 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC.
  * Hirata-san ordered wire for the BS.
  * Fabian weighed the masses that he'd been constructing in the cleanroom and found a 600 g discrepancy from the Inventor.
  * Hirata-san ordered a medium-capacity scale to help check the masses of the parts.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi)
  * Finish assembly of BS IM, RM and IRM (Fabian).
  * Weigh IM/RM/IRM (Fabian, Hirata)
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Mark, Shoda)
  * Remove glue from dummy BS face (Fabian)
  * Remove prism from dummy BS (Hirose, Fabian?)
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata)
  * Clean wire for BS and RM (Hirata)
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
  * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
 * Activity report for weeks of 12/26 and 1/2

{{{
Dear Mark,

I did for Type-B as below,
・modified parts list and screw list for Payload.
・sent lists to i-ject and asked for quotes.
(But we need to send latest list again.)
・made drawings for some jigs and some parts for payload.

For PR
・searched glueing jigs.
・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
・washed additional masses for IM and sent them to Kamioka.

For others
・washed IMMT plate and send them to Kamioka.

Best regards,
Hirata
}}}
{{{
Hello,

Succinctly, it is as follows:

1. Mechanical design:

    a. Pull down system to fix the power recycling IM to the EQ stop.
    b. EQ stop for the BS recoil mass.

2. Checked assembly PR/SR drawings. There were few corrections/changes.

3. Checked fastener list. There were few corrections/changes.

4. Checked component list for the manufacture order. There were few corrections/changes.

5. I helped in searching for the PR mirror box missing pieces at Mitaka.

Regards,

Fabian
}}}

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Activity report for weeks of 12/26 and 1/2

Dear Mark,

I did for Type-B as below,
・modified parts list and screw list for Payload.
・sent lists to i-ject and asked for quotes.
(But we need to send latest list again.)
・made drawings for some jigs and some parts for payload.

For PR
・searched glueing jigs.
・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
・washed additional masses for IM and sent them to Kamioka.

For others
・washed IMMT plate and send them to Kamioka.

Best regards,
Hirata

Hello,

Succinctly, it is as follows: 

1. Mechanical design:

    a. Pull down system to fix the power recycling IM to the EQ stop.
    b. EQ stop for the BS recoil mass.

2. Checked assembly PR/SR drawings. There were few corrections/changes.

3. Checked fastener list. There were few corrections/changes.

4. Checked component list for the manufacture order. There were few corrections/changes.

5. I helped in searching for the PR mirror box missing pieces at Mitaka.

Regards,

Fabian