Line 2: Line 2:
Line 6: Line 5:
==== Report for week of 10/29 ====
 * SRM
  * Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
  * Fabian and Hirata-san finished the in-vacuum cabling.
  * Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
  * We're now ready for final tests of the SF/... items and initial tests of the PI items.
  * Enzo and Fujii-kun built three geophones for SRM.
  * Mark worked on the height budget.
 * SR2
  * Enzo experimented with [[http://www2.mpq.mpg.de/~ros/geo600_docu/soft/liso/manual.pdf|LISO]] (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)
 
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
==== Report for the week of 2/25 ====
Line 22: Line 7:
==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
 * Fabian monitored suspensions during the vent.
 * Terrence and Mark made lots of changes to the Guardians and RTMs:
  * Added UI to take snapshots with ALIGNED/MISALIGNED channels (for late use by Guardian).
  * Changed "IM1" and "IM2" in channel names to "IMV" and "IMH"; also "DIO" and "BO" -> "BIO".
  * Created library blocks for BIO and made all the Type B models use them.
  * Tweaked the control topology to be more LIGO-style: the error signal for DC control is sensor-setpoint (not setpoint-sensor as in many controls textbooks); the input to the damping block is the uninverted sensor signal(s); there is a hard-wired -1 after the damping block representing default negative gain.
 * Fabian went inside the SRM chamber and diagnosed the problem that had appeared shortly before vent. It turned out to be yaw of the IP causing a payload cable to touch. He fixed it with the F0 yaw stepper. (He had tried this earlier without success but it turned out the problem was another dead output on the stepper driver.)
 * Terrence traced the geophone issue to a group of dead channels (#20-23) on the AA chassis. We tried replacing the chassis and it fixed not only the geophone issue but an issue in the TILT OL path (#24-27) that we had planned to debug next.
 * We retested the BIO for stepper remote enable system and this time it was working (probably due to the refactoring of the BIO stuff in the model and/or all the restarts).
 * We rebuilt all the IOP models after removing an unneeded ADC1 block (corresponding to hardware that Yoshizawa-san had removed).
 * Enzo and Terrence wrote Python scripts to automate the process of adapting the control filters to the new topology (where the DAMP and DCCTRL functions are in parallel instead of series).
==== Plan for week of 3/4 ====
 * Enzo at Mitaka.
 * Mark, Fabian Mon-Wed (Thu is farewell party).
 * Final tweaks of SRM?
 * Monitor (re-)pumpdown.
 * Tests of new Guardian.
 * Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
 * Continue monitoring SRM yaw drift.
 * Setup SRM and SR3 LEN OLs.
 * Work on Type B paper.
Line 27: Line 29:
==== Plan for week of 11/19 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo and Fabian at Kamioka Mon-Thu.
 * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
===== SRM =====
 * Go/no-go test of all electronics items, especially SF/... section.
 * Finish vertical height check and adjust SF trim mass as required.
 * Unlock IP and center roughly.
 * Check/adjust alignment of SS.
 * Calibrate IP LVDTs.
 * Add arc weights and geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Disconnect cables at feedthroughs, lock suspension.
 * Crane into tank.
===== SR2 =====
 * Assist MIF team with pico cables and LBB breadboard ballast.
 * Install SR2 OL pillar and shelf (with AOL supervision)?

==== Plan for week of 11/26 ====
 * Move SRM in-air cables over to tank.
 * Remove First Contact.
 * Unlock and align SRM.
 * Hook and roughly ballast LBB.

==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.

==== Vacation/Event Info ====
 * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).
==== Plan for week of 3/11 =====
 * Mark at Kamioka full week?
 * Enzo at Kamioka Mon, Tue, then JPS.
 *
==== Vacation/Travel Info ====
 * Enzo vacation, 3/5 and 3/6.
 * Enzo et al. Farewell Party, 3/7.
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 2/25

  • Fabian monitored suspensions during the vent.
  • Terrence and Mark made lots of changes to the Guardians and RTMs:
    • Added UI to take snapshots with ALIGNED/MISALIGNED channels (for late use by Guardian).
    • Changed "IM1" and "IM2" in channel names to "IMV" and "IMH"; also "DIO" and "BO" -> "BIO".

    • Created library blocks for BIO and made all the Type B models use them.
    • Tweaked the control topology to be more LIGO-style: the error signal for DC control is sensor-setpoint (not setpoint-sensor as in many controls textbooks); the input to the damping block is the uninverted sensor signal(s); there is a hard-wired -1 after the damping block representing default negative gain.
  • Fabian went inside the SRM chamber and diagnosed the problem that had appeared shortly before vent. It turned out to be yaw of the IP causing a payload cable to touch. He fixed it with the F0 yaw stepper. (He had tried this earlier without success but it turned out the problem was another dead output on the stepper driver.)
  • Terrence traced the geophone issue to a group of dead channels (#20-23) on the AA chassis. We tried replacing the chassis and it fixed not only the geophone issue but an issue in the TILT OL path (#24-27) that we had planned to debug next.
  • We retested the BIO for stepper remote enable system and this time it was working (probably due to the refactoring of the BIO stuff in the model and/or all the restarts).
  • We rebuilt all the IOP models after removing an unneeded ADC1 block (corresponding to hardware that Yoshizawa-san had removed).
  • Enzo and Terrence wrote Python scripts to automate the process of adapting the control filters to the new topology (where the DAMP and DCCTRL functions are in parallel instead of series).

Plan for week of 3/4

  • Enzo at Mitaka.
  • Mark, Fabian Mon-Wed (Thu is farewell party).
  • Final tweaks of SRM?
  • Monitor (re-)pumpdown.
  • Tests of new Guardian.
  • Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
  • Continue monitoring SRM yaw drift.
  • Setup SRM and SR3 LEN OLs.
  • Work on Type B paper.

==== Plan for week of 3/11 =====

  • Mark at Kamioka full week?
  • Enzo at Kamioka Mon, Tue, then JPS.

Vacation/Travel Info

  • Enzo vacation, 3/5 and 3/6.
  • Enzo et al. Farewell Party, 3/7.
  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.