* Type B Past Week Summary * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more. * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]). * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease. * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it. * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber. * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working. * Fabian did more pre-assembly of the RM/IM/IRM. * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags. * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank. * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well. * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts - RECEIVED. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list for Fabian/Hirata-san during Mark's vacation * Finish assembly of BS IM, RM and IRM (Fabian). * Weigh IM/RM/IRM (Fabian, Hirata) * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Mark, Shoda) * Remove glue from dummy BS face (Fabian). * Remove prism from dummy BS (Hirose, Fabian?) * Reglue flags and prisms (Tatsumi, Fabian) * Buy wire for BS and RM (Hirata) * Clean wire for BS and RM (Hirata) * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) * Apply vacuum grease to jacks for BS assembly frame (Takahashi) * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
=== Type B (Mark) === ==== Report for week of 7/23 ==== * We finished adding cable clamps to the SR2 PI and SF. * We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF. * We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments. * We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side. * We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.) * We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution. * With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters. * Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces. * Mark did inventory of the BIO stuff for the WD and of the OL parts. ==== Plan for week of 7/30 ==== * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon. ===== SR3 ===== * Finalize optic pitch, OSEM alignment. * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only). * Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator). ===== SR2 ===== * Fix issue with PI/SS/chain alignment. * Put magnets on SR damper ring (2 Cu segment pattern). * Remove PI-SF rod temporarily, install Cu segments and damper ring. * Do vertical height budget; choose optimum F0 keystone height. * Add estimated final ballast mass. * Do PI cable routing. * Adjust ballast/trim mass, with reserve for cables. ===== SRM ===== * Set up filter tuning area. * Tune F0 for SRM. * Add LBB blade units, cable clamps etc. * Check PI coil connections, IP LVDT magnets. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== * Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 7/23
- We finished adding cable clamps to the SR2 PI and SF.
- We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF.
We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments.
- We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side.
- We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.)
- We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution.
- With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters.
- Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces.
- Mark did inventory of the BIO stuff for the WD and of the OL parts.
Plan for week of 7/30
- Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
- Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.
SR3
- Finalize optic pitch, OSEM alignment.
- Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
- Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator).
SR2
- Fix issue with PI/SS/chain alignment.
- Put magnets on SR damper ring (2 Cu segment pattern).
- Remove PI-SF rod temporarily, install Cu segments and damper ring.
- Do vertical height budget; choose optimum F0 keystone height.
- Add estimated final ballast mass.
- Do PI cable routing.
- Adjust ballast/trim mass, with reserve for cables.
SRM
- Set up filter tuning area.
- Tune F0 for SRM.
- Add LBB blade units, cable clamps etc.
- Check PI coil connections, IP LVDT magnets.
To-Do Lists, Schedule
Vacation Info
- Terrence: 8/24-26 f2f, then returns to Hong Kong.
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.