==== Report for week of 10/29 ====
 * SRM
  * Enzo repaired some broken cables and made some long cables from shorter ones. We ultrasonically cleaned them at Toyama U, with help from Yamamoto-san. Enzo then reinforced the joins with EP30 (two cables) or heat shrink.
  * Hirata-san finished tuning the PI. It is now complete except for some PEEK cable clamp pieces which are expected next Monday.
  * Hirata-san wiped writing marks off the F0 and SF yoke magnets, and off the PI.
  * Hirata-san found we were running out of magnets and ordered more - we have almost enough (short by one) for the SF damper, but will need more for the LBB damper.
  * Fabian cabled and tested the BF cap picos.
  * Fabian routed all the cables up to the underside of the SF. He cabled and tested the SF LVDT and stepper.
  * We added the SF cap and weighed the SF/... section. We appear to have a good amount of load capacity margin.
 * SR2
  * We opened the SR2 tank, borrowed a geophone for Fujii-kun's geophone test, and left the IP locked.
  * We gathered parts for the SR2 OL. We believe we have all the pieces we need except for an LED (the one originally allocated to SR2 is currently being used for pitch setting on SRM and we may need to steal it back). Akutsu-san wants to supervise us setting up the LED and receiver supports, so that will happen next week.
 * SR3
  * Terrence visited for another week and made more measurements on the OL. A report is forthcoming.
 * BS
  * We searched for the dog clamps that we had borrowed from AOS to serve as ballast for the BS LBB and returned them to the AOS pallet.
 * Electronics
  * Enzo analyzed the LPCD and worked out the resistors we need to get the drive current recommended for the IM-V OSEMs by Shoda-san.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
==== Report for the week of 3/25 ====
 * Mark and Fabian helped Fujii-kun with PR2. The problem turned out to be two broken flags. Hirata-san drew up a design for a jig to help reglue the flags in situ.
 * Fabian documented the height budget for the Type B suspension in the wiki ([[KAGRA/Subgroups/VIS/OpsManual/TypeB/SR3Data]] etc).
 * Terrence wrote up the final version of his OL diagonalization scheme.
 * Terrence worked on L2P decoupling for the TM.
 * Terrence and Mark edited the Type B Guardian to turn on the payload damping later in the sequence, after IP and GAS, to help ensure that the OSEMs are not touching by the time they're needed (which can happen if the BF is buoyancy compensated for vacuum but the suspension is vented).
 * Mark started on a big tidy-up of the cleanbooth.
 * Mark asked LIGO colleagues about use-by dates for EP30-2. Masterbond says it's good for 6 months in cartridge form and 12 months in jar form (although presumably only if the jars are not opened). If it's too old it may remain tacky after curing. The batch that Type B has was manufactured 2017-11-02 and KEK has a batch from early 2018.
Line 29: Line 14:
==== Plan for week of 11/4 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
  * Add magnets to SF damper.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.
==== Plan for week of 3/25 ====
 * Mark, Fabian at Kamioka Mon-Fri.
 * Assist with PR2.
 * Work on Type B paper.
 * Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
 * Tidy up.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.
  * Return all unused cables to tent.
  * Tidy up cables in rear of SR2 rack.
Line 48: Line 25:
==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.

==== Plan for week of 11/18 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Crane into tank.
==== Vacation/Travel Info ====
 * Enzo's last day 3/29.
 * Terrence's last day for now, 3/29.
 * Mark compensation day for 3/21: 3/29. (He is not really typing these minutes, and anyone who sounds like him in the meeting is an impostor!)
 * Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's vacation from about 5/22 to 6/11 (TBD).
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/25

  • Mark and Fabian helped Fujii-kun with PR2. The problem turned out to be two broken flags. Hirata-san drew up a design for a jig to help reglue the flags in situ.
  • Fabian documented the height budget for the Type B suspension in the wiki (KAGRA/Subgroups/VIS/OpsManual/TypeB/SR3Data etc).

  • Terrence wrote up the final version of his OL diagonalization scheme.
  • Terrence worked on L2P decoupling for the TM.
  • Terrence and Mark edited the Type B Guardian to turn on the payload damping later in the sequence, after IP and GAS, to help ensure that the OSEMs are not touching by the time they're needed (which can happen if the BF is buoyancy compensated for vacuum but the suspension is vented).
  • Mark started on a big tidy-up of the cleanbooth.
  • Mark asked LIGO colleagues about use-by dates for EP30-2. Masterbond says it's good for 6 months in cartridge form and 12 months in jar form (although presumably only if the jars are not opened). If it's too old it may remain tacky after curing. The batch that Type B has was manufactured 2017-11-02 and KEK has a batch from early 2018.

Plan for week of 3/25

  • Mark, Fabian at Kamioka Mon-Fri.
  • Assist with PR2.
  • Work on Type B paper.
  • Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
  • Tidy up.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.
    • Return all unused cables to tent.
    • Tidy up cables in rear of SR2 rack.

Vacation/Travel Info

  • Enzo's last day 3/29.
  • Terrence's last day for now, 3/29.
  • Mark compensation day for 3/21: 3/29. (He is not really typing these minutes, and anyone who sounds like him in the meeting is an impostor!)
  • Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's vacation from about 5/22 to 6/11 (TBD).
  • Mark's final day 6/28.