Line 2: Line 2:
Line 6: Line 5:
==== Report for week of 10/29 ==== ==== Report for the week of 3/18 ====
 * BS
  * Terrence notice that one of the IP LVDTs was not working. We traced it to an unplugged cable, plugged it back in and screwed it together to prevent a recurrence.
  * Simon helped us rebuild the damaged LEN OL QPD stage and Terrence reinstalled it. We removed a C-clamp that we had been using to immobilize the breadboard because it interfered with the QPD stage, and replaced it with a more elegant solution using a dog clamp underneath.
  * We noticed that the BS IP had fallen over in +L at some time shortly before Nakano-san aligned the optic on 3/18. Terrence tried to recenter it but it was unstable. We decided to remove the tank lid one more time and remove some arc weights. The IP frequency had been 39 mHz the last time it was measurable, and we increased it to a much-safer 80 mHz by removing 9 kg. We believe we were able to recover Nakano-san's alignment fairly closely.
  * Terrence then recalibrated and diagonalized both the TILT and LEN OL.
 * SR2
  * Terrence recalibrated the OL.
 * SR3
  * Mark pulled out unused cables leading into the SR3 cleanbooth.
Line 8: Line 16:
  * Enzo realized that he could cover the next round of needed cables (all except geophones) with more cable soldering and did another batch. Because Yamamoto-san's lab was running low on isopropanol, Hirata-san washed them with ethanol at Mozumi.
  * Enzo worked out the optimum output resistance for the LPCDs to substitute for HPCDs with the horizontal IM OSEMs. The value was quite close to that already chosen for modified LPCDs by the cryogenic group, so we're going to standardize on 680 Ω. The modified LPCDs will have to be operated with the internal watchdog disabled for now because it was hard-wired to 2 mA.
  * Fabian finished adding the TM OSEM cables out to the rack and tested them.
  * We ran DC power and network to the second SRM stepper driver. We still need to get one more DC power cable to replace one we borrowed from SR3. We added the remaining steppers to the Python driver and MEDM screen.
  * We reconfigured the top of the assembly frame in preparation for the PI (removing crossbars and moving jacks down).
  * Hirata-san put the magnets on the SF damper and we hooked it to the PI, craned the PI into the assembly frame and joined it to the security structure.
  * We installed the F0-SF rod and flying saucer and suspended the SF/... section. We had plenty of spare load capacity, so we changed the CuBe spring to a weaker one and put 2.3 kg of ballast on the SF cap. This leaves 1.2 kg reserve for cables and an F0 yaw stepper mechanism.
  * We reduced the trim mass on the BF to compensate for the mass of the TM OSEM cables.
  * We measured all the bounce frequencies.
  * Hirata-san put magnets on the LBB damper magnet ring, put the pieces into the tank and assembled them into a sandwich ready for craning. He also did the fixed ring on the ceiling of the tank.
  * Fabian noticed that the DSub9 connectors on the PTFE cables are highly magnetic and need to be kept away from the magnets on the SF damper. This
 * SR2
  * Hirata-san unclamped the LBB damper rings and suspended the LBB. It still needs ballast mass and is currently sitting high, with the blades at their upper stops.
  * Terrence set up the SRM Guardian.
 * Etc/All
  * Mark did an audit of the OL whitening/dewhitening system and fixed a bunch of problems: the SRM chassis was the wrong type, with no actual whitening card; SR2 and SRM needed whitening filters turned on; BS LEN needed the dewhitening turned on; SR2, SR3 and SRM needed dewhitening filters installed and turned on; SRM needed more gain.
  * Terrence weeded out a minor error from his OL diagonalization scheme and got L, T and Y independent at the 1% level for SR2 and SRM. He will do SR3 next.
  * Fabian measured the gain resistor values and other settings of the LVDT drivers, in case a card or chassis fails and we have to approximate the original state without the chance to recalibrate from scratch.
  * Fabian monitored the pumpdown.
Line 22: Line 23:
  ==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
==== Plan for week of 3/25 ====
 * Mark, Fabian, Terrence at Kamioka Mon-Thu.
 * Assist with alignment.
 * Work on Type B paper.
 * Tidy up.
  * Throw out foil and other garbage.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.
  * Return all unused cables to tent.
  * Tidy up cables in rear of SR2 rack.
Line 28: Line 34:
==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
  * Unlock IP and center roughly.
  * Calibrate IP LVDTs.
  * Check/adjust alignment of SS.
  * Add arc weights and geophones (or extra mass equivalent to geophones).
  * Cable/test geophones.
  * Improve centering/tuning of IP and SS alignment.
 * LBB
  * Crane LBB damper ring sandwich to top of lower section of tank.
  * Set tank jacks to nominal height.

==== Plan for week of 11/19 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo and Fabian at Kamioka Mon-Thu.
 * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Crane into tank.

==== Plan for week of 11/26 ====
 * Move SRM in-air cables over to tank.
 * Unlock and align SRM.
==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.


==== Vacation/Event Info ====
 * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).
==== Vacation/Travel Info ====
 * Enzo's final vacation till 3/29.
 * Terrence's last day for now, 3/29.
 * Mark compensation day for 3/21: 3/29.
 * Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's final day ≈6/28 (TBD).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/18

  • BS
    • Terrence notice that one of the IP LVDTs was not working. We traced it to an unplugged cable, plugged it back in and screwed it together to prevent a recurrence.
    • Simon helped us rebuild the damaged LEN OL QPD stage and Terrence reinstalled it. We removed a C-clamp that we had been using to immobilize the breadboard because it interfered with the QPD stage, and replaced it with a more elegant solution using a dog clamp underneath.
    • We noticed that the BS IP had fallen over in +L at some time shortly before Nakano-san aligned the optic on 3/18. Terrence tried to recenter it but it was unstable. We decided to remove the tank lid one more time and remove some arc weights. The IP frequency had been 39 mHz the last time it was measurable, and we increased it to a much-safer 80 mHz by removing 9 kg. We believe we were able to recover Nakano-san's alignment fairly closely.
    • Terrence then recalibrated and diagonalized both the TILT and LEN OL.
  • SR2
    • Terrence recalibrated the OL.
  • SR3
    • Mark pulled out unused cables leading into the SR3 cleanbooth.
  • SRM
    • Terrence set up the SRM Guardian.
  • Etc/All
    • Mark did an audit of the OL whitening/dewhitening system and fixed a bunch of problems: the SRM chassis was the wrong type, with no actual whitening card; SR2 and SRM needed whitening filters turned on; BS LEN needed the dewhitening turned on; SR2, SR3 and SRM needed dewhitening filters installed and turned on; SRM needed more gain.
    • Terrence weeded out a minor error from his OL diagonalization scheme and got L, T and Y independent at the 1% level for SR2 and SRM. He will do SR3 next.
    • Fabian measured the gain resistor values and other settings of the LVDT drivers, in case a card or chassis fails and we have to approximate the original state without the chance to recalibrate from scratch.
    • Fabian monitored the pumpdown.

Plan for week of 3/25

  • Mark, Fabian, Terrence at Kamioka Mon-Thu.
  • Assist with alignment.
  • Work on Type B paper.
  • Tidy up.
    • Throw out foil and other garbage.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.
    • Return all unused cables to tent.
    • Tidy up cables in rear of SR2 rack.

Vacation/Travel Info

  • Enzo's final vacation till 3/29.
  • Terrence's last day for now, 3/29.
  • Mark compensation day for 3/21: 3/29.
  • Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's final day ≈6/28 (TBD).