Differences between revisions 34 and 81 (spanning 47 versions)
Revision 34 as of 2016-07-01 13:11:54
Size: 2400
Editor: MarkBarton
Comment:
Revision 81 as of 2016-11-04 11:08:28
Size: 1472
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * Mark and Fabian worked at Kamioka with Fujii-san:
   * We attempted to measure the tilt sensitivity of the accelerometers by adding shims under the legs but gave up when we discovered that picking up and putting down the accelerometer perturbs the zero point even without shims. We will probably need a special tilt stage to do this properly.
   * We took some frequency and Q measurements. The results were amplitude dependent. Joris thinks that this is due to not operating the accelerometers close enough to zero DC output.
   * We set up for a test of the geophone noise. One geophone is reading half the output of the others - one of the adapter cables is broken.
  * Hirata-san:
   * Received extra compensation masses and washed them.
   * Received PI guides, assembled them and shipped them to Kamioka.
   * Received backup set of pillar for security structure (with M10 instead of M12 holes at top).
   * Removed adhesive from base of BS flags in preparation for regluing.
   * Did assembly drawings for cable clamps and other add-on parts for BF and SF.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Feedthrough Adapters
   * Connectors RECEIVED.
  * SR machining test ONGOING.
  * Installation stuff
   * "Ceiling" work in BS clean booth (removal of second floor section) scheduled for Fri 7/1.
   * Assembly frame construction scheduled for 7/4
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - ordered with assembly frame, will arrive next week.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * Mark
   * Updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]:
    * Added information on the binary IO.
    * Renamed channels to conform to Okutomi-kun's new scheme.
    * Made the ADC/DAC channel assignment consistent and more logical.
    * Updated the stepper motor sections with info about the new driver chassis.
   * Worked on schedule.
   * Updated the installation procedure with lessons learned from the last few weeks.
   * Downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.
   * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
  * Hirata-san
   * Updated the BS 3D Assembly with the new rods and receptacles.
   * Made 2D drawings of SR2 and SR3 (ongoing).
   * Made SRM 3D assembly (ongoing)
   * Asked for and got quotes for hexagon cable clamps. Takahashi-san ordered the PEEK components. Next week Hirata-san will look for parts that should already be at Kamioka.
   * Washed screws for hexagon cable clamps and shim rings for Fabian.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark
      • Updated the BS circuit diagram D1503600:

        • Added information on the binary IO.
        • Renamed channels to conform to Okutomi-kun's new scheme.
        • Made the ADC/DAC channel assignment consistent and more logical.
        • Updated the stepper motor sections with info about the new driver chassis.
      • Worked on schedule.
      • Updated the installation procedure with lessons learned from the last few weeks.
      • Downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.
      • Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
    • Hirata-san
      • Updated the BS 3D Assembly with the new rods and receptacles.
      • Made 2D drawings of SR2 and SR3 (ongoing).
      • Made SRM 3D assembly (ongoing)
      • Asked for and got quotes for hexagon cable clamps. Takahashi-san ordered the PEEK components. Next week Hirata-san will look for parts that should already be at Kamioka.
      • Washed screws for hexagon cable clamps and shim rings for Fabian.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)