Line 5: Line 5:
 * Type B Past Week Summary
  * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
  * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]).
  * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease.
  * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
  * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
  * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
  * Fabian did more pre-assembly of the RM/IM/IRM.
  * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
  * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
  * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
  * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * To-do list for Fabian/Hirata-san during Mark's vacation
   * Finish assembly of BS IM, RM and IRM (Fabian).
   * Weigh IM/RM/IRM (Fabian, Hirata)
   * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
   * Analyze geophone data (Mark, Shoda)
   * Remove glue from dummy BS face (Fabian).
   * Remove prism from dummy BS (Hirose, Fabian?)
   * Reglue flags and prisms (Tatsumi, Fabian)
   * Buy wire for BS and RM (Hirata)
   * Clean wire for BS and RM (Hirata)
   * Do fit/function test of winches (Fabian/Hirata)
   * Ship winches to Kamioka (Hirata/Fabian)
   * Work on BS simulation (Fabian)
   * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
   * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
   * Write more of payload assembly procedure (Fabian)
   * Write more of main assembly procedure (Mark)
  * Longer term to-do list
   * Do BS Simulink model (Mark, Kokeyama)
   * Do 2D drawings of SR2 parts (Hirata)
   * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
   * Order SRM/PRM parts (Hirata/Shoda)
   * Order SRx fasteners (Hirata)
   * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Past week report ====
 * Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen.
 * Enzo and Mark did a new overview screen for the BS.
 * Enzo added DIO cards to the rack and connected them to the coil drivers.
 * Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range.
 * Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring.
 * Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime.


==== Plan for week of 12/25 ====
 * Power outage 12/25.
 * Mark, Enzo, Fabian vacation
 * Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD.
 * Recover after power outage.
 * Create SR2 real-time model.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
 * Weigh IM (per Fabian's note in the paper log).
 * Remove L-brackets from bars on IM ring - send for cleaning/remachining.
 * Setup OL for checking pitch of SR.
 * Wipe/blow dust off SR2 frame.
 * Crane IM into frame.

==== Plan for week of 1/9 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Enzo 1/30-2/19

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen.
  • Enzo and Mark did a new overview screen for the BS.
  • Enzo added DIO cards to the rack and connected them to the coil drivers.
  • Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range.
  • Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring.
  • Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime.

Plan for week of 12/25

  • Power outage 12/25.
  • Mark, Enzo, Fabian vacation
  • Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD.
  • Recover after power outage.
  • Create SR2 real-time model.
  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
  • Weigh IM (per Fabian's note in the paper log).
  • Remove L-brackets from bars on IM ring - send for cleaning/remachining.
  • Setup OL for checking pitch of SR.
  • Wipe/blow dust off SR2 frame.
  • Crane IM into frame.

Plan for week of 1/9

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Enzo 1/30-2/19

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)