Line 6: Line 6:
==== Report for week of 10/29 ==== ==== Report for week of 12/17 ====
 * BS
  * Miyakawa-san worked on the BS real-time model and the gain/offset settings for the F0 LVDTINF block were lost, so we reentered them and did a new safe.snap file.
Line 8: Line 10:
  * Enzo repaired some broken cables and made some long cables from shorter ones. We ultrasonically cleaned them at Toyama U, with help from Yamamoto-san. Enzo then reinforced the joins with EP30 9two cables) or heat shrink (one cable).
  * Hirata-san finished tuning the PI. It is now complete except for some PEEK cable clamp pieces which are expected next Monday.
  * Hirata-san wiped writing off the F0 and SF yoke magnets, and off the PI.
  * Hirata-san found we were running out of magnets and ordered more - we have almost enough (short by one) for the SF damper, but will need more for the LBB damper.
  * Fabian cabled and tested the BF cap picos.
  * Fabian routed all the cables up to the underside of the SF. He cabled and tested the SF LVDT and stepper.
  * We added the SF cap and weighed the SF/... section. We appear to have a good amount of load capacity margin.
  * We put receptacles and magnets on the SF damper ring.
  * We unlocked the IP adjusted the level with the jacks to center it. As hoped, this also improved the alignment of the chain insecurity structure and fixed a touching issue.
  * Hirata-san installed and cabled the new F0 yaw stepper. We had allowed plenty of reserve mass, so there was no problem getting back to nominal height of the keystone. [''As of Thursday afternoon, it had not yet been tested - UPDATE?'']
  * We found that the Nikhef method Fabian had used to tune the F0 LVDT driver gave an artificially narrow working range, so he retuned it with Enzo's method and recalibrated the LVDT.
  * Fabian did a vertical position survey with all the GAS filters at nominal and found the height of the RM above the SS bottom plate was about 2.5 mm lower than in the CAD. This is about what we expected from a chain 7 mm longer than CAD and and F0 keystone set to 5 mm higher than CAD. In future we can survey to either the optic or the security structure as convenient, and we are in the range where we should easily be able to match the correct beam height with the jacks under the PI.
  * We got two OL viewports for SRM from Akutsu-san, and will install them sometime in January, whenever we have a free moment. Akutsu-san pre-torqued the inner ring of screws around the glass, so we only need to torque the outer bolts.
  * We took transfer functions for the IM. All of them look good except IM-T. We will inspect the payload next week in case anything is touching or rubbing.
  * Hirata-san opened the +X door of the vacuum chamber for visual inspection. We closed it back and covered with tape a small gap at the door.
 * SR3
  * We also got a camera viewport for SR3 from Akutsu-san and will install it sometime in January.
  * Hirata-san installed and cabled the new F0 yaw stepper.
Line 17: Line 21:
  * We opened the SR2 tank, borrowed a geophone for Fujii-kun's geophone test, and left the IP locked.
  * We gathered parts for the SR2 OL. We believe we have all the pieces we need except for an LED (the one originally allocated to SR2 is currently being used for pitch setting on SRM and we may need to steal it back). Akutsu-san wants to supervise us setting up the LED and receiver supports, so that will happen next week.
 * SR3
  * Terrence visited for another week and made more measurements on the OL.
 * BS
  * We searched for the dog clamps that we had borrowed from AOS to serve as ballast for the BS LBB and returned them to the AOS pallet.
 * Electronics
  * Enzo analyzed the LPCD and worked out the resistors we need to get the drive current recommended for the IM-V OSEMs by Shoda-san. We brought back three LPCDs for modification.
  * Enzo calibrated the SR2 OL. He noted that with the standard f=2500 mm collimator, the angular range was only about 100 µrad in pitch and 150 µrad in yaw, which is rather less than Enomoto-kun's preferred range of more like 400 µrad, so we borrowed f=1100 mm and f=3500 mm collimators to characterize. [''Enzo was going to do f=1100 mm and maybe f=3500 mm on Friday morning 12/21 - UPDATE?'']
  * Hirata-san installed and cabled the new F0 yaw stepper. We did not have enough reserve mass for SR2, so to save 300 g we had Mesco make a new, lighter top plate, and Hirata-san ultrasonically cleaned it. We were then able to get the desired F0 keystone height with about 200 g to spare.
  * The RM was touching the security structure and we were able to move it free by adjusting the cylinder with the spring and leaving the stepper motor in its nominal position. The f=1100 mm collimator was installed and the QPD was calibrated.
 * Etc
  * Enzo did a historical survey of the temperature as the various suspensions were being built and concluded that ideal operating temperature would be 25°C in the BS/SR2 area and 24°C for SR3/SRM.
  * Mark wrote a bash script to log all the GAS filter heights and LVDT actuation offsets, and an Excel spreadsheet to analyze the data to get an overview of the heights of the suspensions and the amount of height adjustment being used. He also reviewed old TF data to get near-DC values for the effect of GAS actuation on GAS height. This uncovered a few issues with calibration settings (such as for BS F0) having been lost because they hadn't been recorded in a safe.snap file, which we fixed.
Line 30: Line 33:
==== Plan for week of 11/4 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
  * Add magnets to SF damper.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.
==== Plan for week of 12/17 ====
 * Final alignment of SRM payload, plus BF and SF GAS.
 * (Time permitting) unlocking/centering/tuning of IP.
 * Installation of Enomoto-kun's beam target on SRM (if available).
 * Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
 * Installation of viewports on SRM.
Line 49: Line 40:
==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
==== Plan for week of 12/24 ====
 * Mark and Hirata-san on holidays, Enzo at Mitaka, Fabian.
Line 59: Line 43:
==== Plan for week of 11/18 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Crane into tank.
==== Plan for week of 1/7 ====
 * Make sure BS is floating, recenter OL to capture current yaw position.
 * Vent BS.
 * Inspect BS F0 blades for cracks.
 * Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.
 * Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
 * Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
 * Add more mass to IP to get lower frequency.
 * Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

==== Vacation/Etc Info ====
 * Mark: 12/24 - 1/4.
 * Hirata-san: 12/24 - 1/4.
 * Fabian: 12/31 - 1/4
 * Enzo: 12/31 - 1/4.
 * Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
 * Terrence: back at Kamioka from 1/7.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/17

  • BS
    • Miyakawa-san worked on the BS real-time model and the gain/offset settings for the F0 LVDTINF block were lost, so we reentered them and did a new safe.snap file.
  • SRM
    • We unlocked the IP adjusted the level with the jacks to center it. As hoped, this also improved the alignment of the chain insecurity structure and fixed a touching issue.
    • Hirata-san installed and cabled the new F0 yaw stepper. We had allowed plenty of reserve mass, so there was no problem getting back to nominal height of the keystone. [As of Thursday afternoon, it had not yet been tested - UPDATE?]

    • We found that the Nikhef method Fabian had used to tune the F0 LVDT driver gave an artificially narrow working range, so he retuned it with Enzo's method and recalibrated the LVDT.
    • Fabian did a vertical position survey with all the GAS filters at nominal and found the height of the RM above the SS bottom plate was about 2.5 mm lower than in the CAD. This is about what we expected from a chain 7 mm longer than CAD and and F0 keystone set to 5 mm higher than CAD. In future we can survey to either the optic or the security structure as convenient, and we are in the range where we should easily be able to match the correct beam height with the jacks under the PI.
    • We got two OL viewports for SRM from Akutsu-san, and will install them sometime in January, whenever we have a free moment. Akutsu-san pre-torqued the inner ring of screws around the glass, so we only need to torque the outer bolts.
    • We took transfer functions for the IM. All of them look good except IM-T. We will inspect the payload next week in case anything is touching or rubbing.
    • Hirata-san opened the +X door of the vacuum chamber for visual inspection. We closed it back and covered with tape a small gap at the door.
  • SR3
    • We also got a camera viewport for SR3 from Akutsu-san and will install it sometime in January.
    • Hirata-san installed and cabled the new F0 yaw stepper.
  • SR2
    • Enzo calibrated the SR2 OL. He noted that with the standard f=2500 mm collimator, the angular range was only about 100 µrad in pitch and 150 µrad in yaw, which is rather less than Enomoto-kun's preferred range of more like 400 µrad, so we borrowed f=1100 mm and f=3500 mm collimators to characterize. [Enzo was going to do f=1100 mm and maybe f=3500 mm on Friday morning 12/21 - UPDATE?]

    • Hirata-san installed and cabled the new F0 yaw stepper. We did not have enough reserve mass for SR2, so to save 300 g we had Mesco make a new, lighter top plate, and Hirata-san ultrasonically cleaned it. We were then able to get the desired F0 keystone height with about 200 g to spare.
    • The RM was touching the security structure and we were able to move it free by adjusting the cylinder with the spring and leaving the stepper motor in its nominal position. The f=1100 mm collimator was installed and the QPD was calibrated.
  • Etc
    • Enzo did a historical survey of the temperature as the various suspensions were being built and concluded that ideal operating temperature would be 25°C in the BS/SR2 area and 24°C for SR3/SRM.
    • Mark wrote a bash script to log all the GAS filter heights and LVDT actuation offsets, and an Excel spreadsheet to analyze the data to get an overview of the heights of the suspensions and the amount of height adjustment being used. He also reviewed old TF data to get near-DC values for the effect of GAS actuation on GAS height. This uncovered a few issues with calibration settings (such as for BS F0) having been lost because they hadn't been recorded in a safe.snap file, which we fixed.

To-Do Lists, Schedule

Plan for week of 12/17

  • Final alignment of SRM payload, plus BF and SF GAS.
  • (Time permitting) unlocking/centering/tuning of IP.
  • Installation of Enomoto-kun's beam target on SRM (if available).
  • Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
  • Installation of viewports on SRM.

Plan for week of 12/24

  • Mark and Hirata-san on holidays, Enzo at Mitaka, Fabian.

Plan for week of 1/7

  • Make sure BS is floating, recenter OL to capture current yaw position.
  • Vent BS.
  • Inspect BS F0 blades for cracks.
  • Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.

  • Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
  • Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
  • Add more mass to IP to get lower frequency.
  • Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

Vacation/Etc Info

  • Mark: 12/24 - 1/4.
  • Hirata-san: 12/24 - 1/4.
  • Fabian: 12/31 - 1/4
  • Enzo: 12/31 - 1/4.
  • Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
  • Terrence: back at Kamioka from 1/7.