* Fabian took photos of the cleanroom in the ATC. * Hirata-san ordered wire for the BS. * Fabian weighed the masses that he'd been constructing in the cleanroom and found a 600 g discrepancy from the Inventor. * Hirata-san ordered a medium-capacity scale to help check the masses of the parts. |
* Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Took data with geophones connected but immobilized and then stored geophones in boxes. * Tested signals from first satellite amp getting to digital system. * Weighed mirror box. * Did fit check of flag holders for stub flags. Very minor adjustments will be needed. * Covered everything in preparation for modifications to clean booth roof (9/20-21). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. |
Line 11: | Line 24: |
* OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts - RECEIVED. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Apply grease to jacks for assembly frame (Takahashi) * Finish assembly of BS IM, RM and IRM (Fabian). * Weigh IM/RM/IRM (Fabian, Hirata) * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Mark, Shoda) * Remove glue from dummy BS face (Fabian) * Remove prism from dummy BS (Hirose, Fabian?) * Reglue flags and prisms (Tatsumi, Fabian) * Buy wire for BS and RM (Hirata) * Clean wire for BS and RM (Hirata) * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) |
* Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. |
Line 36: | Line 31: |
* Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) * Apply vacuum grease to jacks for BS assembly frame (Takahashi) * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list |
|
Line 43: | Line 33: |
* Redesign SRx IM wire clamps for larger prisms, remachined RMs. | * Redesign SRx IM wire clamps for larger prisms, remachined RMs |
Line 46: | Line 36: |
* Check SR RM machining test progress (Hirata) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
- Hung RM.
- Did permanent routing of RM OSEM cables to IM.
- Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
- Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
- Did temporary routing of RM OSEMs to PR2 rack (4 channels).
- Took data with geophones connected but immobilized and then stored geophones in boxes.
- Tested signals from first satellite amp getting to digital system.
- Weighed mirror box.
- Did fit check of flag holders for stub flags. Very minor adjustments will be needed.
- Covered everything in preparation for modifications to clean booth roof (9/20-21).
- Hirata-san:
- Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
- Started 3D CAD for SRM.
- Checked flag design.
- Assembled a bottom filter (ongoing).
- Cleaned maraging rods.
- Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
- Type B ongoing issues
- Longer term to-do list
- Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
- Part "disk security" top has to be modified - screw positions do not match.
- Write more of payload assembly procedure (Fabian) - ONGOING
Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING
- Lower breadboard installation to be incorporated into the procedure document.
- Work on BS simulation (Fabian)
- Do BS Simulink model (Mark, Kokeyama)
- Do 2D drawings of SR2 parts (Hirata)
- Redesign SRx IM wire clamps for larger prisms, remachined RMs
- Order SRM/PRM parts (Hirata/Shoda)
- Order SRx fasteners (Hirata)
- Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.