Differences between revisions 35 and 53 (spanning 18 versions)
Revision 35 as of 2016-07-07 15:10:05
Size: 3781
Editor: MarkBarton
Comment:
Revision 53 as of 2016-08-11 15:39:22
Size: 4142
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
  * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]).
  * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease.
  * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
  * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
  * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
  * Fabian did more pre-assembly of the RM/IM/IRM.
  * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
  * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
  * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
  * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Mark, Fabian and Hirata-san retrieved the dummy BS and mirror box from Kashiwa.
  * Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
  * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Fabian worked on the payload assembly procedure.
  * Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
 
Line 18: Line 19:
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
Line 21: Line 20:
   * Akutsu-san is working to get wide-mouth OSEMs    * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
Line 24: Line 23:
  * SR machining test ongoing.
Line 27: Line 25:
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
Line 31: Line 27:
  * To-do list for Fabian/Hirata-san during Mark's vacation
   * Finish assembly of BS IM, RM and IRM (Fabian).
   * Weigh IM/RM/IRM (Fabian, Hirata)
   * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
   * Analyze geophone data (Mark, Shoda)
   * Remove glue from dummy BS face (Fabian).
   * Remove prism from dummy BS (Hirose, Fabian?)
   * Reglue flags and prisms (Tatsumi, Fabian)
   * Buy wire for BS and RM (Hirata)
   * Clean wire for BS and RM (Hirata)
   * Do fit/function test of winches (Fabian/Hirata)
   * Ship winches to Kamioka (Hirata/Fabian)
   * Work on BS simulation (Fabian)
   * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
   * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
   * Write more of payload assembly procedure (Fabian)
   * Write more of main assembly procedure (Mark)
  * Longer term to-do list
   * Do BS Simulink model (Mark, Kokeyama)
   * Do 2D drawings of SR2 parts (Hirata)
   * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
   * Order SRM/PRM parts (Hirata/Shoda)
   * Order SRx fasteners (Hirata)
   * Check SR RM machining test progress (Hirata)
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
    • Mark wrote up the gluing procedure as a new document E1605505. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)

    • Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
    • The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
    • Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
    • Mark, Fabian and Hirata-san retrieved the dummy BS and mirror box from Kashiwa.
    • Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
    • Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
    • Fabian worked on the payload assembly procedure.
    • Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
    • Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
  • Type B ongoing issues
    • OSEMs
      • Akutsu-san is working to get wide-mouth OSEMs (2 assembled; another few were assembled and a batch of 7 were washed.

    • Longer cables for BF->PI and SF->PI.

      • Connectors RECEIVED, cables being made.
    • Lower breadboard stuff
      • Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
    • Documents
  • To-do list during Mark's vacation
    • Weigh IM/RM/IRM (Fabian, Hirata) - DONE
      • New trim mass - ORDERED.
    • Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
    • Analyze geophone data (Fabian/Shoda) - DONE.
    • Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
    • Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
    • Clean wire for BS and RM (Hirata) - DONE
    • Get new winch parts for new wire diameters - ORDERED, expected 8/5.
    • Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
    • Ship winches to Kamioka (Hirata/Fabian)
    • Work on BS simulation (Fabian)
    • Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of main assembly procedure (Mark) - ONGOING
  • Longer term to-do list
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)