Line 2: Line 2:
Line 6: Line 5:
==== Report for week of 12/17 ==== ==== Report for the week of 3/18 ====
Line 8: Line 7:
  * Miyakawa-san worked on the BS real-time model and the gain/offset settings for the F0 LVDTINF block were lost, so we reentered them and did a new safe.snap file.   * Terrence notice that one of the IP LVDTs was not working. We traced it to an unplugged cable, plugged it back in and screwed it together to prevent a recurrence.
  * Simon helped us rebuild the damaged LEN OL QPD stage and Terrence reinstalled it. We removed a C-clamp that we had been using to immobilize the breadboard because it interfered with the QPD stage, and replaced it with a more elegant solution using a dog clamp underneath.
  * We noticed that the BS IP had fallen over in +L at some time shortly before Nakano-san aligned the optic on 3/18. Terrence tried to recenter it but it was unstable. We decided to remove the tank lid one more time and remove some arc weights. The IP frequency had been 39 mHz the last time it was measurable, and we increased it to a much-safer 80 mHz by removing 9 kg. We believe we were able to recover Nakano-san's alignment fairly closely.
  * Terrence then recalibrated and diagonalized both the TILT and LEN OL.
 * SR2
  * Terrence recalibrated the OL.
 * SR3
  * Mark pulled out unused cables leading into the SR3 cleanbooth.
Line 10: Line 16:
  * We unlocked the IP adjusted the level with the jacks to center it. As hoped, this also improved the alignment of the chain insecurity structure and fixed a touching issue.
  * Hirata-san installed and cabled the new F0 yaw stepper. We had allowed plenty of reserve mass, so there was no problem getting back to nominal height of the keystone. [''As of Thursday afternoon, it had not yet been tested - UPDATE?'']
  * We found that the Nikhef method Fabian had used to tune the F0 LVDT driver gave an artificially narrow working range, so he retuned it with Enzo's method and recalibrated the LVDT.
  * Fabian did a vertical position survey with all the GAS filters at nominal and found the height of the RM above the SS bottom plate was about 2.5 mm lower than in the CAD. This is about what we expected from a chain 7 mm longer than CAD and and F0 keystone set to 5 mm higher than CAD. In future we can survey to either the optic or the security structure as convenient, and we are in the range where we should easily be able to match the correct beam height with the jacks under the PI.
  * We got two OL viewports for SRM from Akutsu-san, and will install them sometime in January, whenever we have a free moment. Akutsu-san pre-torqued the inner ring of screws around the glass, so we only need to torque the outer bolts.
  * We took transfer functions for the IM. All of them look good except IM-T. We will inspect the payload next week in case anything is touching or rubbing.
  * Hirata-san opened the +X door of the vacuum chamber for visual inspection. We closed it back and covered with tape a small gap at the door.
 * SR3
  * We also got a camera viewport for SR3 from Akutsu-san and will install it sometime in January.
  * Hirata-san installed and cabled the new F0 yaw stepper.
 * SR2
  * Enzo calibrated the SR2 OL. He noted that with the standard f=2500 mm collimator, the angular range was only about 100 µrad in pitch and 150 µrad in yaw, which is rather less than Enomoto-kun's preferred range of more like 400 µrad, so we borrowed f=1100 mm and f=3500 mm collimators to characterize. [''Enzo was going to do f=1100 mm and maybe f=3500 mm on Friday morning 12/21 - UPDATE?'']
  * Hirata-san installed and cabled the new F0 yaw stepper. We did not have enough reserve mass for SR2, so to save 300 g we had Mesco make a new, lighter top plate, and Hirata-san ultrasonically cleaned it. We were then able to get the desired F0 keystone height with about 200 g to spare.
  * The RM was touching the security structure due to a large yaw displacement. We were able to move it free by adjusting the cylinder with the spring and leaving the stepper motor in its nominal position. The f=1100 mm collimator was installed and the QPD was calibrated.
  * Terrence set up the SRM Guardian.
 * Etc/All
  * Mark did an audit of the OL whitening/dewhitening system and fixed a bunch of problems: the SRM chassis was the wrong type, with no actual whitening card; SR2 and SRM needed whitening filters turned on; BS LEN needed the dewhitening turned on; SR2, SR3 and SRM needed dewhitening filters installed and turned on; SRM needed more gain.
  * Terrence weeded out a minor error from his OL diagonalization scheme and got L, T and Y independent at the 1% level for SR2 and SRM. He will do SR3 next.
  * Fabian measured the gain resistor values and other settings of the LVDT drivers, in case a card or chassis fails and we have to approximate the original state without the chance to recalibrate from scratch.
  * Fabian monitored the pumpdown.
Line 25: Line 23:
---- /!\ '''Edit conflict - your version:''' ----
  * Hirata-san opened the +X door of the vacuum chamber so we could inspect the payload, especially the OSEMs. We closed it back and covered with tape a small gap at the door.
 * SR3
  * We also got a camera viewport for SR3 from Akutsu-san and will install it sometime in January.
  * Hirata-san installed and cabled the new F0 yaw stepper.
 * SR2
  * Enzo calibrated the SR2 OL. He noted that with the standard f=2500 mm collimator, the angular range was only about 100 µrad in pitch and 150 µrad in yaw, which is rather less than Enomoto-kun's preferred range of more like 400 µrad, so we borrowed f=1100 mm and f=3500 mm collimators to characterize. Enzo did f=1100 mm and will do f=3500 mm soon.]
  * Hirata-san installed and cabled the new F0 yaw stepper. We did not have enough reserve mass for SR2, so to save 300 g we had Mesco make a new, lighter top plate, and Hirata-san ultrasonically cleaned it. We were then able to get the desired F0 keystone height with about 200 g to spare.
  * After installing the yaw stepper, the RM was touching the security structure but we were able to move it free by adjusting the cylinder with the spring and leaving the stepper motor in its nominal position.
==== Plan for week of 3/25 ====
 * Mark, Fabian, Terrence at Kamioka Mon-Thu.
 * Assist with alignment.
 * Work on Type B paper.
 * Tidy up.
  * Throw out foil and other garbage.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.
  * Return all unused cables to tent.
  * Tidy up cables in rear of SR2 rack.
Line 35: Line 34:
---- /!\ '''End of edit conflict''' ----
 * Etc
  * Enzo did a historical survey of the temperature as the various suspensions were being built and concluded that ideal operating temperature would be 25°C in the BS/SR2 area and 24°C for SR3/SRM.
  * Mark wrote a bash script to log all the GAS filter heights and LVDT actuation offsets, and an Excel spreadsheet to analyze the data to get an overview of the heights of the suspensions and the amount of height adjustment being used. He also reviewed old TF data to get near-DC values for the effect of GAS actuation on GAS height. This uncovered a few issues with calibration settings (such as for BS F0) having been lost because they hadn't been recorded in a safe.snap file, which we fixed.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 12/17 ====
 * Final alignment of SRM payload, plus BF and SF GAS.
 * (Time permitting) unlocking/centering/tuning of IP.
 * Installation of Enomoto-kun's beam target on SRM (if available).
 * Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
 * Installation of viewports on SRM.

==== Plan for week of 12/24 ====
 * Mark and Hirata-san on holidays, Enzo at Mitaka, Fabian.

==== Plan for week of 1/7 ====
 * Make sure BS is floating, recenter OL to capture current yaw position.
 * Vent BS.
 * Inspect BS F0 blades for cracks.
 * Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.
 * Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
 * Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
 * Add more mass to IP to get lower frequency.
 * Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

==== Vacation/Etc Info ====
 * Mark: 12/24 - 1/4.
 * Hirata-san: 12/24 - 1/4.
 * Fabian: 12/31 - 1/4
 * Enzo: 12/31 - 1/4.
 * Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
 * Terrence: back at Kamioka from 1/7.
==== Vacation/Travel Info ====
 * Enzo's final vacation till 3/29.
 * Terrence's last day for now, 3/29.
 * Mark compensation day for 3/21: 3/29.
 * Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's final day ≈6/28 (TBD).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/18

  • BS
    • Terrence notice that one of the IP LVDTs was not working. We traced it to an unplugged cable, plugged it back in and screwed it together to prevent a recurrence.
    • Simon helped us rebuild the damaged LEN OL QPD stage and Terrence reinstalled it. We removed a C-clamp that we had been using to immobilize the breadboard because it interfered with the QPD stage, and replaced it with a more elegant solution using a dog clamp underneath.
    • We noticed that the BS IP had fallen over in +L at some time shortly before Nakano-san aligned the optic on 3/18. Terrence tried to recenter it but it was unstable. We decided to remove the tank lid one more time and remove some arc weights. The IP frequency had been 39 mHz the last time it was measurable, and we increased it to a much-safer 80 mHz by removing 9 kg. We believe we were able to recover Nakano-san's alignment fairly closely.
    • Terrence then recalibrated and diagonalized both the TILT and LEN OL.
  • SR2
    • Terrence recalibrated the OL.
  • SR3
    • Mark pulled out unused cables leading into the SR3 cleanbooth.
  • SRM
    • Terrence set up the SRM Guardian.
  • Etc/All
    • Mark did an audit of the OL whitening/dewhitening system and fixed a bunch of problems: the SRM chassis was the wrong type, with no actual whitening card; SR2 and SRM needed whitening filters turned on; BS LEN needed the dewhitening turned on; SR2, SR3 and SRM needed dewhitening filters installed and turned on; SRM needed more gain.
    • Terrence weeded out a minor error from his OL diagonalization scheme and got L, T and Y independent at the 1% level for SR2 and SRM. He will do SR3 next.
    • Fabian measured the gain resistor values and other settings of the LVDT drivers, in case a card or chassis fails and we have to approximate the original state without the chance to recalibrate from scratch.
    • Fabian monitored the pumpdown.

Plan for week of 3/25

  • Mark, Fabian, Terrence at Kamioka Mon-Thu.
  • Assist with alignment.
  • Work on Type B paper.
  • Tidy up.
    • Throw out foil and other garbage.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.
    • Return all unused cables to tent.
    • Tidy up cables in rear of SR2 rack.

Vacation/Travel Info

  • Enzo's final vacation till 3/29.
  • Terrence's last day for now, 3/29.
  • Mark compensation day for 3/21: 3/29.
  • Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's final day ≈6/28 (TBD).