Line 2: Line 2:
Line 6: Line 5:
==== Report for week of 12/17 ====
 * BS
  * We opened the top of the BS tank after the vent.
  * We inspected the BS F0 blades for cracks but still didn't find any.
  * We removed the arc weights and geophones, and added new longer studs for the arc weights and new cables for the geophones. We then put back the original arc weights and new geophones.
  * We measured the geometry of the various IP items to check the IP diagonalization matrices.
  * We installed the new double-sided F0 FR. We were not close to needing to add the optional !CuBe spring. Unfortunately the FR had rather less friction but still didn't work. After checking a bunch of possibilities and comparing against SRM (also non-working) and SR2/SR3 (working), we suspect the carriage may be assembled upside down, with the metal plate below and the PEEK plate above. We will try changing it next week.
 * We adjusted the F0 keystone trim mass and were able to get it to sit at CAD nominal height at nominal temperature (24.9°C) with mid-range FR and modest extra mass (413 g). Interestingly, we noticed that removing the arc weights and/or geophones reduced the load capacity by a few hundred grams.
 * We measured the total range of the IP FRs in steps and set them to mid-range in preparation for tuning the IP frequency and (re-)centering the IP.
 * SRM
  * We borrowed an LED from SR2 and set the pitch of the SRM optic.
  * We found the SRM front end had crashed and could not be properly reset by cycling the power from the web interface. Yamamoto-san eventually got it working for us, although it didn't seem to take more than restarting the user and IOP models.
  * We sealed and retested the new geophones originally intended for SRM, but decided to use them on BS instead.
  * We installed the two OL viewports. We also tried to install the camera viewport but we couldn't get the Cu gasket to sit in the recess, so we gave up and will probably reallocate the camera viewport to SR3 for now (where it will go on a different type of flange which we've had success with. Saito-san says that we can get help with the SRM flange from Mirapro on 1/28.
 * SR3
  * We opened the top of the tank briefly to inspect the configuration of the F0 FR, but didn't do any significant work.
  * Hirose-san inspected inside the bottom part of the chamber and found some dust, so he recommended we wipe with Vectra-Alpha wipes (IPA-resistant type) and IPA. he gave us a powerful LED flashlight array and asked us to use it to look for dust in all the chambers.
 * Etc
  * We gave Simon a list of items we still need for the SRM OL. He seemed to think that they should be in stock at Kamioka and will help us look for them next Tue 1/15.
  * Mark and Enzo booked flights for the KAGRA International Workshop.
  * Mark had to schedule a trip to Australia for the week of 1/21 to attend to family business.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
==== Report for the week of 3/11 ====
 * Fabian mostly helped Fujii-kun with the PRM.
 * Mark and Hirata-san debugged the BS:
  * We inspected the payload section and quickly found the problem: two RM EQ stops were touching, on the +L (-X,+Y) side at the top. This was probably because the stops had been adjusted with the IP unlocked and sitting a few mm to -L, whereas now we have the DCCTRL running and have been locking the IP at the LVDT zero. We drove the IP to L=+1.5 mm as a near-worst case, and backed off all the stops to give several mm of margin. Then we zeroed the IP pitch, roll and yaw with the picos.
  * We also opened the top of the BS and confirmed that the mechanical zero defined by the locking mechanism agreed with the LVDT zero. It was very close in L and T, but -728 µrad in Y, driven mostly by a -805 µm offset in H3. That much is probably not a dumb error but just a difference in technique among the three people using calipers to take data for the calibration.
  * We then prepared the BS for close-up:
   * We wiped and inspected the O-ring for the lid and replaced the lid.
   * We wiped all accessible surfaces in the lower half of the tank, rescued some dropped items (some PEEK tube and a small nut) and un-immobilized the LBB.
  * After all the above, the OL was a bit off-center but still on the QPD, and Nagano-san fairly quickly recovered the original alignment.
 * Terrence rebuilt the BS OL according to a new layout suggested by Simon, which avoids scrambling the pitch/yaw at the first steering mirror and greatly reduces the amount of diagonalization required.
 * Terrence noticed some anomalous cross coupling on the SR2 (but not the SR3) and we investigated.
  * We suspected it might be an odd position of the beam spot on the optic, so we took pictures through the camera and LED viewports of SR3, and opened the SR2 tank and used a white target, but the beam spots were in very similar positions - close to central vertically and about 3 cm to the left of center horizontally.
  * We suspected it might be something touching at the IRM (because the IM OSEM TFs were fine), so we checked using a stick mirror with the IP centered, but all EQ stops were well backed off.
  * We suspected it might be a ghost beam from the LEN/TILT beamsplitter (and one was clearly visible on the SR2 TILT QPD) so Terrence set up a beam block, which improved things slightly but not completely.
  * Finally Terrence discovered that the problem was mainly uneven sensitivities of the QPD quadrants, and devised a new calibration and diagonalization procedure which allowed for it.
 * Enzo and Terrence did a health check of the SRM and it was fine except for some apparent electrical noise around 240 Hz. They put in a notch filter to get rid of it for now.
Line 32: Line 22:
==== Plan for week of 1/7 ====
 * Make sure BS is floating, recenter OL to capture current yaw position.
 * Vent BS.
 * Inspect BS F0 blades for cracks.
 * Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.
 * Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
 * Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
 * Add more mass to IP to get lower frequency.
 * Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).
==== Plan for week of 3/11 ====
 * Mark at Kamioka full week.
 * Enzo at Kamioka Mon, Tue, then JPS.
 * Hirata-san at Kamioka from Monday lunchtime through Friday.
 * Fix BS.
 * Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
 * Continue monitoring SRM yaw drift.
 * More mode Q measurements.
 * Work on Type B paper.
Line 42: Line 32:
==== Vacation/Etc Info ====
 * Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
 * Terrence: back at Kamioka from 1/7.

==== Vacation/Travel Info ====
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/11

  • Fabian mostly helped Fujii-kun with the PRM.
  • Mark and Hirata-san debugged the BS:
    • We inspected the payload section and quickly found the problem: two RM EQ stops were touching, on the +L (-X,+Y) side at the top. This was probably because the stops had been adjusted with the IP unlocked and sitting a few mm to -L, whereas now we have the DCCTRL running and have been locking the IP at the LVDT zero. We drove the IP to L=+1.5 mm as a near-worst case, and backed off all the stops to give several mm of margin. Then we zeroed the IP pitch, roll and yaw with the picos.
    • We also opened the top of the BS and confirmed that the mechanical zero defined by the locking mechanism agreed with the LVDT zero. It was very close in L and T, but -728 µrad in Y, driven mostly by a -805 µm offset in H3. That much is probably not a dumb error but just a difference in technique among the three people using calipers to take data for the calibration.
    • We then prepared the BS for close-up:
      • We wiped and inspected the O-ring for the lid and replaced the lid.
      • We wiped all accessible surfaces in the lower half of the tank, rescued some dropped items (some PEEK tube and a small nut) and un-immobilized the LBB.
    • After all the above, the OL was a bit off-center but still on the QPD, and Nagano-san fairly quickly recovered the original alignment.
  • Terrence rebuilt the BS OL according to a new layout suggested by Simon, which avoids scrambling the pitch/yaw at the first steering mirror and greatly reduces the amount of diagonalization required.
  • Terrence noticed some anomalous cross coupling on the SR2 (but not the SR3) and we investigated.
    • We suspected it might be an odd position of the beam spot on the optic, so we took pictures through the camera and LED viewports of SR3, and opened the SR2 tank and used a white target, but the beam spots were in very similar positions - close to central vertically and about 3 cm to the left of center horizontally.
    • We suspected it might be something touching at the IRM (because the IM OSEM TFs were fine), so we checked using a stick mirror with the IP centered, but all EQ stops were well backed off.
    • We suspected it might be a ghost beam from the LEN/TILT beamsplitter (and one was clearly visible on the SR2 TILT QPD) so Terrence set up a beam block, which improved things slightly but not completely.
    • Finally Terrence discovered that the problem was mainly uneven sensitivities of the QPD quadrants, and devised a new calibration and diagonalization procedure which allowed for it.
  • Enzo and Terrence did a health check of the SRM and it was fine except for some apparent electrical noise around 240 Hz. They put in a notch filter to get rid of it for now.

Plan for week of 3/11

  • Mark at Kamioka full week.
  • Enzo at Kamioka Mon, Tue, then JPS.
  • Hirata-san at Kamioka from Monday lunchtime through Friday.
  • Fix BS.
  • Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
  • Continue monitoring SRM yaw drift.
  • More mode Q measurements.
  • Work on Type B paper.

Vacation/Travel Info

  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.