* Type B Past Week Summary * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more. * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]). * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease. * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it. * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber. * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working. * Fabian did more pre-assembly of the RM/IM/IRM. * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags. * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank. * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well. * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18. * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts - RECEIVED. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Apply grease to jacks for assembly frame (Takahashi) * Finish assembly of BS IM, RM and IRM (Fabian). * Weigh IM/RM/IRM (Fabian, Hirata) * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Mark, Shoda) * Remove glue from dummy BS face (Fabian) * Remove prism from dummy BS (Hirose, Fabian?) * Reglue flags and prisms (Tatsumi, Fabian) * Buy wire for BS and RM (Hirata) * Clean wire for BS and RM (Hirata) * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) * Apply vacuum grease to jacks for BS assembly frame (Takahashi) * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
=== Type B (Mark) === ==== Report for week of 1/29 ==== * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth. * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]). * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]). * We referred the BS OL. * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine. * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts. * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding. * Hirata-san * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop). ==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. * All others at Kamioka. * Make in-air pico adapter cables. * Test IM picos and BF yaw pico. * Test FR. * Calibrate LVDT. * Get screws for ballast mass from Takahashi-san. * Install ballast mass in BF. * Set up for F0 test. * Lower IM crossbars in SR3 assembly frame. * Open curtain on SR3 crane slot. * Set up dummy load (weight carrier, rods etc). * Do F0 test. * Bring in F0. * Hook up dummy load. * Adjust dummy load. ==== Plan for week of 2/5 ==== * Enzo on vacation; all others at Kamioka. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. ==== Plan for week of 2/12 ==== * Enzo on vacation; all others at Kamioka. ==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog 4058).
We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog 4061).
- We referred the BS OL.
- We removed the BS tank lid and inspected the BS top filter blades. They seemed fine.
- Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
- Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
- Hirata-san
- Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
Plan for week of 1/29
- Enzo at Mitaka 1/29 and most of 1/30, then vacation.
- Kozu-kun away.
- All others at Kamioka.
- Make in-air pico adapter cables.
- Test IM picos and BF yaw pico.
- Test FR.
- Calibrate LVDT.
- Get screws for ballast mass from Takahashi-san.
- Install ballast mass in BF.
- Set up for F0 test.
- Lower IM crossbars in SR3 assembly frame.
- Open curtain on SR3 crane slot.
- Set up dummy load (weight carrier, rods etc).
- Do F0 test.
- Bring in F0.
- Hook up dummy load.
- Adjust dummy load.
Plan for week of 2/5
- Enzo on vacation; all others at Kamioka.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Plan for week of 2/12
- Enzo on vacation; all others at Kamioka.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2