Line 5: Line 5:
 * Type B Past Week Summary
  * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
  * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]).
  * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease.
  * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
  * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
  * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
  * Fabian did more pre-assembly of the RM/IM/IRM.
  * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
  * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
  * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
  * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * To-do list for Fabian/Hirata-san during Mark's vacation
   * Finish assembly of BS IM, RM and IRM (Fabian).
   * Weigh IM/RM/IRM (Fabian, Hirata)
   * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
   * Analyze geophone data (Mark, Shoda)
   * Remove glue from dummy BS face (Fabian).
   * Remove prism from dummy BS (Hirose, Fabian?)
   * Reglue flags and prisms (Tatsumi, Fabian)
   * Buy wire for BS and RM (Hirata)
   * Clean wire for BS and RM (Hirata)
   * Do fit/function test of winches (Fabian/Hirata)
   * Ship winches to Kamioka (Hirata/Fabian)
   * Work on BS simulation (Fabian)
   * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
   * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
   * Write more of payload assembly procedure (Fabian)
   * Write more of main assembly procedure (Mark)
  * Longer term to-do list
   * Do BS Simulink model (Mark, Kokeyama)
   * Do 2D drawings of SR2 parts (Hirata)
   * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
   * Order SRM/PRM parts (Hirata/Shoda)
   * Order SRx fasteners (Hirata)
   * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for week of 7/9 ====
 * We cleaned up after the heavy rain. There was no significant damage but some cardboard boxes of parts got wet and the contents needed to be moved to other containers and the boxes discarded. Water collected on the SR2 crane slot cover and had to be vacuumed away before the cover could be opened. A new section of corrugated roof was installed to minimize the problem for the future.
 * Enzo and team got all of the in-vacuum and in-air cables for the SF/... and PI properly routed and tested except (so far) for the geophones.
 * Hirata-san and team finished tuning of the F0 for SR2 and moved the PI into the SR2 cleanbooth. It turns out to be about 8 kg weaker than for SR3, whereas the SR2 chain is only 3 kg lighter, so we will have to do some combination of decompression, removing Cu segments and using a stronger CuBe spring (e.g., a Type A F0 FR blade instead of the F2 one in SR3). We closed the floor in the SRM area for safety, but we will probably reopen it as soon as next week for the SRM F0 build.
 * Hirata-san opened the SR3 tank, craned the LBB damper ring sandwich up to the top of the tank and suspended it.
 * Enzo and team corrected a lot of flipped connections on the SR3 PI LVDTs (primary<->secondary on the horizontal, primary<->actuation on the F0).
 * We added the arc weights and geophones and re-centered the IP. It seems stable and very soft, which is good.

==== Plan for week of 7/9 ====
==== Plan for week of 7/16 ====
 * Monday 7/16 is Sea Day.
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.
===== Main Sequence =====
 * Check/restore alignment of payload, especially optic pitch.
 * Testing, TFs.
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.

===== F0/LBB Stuff =====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/9

  • We cleaned up after the heavy rain. There was no significant damage but some cardboard boxes of parts got wet and the contents needed to be moved to other containers and the boxes discarded. Water collected on the SR2 crane slot cover and had to be vacuumed away before the cover could be opened. A new section of corrugated roof was installed to minimize the problem for the future.
  • Enzo and team got all of the in-vacuum and in-air cables for the SF/... and PI properly routed and tested except (so far) for the geophones.
  • Hirata-san and team finished tuning of the F0 for SR2 and moved the PI into the SR2 cleanbooth. It turns out to be about 8 kg weaker than for SR3, whereas the SR2 chain is only 3 kg lighter, so we will have to do some combination of decompression, removing Cu segments and using a stronger CuBe spring (e.g., a Type A F0 FR blade instead of the F2 one in SR3). We closed the floor in the SRM area for safety, but we will probably reopen it as soon as next week for the SRM F0 build.

  • Hirata-san opened the SR3 tank, craned the LBB damper ring sandwich up to the top of the tank and suspended it.
  • Enzo and team corrected a lot of flipped connections on the SR3 PI LVDTs (primary<->secondary on the horizontal, primary<->actuation on the F0).

  • We added the arc weights and geophones and re-centered the IP. It seems stable and very soft, which is good.

Plan for week of 7/9

Plan for week of 7/16

  • Monday 7/16 is Sea Day.
  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.

Main Sequence
  • Check/restore alignment of payload, especially optic pitch.
  • Testing, TFs.
  • Lock suspension.
  • Crane into tank.
  • Unlock suspension.
  • Rearrange cables.
  • Test.

F0/LBB Stuff
  • Install correct IP in PI #2.
  • Crane PI #2 to second floor.
  • Rebuild top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.