* Type B Past Week Summary * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more. * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]). * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease. * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it. * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber. * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working. * Fabian did more pre-assembly of the RM/IM/IRM. * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags. * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank. * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well. * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts - RECEIVED. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list for Fabian/Hirata-san during Mark's vacation * Finish assembly of BS IM, RM and IRM (Fabian). * Weigh IM/RM/IRM (Fabian, Hirata) * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Mark, Shoda) * Remove glue from dummy BS face (Fabian). * Remove prism from dummy BS (Hirose, Fabian?) * Reglue flags and prisms (Tatsumi, Fabian) * Buy wire for BS and RM (Hirata) * Clean wire for BS and RM (Hirata) * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) * Apply vacuum grease to jacks for BS assembly frame (Takahashi) * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
=== Type B (Mark) === ==== Report for week of 9/10 ==== * We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank. * We checked all the motors, like: ** the IM picos, BF picos. * We checked the BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod). * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains. * We reset the IP FRs to midrange. * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure. * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs. * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage. === Type B (Mark) === ==== Report for week of 9/3 ==== * We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected. * We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables. * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains. * We reset the IP FRs to midrange. * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure. * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs. * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage. ==== Plan for week of 9/10 ==== * Monday 9/10 is scheduled power outage. * Mark in US (job interview). * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri. * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation. ===== Etc ===== * Recover from power outage. ===== SR2 ===== * Calibrate F0 LVDTs. * Calibrate IP LVDTs. * Cable geophones and any other remaining PI items. * Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables). * Do basic go/no-go test of electronic items. * Check SF keystone height and offload with FR as necessary. * Adjust ballast/trim mass of SF, with reserve for yaw stepper. * Set SF damper magnet ring height. * Check/tweak optic pitch. * TFs. ==== Plan for week of 9/17 ==== * Monday 9/17 is holiday (Respect for the Aged Day). * Enzo on vacation. * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. ===== SR2 ===== * Crane SR2 into tank. * Move SR2 in-air cables. * Remove First Contact. * Unlock and realign suspension. ===== SRM ===== * Set pitch of SRM and RM, tighten clamps, remove winch system. * Weigh IM/... section. * Build up SS to BF level. * Add BF. ==== Plan for week of 9/24 ==== * Monday 9/24 is holiday (Autumn Equinox). * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. * Suspend IM and tweak height/balance. ===== SRM ===== * Cable/test BF. * Install IRM. * Install/cable/test IM OSEMs. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark: 9/10-14 (job interview in US). * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 9/10
- We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
- We checked all the motors, like:
- * the IM picos, BF picos.
- We checked the BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
- We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
- We reset the IP FRs to midrange.
- We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
- We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
- We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.
Type B (Mark)
Report for week of 9/3
- We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
- We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
- We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
- We reset the IP FRs to midrange.
- We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
- We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
- We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.
Plan for week of 9/10
- Monday 9/10 is scheduled power outage.
- Mark in US (job interview).
- Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
- Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
Etc
- Recover from power outage.
SR2
- Calibrate F0 LVDTs.
- Calibrate IP LVDTs.
- Cable geophones and any other remaining PI items.
- Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
- Do basic go/no-go test of electronic items.
- Check SF keystone height and offload with FR as necessary.
- Adjust ballast/trim mass of SF, with reserve for yaw stepper.
- Set SF damper magnet ring height.
- Check/tweak optic pitch.
- TFs.
Plan for week of 9/17
- Monday 9/17 is holiday (Respect for the Aged Day).
- Enzo on vacation.
- Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
SR2
- Crane SR2 into tank.
- Move SR2 in-air cables.
- Remove First Contact.
- Unlock and realign suspension.
SRM
- Set pitch of SRM and RM, tighten clamps, remove winch system.
- Weigh IM/... section.
- Build up SS to BF level.
- Add BF.
Plan for week of 9/24
- Monday 9/24 is holiday (Autumn Equinox).
- Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
- Suspend IM and tweak height/balance.
SRM
- Cable/test BF.
- Install IRM.
- Install/cable/test IM OSEMs.
To-Do Lists, Schedule
Vacation Info
- Mark: 9/10-14 (job interview in US).
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.