended up scrambling the IRM-IM alignment, probably through sending a command to the wrong pico driver. We mostly fixed the BF/IRM pitch/roll, but we have some more work to do to fix the IM/RM/TM pitch/roll.
  • We debugged a problem with the SR2 alignment - the chain was offset by about 5 mm to +T, leading to fouling at the IM and RM levels. Some 2 mm of the offset was due to the F0 keystone being off center, apparently due to some combination of different-strength blades and the CuBe auxiliary spring, but the rest is a mystery.

  • We fixed a problem with the levelness of the PI due to the feet of the IP being set at uneven heights into the PI weldment, and it got the IP very closed to centered but it didn't fix the fouling problem.
  • We eventually fixed the fouling by setting the security structure at a slight angle so it remains slightly off at the SF level but is good at the bottom.
  • We installed the SR2 SF damper Cu segments and magnet ring.
  • Enzo and team debugged a malfunctioning bit in the SR3 IP BIO which turned out to be a defective 37-pin gender changer.

Plan for week of 8/6

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

SR3
  • Finalize optic pitch, OSEM alignment.
  • Do TFs with temporary OL.
  • Install final OL.
  • Hook LBB, add ballast mass.

SR2
  • Add estimated final ballast mass.
  • Do PI cable routing.
  • Adjust ballast/trim mass, with reserve for cables.

SRM
  • Assemble metal mass.
  • Glue prisms, flags.
  • Reconfigure, align assembly frame.
  • Tune F0 for SRM.
  • Add LBB blade units, cable clamps etc.
  • Check PI coil connections, IP LVDT magnets.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.