* Type B Past Week Summary * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more. * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]). * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease. * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it. * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber. * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working. * Fabian did more pre-assembly of the RM/IM/IRM. * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags. * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank. * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well. * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18. * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts - RECEIVED. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Apply grease to jacks for assembly frame (Takahashi) * Finish assembly of BS IM, RM and IRM (Fabian). * Weigh IM/RM/IRM (Fabian, Hirata) * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Mark, Shoda) * Remove glue from dummy BS face (Fabian) * Remove prism from dummy BS (Hirose, Fabian?) * Reglue flags and prisms (Tatsumi, Fabian) * Buy wire for BS and RM (Hirata) * Clean wire for BS and RM (Hirata) * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) * Apply vacuum grease to jacks for BS assembly frame (Takahashi) * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
=== Type B (Mark) === ==== Past week report ==== * We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box. * Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.) * Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.) * Enzo found nearly all in-vacuum cables. * Enzo and Shoda-san got several more loops closed on the BS. * Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4). * Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them. * Hirata-san worked on SR procurement. * Hirata-san worked with Mirapro to get the SRM LBB installed in the tank. ==== Plan for week of 12/4 ==== * Mark at Kamioka. * Fabian at f2f satellite meeting Mon, then Kamioka. * Enzo at f2f then Mitaka. * Hirata-san at Kamioka Mon-Thu, Mitaka Fri. * Kozu-kun Thu only. * Mirror gluing. * IM assembly and pico test. ==== Plan for week of 12/11 * Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka. * Kozu-kun Mon-Thu only. * Assembly frame alignment and optical table centering. * Move trolley system from SR3. * OL setup. ==== Plan for week of 12/18 ==== * Shoda-san vacation * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed. ==== Vacation Info ==== * Mark 12/22-1/3 * Enzo TBD, probably 12/22-1/3 * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) * Shoda-san 12/18-21 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
- Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
- Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
- Enzo found nearly all in-vacuum cables.
- Enzo and Shoda-san got several more loops closed on the BS.
- Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
- Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
- Hirata-san worked on SR procurement.
- Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.
Plan for week of 12/4
- Mark at Kamioka.
- Fabian at f2f satellite meeting Mon, then Kamioka.
- Enzo at f2f then Mitaka.
- Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
- Kozu-kun Thu only.
- Mirror gluing.
- IM assembly and pico test.
==== Plan for week of 12/11
- Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
- Kozu-kun Mon-Thu only.
- Assembly frame alignment and optical table centering.
- Move trolley system from SR3.
- OL setup.
Plan for week of 12/18
- Shoda-san vacation
- Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Vacation Info
- Mark 12/22-1/3
- Enzo TBD, probably 12/22-1/3
- Fabian 12/22-1/5
- Hirata-san 12/21-22 (conference)
- Shoda-san 12/18-21