Differences between revisions 34 and 62 (spanning 28 versions)
Revision 34 as of 2016-07-01 13:11:54
Size: 2400
Editor: MarkBarton
Comment:
Revision 62 as of 2016-09-02 13:42:20
Size: 2658
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian worked at Kamioka with Fujii-san:
   * We attempted to measure the tilt sensitivity of the accelerometers by adding shims under the legs but gave up when we discovered that picking up and putting down the accelerometer perturbs the zero point even without shims. We will probably need a special tilt stage to do this properly.
   * We took some frequency and Q measurements. The results were amplitude dependent. Joris thinks that this is due to not operating the accelerometers close enough to zero DC output.
   * We set up for a test of the geophone noise. One geophone is reading half the output of the others - one of the adapter cables is broken.
  * Hirata-san:
   * Received extra compensation masses and washed them.
   * Received PI guides, assembled them and shipped them to Kamioka.
   * Received backup set of pillar for security structure (with M10 instead of M12 holes at top).
   * Removed adhesive from base of BS flags in preparation for regluing.
   * Did assembly drawings for cable clamps and other add-on parts for BF and SF.
 * Type B Past Week Summary - weeks of 8/22 and 8/29
  * Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
   * Weighed the BF, SF and dummy BS (in mirror box).
   * Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
   * Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
   * Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
   * Realigned and immobilized the optical table (which had been bumped).
   * Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
   * Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
   * We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
Line 17: Line 20:
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Feedthrough Adapters
   * Connectors RECEIVED.
  * SR machining test ONGOING.
  * Installation stuff
   * "Ceiling" work in BS clean booth (removal of second floor section) scheduled for Fri 7/1.
   * Assembly frame construction scheduled for 7/4
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - ordered with assembly frame, will arrive next week.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary - weeks of 8/22 and 8/29
    • Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
      • Weighed the BF, SF and dummy BS (in mirror box).
      • Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
      • Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
      • Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
      • Realigned and immobilized the optical table (which had been bumped).
      • Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
      • Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
      • We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
    • Hirata-san made a 3D assembly model for SR2 and added the optical design.
    • Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
    • Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
    • Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
  • Type B ongoing issues
    • Longer cables for BF->PI and SF->PI - RECEIVED

  • Longer term to-do list
    • Decide position of BS rack - DONE
    • Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING

    • Lower breadboard installation to be incorporated into the procedure document.
    • Work on BS simulation (Fabian)
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)