Differences between revisions 37 and 137 (spanning 100 versions)
Revision 37 as of 2016-07-13 03:09:22
Size: 2317
Editor: MarkBarton
Comment:
Revision 137 as of 2017-04-14 13:36:43
Size: 2522
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC.
  * Hirata-san ordered wire for the BS.
  * Fabian weighed the masses that he'd been constructing in the cleanroom and found a 600 g discrepancy from the Inventor.
  * Hirata-san ordered a medium-capacity scale to help check the masses of the parts.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi)
  * Finish assembly of BS IM, RM and IRM (Fabian).
  * Weigh IM/RM/IRM (Fabian, Hirata)
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Mark, Shoda)
  * Remove glue from dummy BS face (Fabian)
  * Remove prism from dummy BS (Hirose, Fabian?)
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata)
  * Clean wire for BS and RM (Hirata)
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
  * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

 * Filed crane adapter ring to make it fit better on the hook.
 * Debugged the BF and SF LVDTs (the signal generator had lost its settings in the rack shutdown).
 * Debugged the TM-H4 OSEM problem (a "Type 3 extension cable had gone bad).
 * Weighed eyebolts used to lie the SF.
 * Shipped the old pico driver and joystick back to Mitaka for Eleonora.
 * Borrowed a second pico driver ("PR3") and set it and "BS" up in the rack.
 * Practiced driving the BF cap picos with the new drivers.
 * (With help from Miyo-kun) got the pico MEDM screens running.
 * Replace the temporary "PR3" driver with a new one "BS_BF", and renamed "BS" to "BS_IM".
 * Checked all the DIO connections to the LPCD and connected up the HPCDs. With help from Kokeyama-san we can now see all the drivers from EPICS.
 * Worked on balancing the BF/IRM/IM... section. Sometime during this work, the IM sank and would not come back to its proper position even with the fishing rod. We put a scale under the RM and found that the imbalance was 488 g. Using the fishing rod we got this down to 235 g, but we found that the direction of the stepper was not consistently related to the direction selected on the driver screen - we had previously noted that "left" was "up, but driving "up" the imbalance would decrease to 235 g and then start increasing again, indicating the stepper had bounced off some obstacle. (There was no obvious sound when this happened, unlike at the low end.)
 * We decided to give up on tuning the height of the IM with the fishing rod and to proceed with the test hang by locking the BF keystone at the desired height.
 * Hirata-san installed the PI fishing rod and magic wand, and did more work on changing the PI LVDT connectors from female to male.
 * Enzo made many edits to the circuit diagram, adding the DIO for the HPCDs and correcting minor mistakes.

==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 4/17:
 * Install temporary ballast mass in SF.
 * Lift SF/BF/... section and check total weight and SF balance.
 * Continue swap of PI LVDT connectors (female->male)
 * Start preparing LBB spring units.
Week of 4/24:
 * Crane in PI.
 * Connect SF/BF... section.
 * Temporarily remove PI and adjust SF ballast if necessary.
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • Filed crane adapter ring to make it fit better on the hook.
  • Debugged the BF and SF LVDTs (the signal generator had lost its settings in the rack shutdown).
  • Debugged the TM-H4 OSEM problem (a "Type 3 extension cable had gone bad).
  • Weighed eyebolts used to lie the SF.
  • Shipped the old pico driver and joystick back to Mitaka for Eleonora.
  • Borrowed a second pico driver ("PR3") and set it and "BS" up in the rack.
  • Practiced driving the BF cap picos with the new drivers.
  • (With help from Miyo-kun) got the pico MEDM screens running.
  • Replace the temporary "PR3" driver with a new one "BS_BF", and renamed "BS" to "BS_IM".
  • Checked all the DIO connections to the LPCD and connected up the HPCDs. With help from Kokeyama-san we can now see all the drivers from EPICS.
  • Worked on balancing the BF/IRM/IM... section. Sometime during this work, the IM sank and would not come back to its proper position even with the fishing rod. We put a scale under the RM and found that the imbalance was 488 g. Using the fishing rod we got this down to 235 g, but we found that the direction of the stepper was not consistently related to the direction selected on the driver screen - we had previously noted that "left" was "up, but driving "up" the imbalance would decrease to 235 g and then start increasing again, indicating the stepper had bounced off some obstacle. (There was no obvious sound when this happened, unlike at the low end.)
  • We decided to give up on tuning the height of the IM with the fishing rod and to proceed with the test hang by locking the BF keystone at the desired height.
  • Hirata-san installed the PI fishing rod and magic wand, and did more work on changing the PI LVDT connectors from female to male.
  • Enzo made many edits to the circuit diagram, adding the DIO for the HPCDs and correcting minor mistakes.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 4/17:

  • Install temporary ballast mass in SF.
  • Lift SF/BF/... section and check total weight and SF balance.
  • Continue swap of PI LVDT connectors (female->male)

  • Start preparing LBB spring units.

Week of 4/24:

  • Crane in PI.
  • Connect SF/BF... section.
  • Temporarily remove PI and adjust SF ballast if necessary.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)