 * Type B Past Week Summary
  * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
  * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]).
  * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease.
  * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
  * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
  * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
  * Fabian did more pre-assembly of the RM/IM/IRM.
  * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
  * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
  * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
  * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * To-do list for Fabian/Hirata-san during Mark's vacation
   * Finish assembly of BS IM, RM and IRM (Fabian).
   * Weigh IM/RM/IRM (Fabian, Hirata)
   * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
   * Analyze geophone data (Mark, Shoda)
   * Remove glue from dummy BS face (Fabian).
   * Remove prism from dummy BS (Hirose, Fabian?)
   * Reglue flags and prisms (Tatsumi, Fabian)
   * Buy wire for BS and RM (Hirata)
   * Clean wire for BS and RM (Hirata)
   * Do fit/function test of winches (Fabian/Hirata)
   * Ship winches to Kamioka (Hirata/Fabian)
   * Work on BS simulation (Fabian)
   * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
   * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
   * Write more of payload assembly procedure (Fabian)
   * Write more of main assembly procedure (Mark)
  * Longer term to-do list
   * Do BS Simulink model (Mark, Kokeyama)
   * Do 2D drawings of SR2 parts (Hirata)
   * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
   * Order SRM/PRM parts (Hirata/Shoda)
   * Order SRx fasteners (Hirata)
   * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for week of 7/30 ====
 * We set up an OL outside the tank and checked the SR3 pitch - it was OK.
 * We ran power to the SR3 pico and stepper drivers and tested them.
 * We tried to offload a 700 µm discrepancy between the BF GAS zero position and the IM-V zero position but ended up scrambling the IRM-IM alignment, probably through sending a command to the wrong pico driver. We mostly fixed the BF/IRM pitch/roll, but we have some more work to do to fix the IM/RM/TM pitch/roll.
 * We debugged a problem with the SR2 alignment - the chain was offset by about 5 mm to +T, leading to fouling at the IM and RM levels. Some 2 mm of the offset was due to the F0 keystone being off center, apparently due to some combination of different-strength blades and the CuBe auxiliary spring, but the rest is a mystery.
 * We fixed a problem with the levelness of the PI due to the feet of the IP being set at uneven heights into the PI weldment, and it got the IP very closed to centered but it didn't fix the fouling problem.
 * We eventually fixed the fouling by setting the security structure at a slight angle so it remains slightly off at the SF level but is good at the bottom.
 * We installed the SR2 SF damper Cu segments and magnet ring.
 * Enzo and team debugged a malfunctioning bit in the SR3 IP BIO which turned out to be a defective 37-pin gender changer.

==== Plan for week of 8/6 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Do TFs with temporary OL.
 * Install final OL.
 * Hook LBB, add ballast mass.

===== SR2 =====
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 
===== SRM =====
 * Assemble metal mass.
 * Glue prisms, flags.
 * Reconfigure, align assembly frame.
 * Tune F0 for SRM.
 * Add LBB blade units, cable clamps etc.
 * Check PI coil connections, IP LVDT magnets.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/30

  • We set up an OL outside the tank and checked the SR3 pitch - it was OK.
  • We ran power to the SR3 pico and stepper drivers and tested them.
  • We tried to offload a 700 µm discrepancy between the BF GAS zero position and the IM-V zero position but ended up scrambling the IRM-IM alignment, probably through sending a command to the wrong pico driver. We mostly fixed the BF/IRM pitch/roll, but we have some more work to do to fix the IM/RM/TM pitch/roll.
  • We debugged a problem with the SR2 alignment - the chain was offset by about 5 mm to +T, leading to fouling at the IM and RM levels. Some 2 mm of the offset was due to the F0 keystone being off center, apparently due to some combination of different-strength blades and the CuBe auxiliary spring, but the rest is a mystery.

  • We fixed a problem with the levelness of the PI due to the feet of the IP being set at uneven heights into the PI weldment, and it got the IP very closed to centered but it didn't fix the fouling problem.
  • We eventually fixed the fouling by setting the security structure at a slight angle so it remains slightly off at the SF level but is good at the bottom.
  • We installed the SR2 SF damper Cu segments and magnet ring.
  • Enzo and team debugged a malfunctioning bit in the SR3 IP BIO which turned out to be a defective 37-pin gender changer.

Plan for week of 8/6

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

SR3
  • Finalize optic pitch, OSEM alignment.
  • Do TFs with temporary OL.
  • Install final OL.
  • Hook LBB, add ballast mass.

SR2
  • Add estimated final ballast mass.
  • Do PI cable routing.
  • Adjust ballast/trim mass, with reserve for cables.

SRM
  • Assemble metal mass.
  • Glue prisms, flags.
  • Reconfigure, align assembly frame.
  • Tune F0 for SRM.
  • Add LBB blade units, cable clamps etc.
  • Check PI coil connections, IP LVDT magnets.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.