 * Type B Past Week Summary
  * Mark did a Type B schedule presentation at the Extended Chiefs Meeting. It was decided to order a second assembly frame so that the BS/SR2/SR3/SRM installations can overlap more.
  * Mark and Hirata-san helped Mirapro construct the assembly frame ([[https://goo.gl/photos/tVGoebw7FTRMAYB2A|photos]]).
  * Mark and Hirata-san took the jacks and adapter plates off the frame, and cleaned them to remove as much of the original grease as possible. Takahashi-san has offered to re-grease them with vacuum grease.
  * Mark and Hirata-san wiped down the assembly frame and put the clean bag on it.
  * Saito-san, Ohishi-san and several people from Mirapro adjusted the position of the BS chamber.
  * Mark plugged the geophones back into the PR2 rack and checked that the repaired cable was working.
  * Fabian did more pre-assembly of the RM/IM/IRM.
  * Takahashi-san ordered 10 mm diameter x 10 mm long magnets for the IM flags.
  * Mark inspected the SR2 section of the clean booth to see where SR2 assembly could be done. The slot in the ceiling for the crane runs in the ±X direction (at right angles to that for the BS), and there are suitable space on both the +X and the -X sides of the SR2 tank.
  * Hasegawa-san (of Hirose-san's lab) took delivery of the cup for removing the prisms on the dummy BS. It fits well.
  * Tatsumi-san ordered [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5357|modifications]] to the BS gluing jig to make it easier to remove the pieces holding the flags after the flags are attached. The parts are expected Fri 7/8. He also ordered more EP30, but this won't arrive until the week of 7/18.
 * Type B Past Week Summary - week of 8/8
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
  * Hirata-san measured another standard filter and cleaned various parts for people.
  * Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs.
  * Fabian worked on the payload assembly procedure.
 * Type B Past Week Summary - week of 8/15
  * Hirata-san shipped the fasteners to Kamioka, and they arrived Tuesday.
  * Hirata-san shipped a large load of Type A and Type B items, which Mark and Fabian received on Thursday 8/18.
  * Akutsu-san shipped the first 7 OSEMs.
  * Hirata-san and Ikenoue-san did a successful function test of the BS winches with the new clamp parts for the thicker wires.
  * Mark, Fabian and Zhao-kun did a major cleanup and reorganization of the BS clean booth at Kamioka, putting PR2 stuff in boxes, vacuuming and wiping, and making space.
  * Mark, Fabian and Zhao-kun set the crossbeams of the assembly frame to their correct positions and installed the EQ stop ring on top, ready to receive the IM. This is the first actual installation activity for Type B.
  *
Line 18: Line 23:
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Longer cables for BF->PI and SF->PI still not received, Takahashi-san to check status.
Line 25: Line 26:
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
Line 29: Line 28:
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi)
  * Finish assembly of BS IM, RM and IRM (Fabian).
  * Weigh IM/RM/IRM (Fabian, Hirata)
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Mark, Shoda)
  * Remove glue from dummy BS face (Fabian)
  * Remove prism from dummy BS (Hirose, Fabian?)
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata)
  * Clean wire for BS and RM (Hirata)
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
 * Longer term to-do list
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
Line 43: Line 33:
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
  * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
Line 50: Line 35:
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.   * Redesign SRx IM wire clamps for larger prisms, remachined RMs
Line 53: Line 38:
  * Check SR RM machining test progress (Hirata)
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary - week of 8/8
    • Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
    • Mark wrote up the gluing procedure as a new document E1605505. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)

    • Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
    • Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
    • Hirata-san measured another standard filter and cleaned various parts for people.
    • Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
    • Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs.
    • Fabian worked on the payload assembly procedure.
  • Type B Past Week Summary - week of 8/15
    • Hirata-san shipped the fasteners to Kamioka, and they arrived Tuesday.
    • Hirata-san shipped a large load of Type A and Type B items, which Mark and Fabian received on Thursday 8/18.
    • Akutsu-san shipped the first 7 OSEMs.
    • Hirata-san and Ikenoue-san did a successful function test of the BS winches with the new clamp parts for the thicker wires.
    • Mark, Fabian and Zhao-kun did a major cleanup and reorganization of the BS clean booth at Kamioka, putting PR2 stuff in boxes, vacuuming and wiping, and making space.
    • Mark, Fabian and Zhao-kun set the crossbeams of the assembly frame to their correct positions and installed the EQ stop ring on top, ready to receive the IM. This is the first actual installation activity for Type B.
  • Type B ongoing issues
    • Longer cables for BF->PI and SF->PI still not received, Takahashi-san to check status.

    • Lower breadboard stuff
      • Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
    • Documents
  • Longer term to-do list
    • Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of main assembly procedure (Mark) - ONGOING
    • Work on BS simulation (Fabian)
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)