Line 5: Line 5:
 * Type B Past Week Summary
  * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
  * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]).
  * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease.
  * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
  * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
  * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
  * Fabian did more pre-assembly of the RM/IM/IRM.
  * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
  * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
  * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
  * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi)
  * Finish assembly of BS IM, RM and IRM (Fabian).
  * Weigh IM/RM/IRM (Fabian, Hirata)
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Mark, Shoda)
  * Remove glue from dummy BS face (Fabian)
  * Remove prism from dummy BS (Hirose, Fabian?)
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata)
  * Clean wire for BS and RM (Hirata)
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
  * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
 * Activity report for weeks of 12/26 and 1/2

  * Hirata-san:
   * Modified parts list and screw list for payload.
   * Sent lists to i-ject and asked for preliminary quotes.
   * Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
   * For Type Bp:
    * Searched for PR gluing jigs.
    * Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
    * Washed additional masses for IM and sent them to Kamioka.
   * For others:
    * Washed IMMT plate and sent them to Kamioka.
  * Fabian
   * Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
   * Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
   * Worked on design of additional trim mass (≈18 kg) for the BS BF.
   * Checked assembly PR/SR drawings. There were a few corrections/changes.
   * Checked fastener list. There were few corrections/changes.
   * Checked component list for the manufacture order. There were few corrections/changes.
   * Helped in searching for the PR gluing jigs.
  * Mark
   * Started design of SR assembly frame (but then passed it to Fabian).
   * Worked on task lists and schedule.
 * Plan for 1/10-13
  * Mark and Fabian at Kamioka:
   * Finish rebalance of IM
   * Reinstall IRM, adjust OSEMs
   * Replace broken Type 3 cable.
   * Do TFs from IRM OSEMs to IRM and IM OSEMs.
   * Cable up and test BF LVDT and fishing rod (time permitting).
   * Disconnect BF and ship back to Mitaka (time permitting).
  * Hirata-san:
   * More SR procurement.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Activity report for weeks of 12/26 and 1/2
    • Hirata-san:
      • Modified parts list and screw list for payload.
      • Sent lists to i-ject and asked for preliminary quotes.
      • Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
      • For Type Bp:
        • Searched for PR gluing jigs.
        • Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
        • Washed additional masses for IM and sent them to Kamioka.
      • For others:
        • Washed IMMT plate and sent them to Kamioka.
    • Fabian
      • Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
      • Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
      • Worked on design of additional trim mass (≈18 kg) for the BS BF.
      • Checked assembly PR/SR drawings. There were a few corrections/changes.
      • Checked fastener list. There were few corrections/changes.
      • Checked component list for the manufacture order. There were few corrections/changes.
      • Helped in searching for the PR gluing jigs.
    • Mark
      • Started design of SR assembly frame (but then passed it to Fabian).
      • Worked on task lists and schedule.
  • Plan for 1/10-13
    • Mark and Fabian at Kamioka:
      • Finish rebalance of IM
      • Reinstall IRM, adjust OSEMs
      • Replace broken Type 3 cable.
      • Do TFs from IRM OSEMs to IRM and IM OSEMs.
      • Cable up and test BF LVDT and fishing rod (time permitting).
      • Disconnect BF and ship back to Mitaka (time permitting).
    • Hirata-san:
      • More SR procurement.