Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC.
  * Hirata-san ordered wire for the BS.
  * Fabian weighed the masses that he'd been constructing in the cleanroom and found a 600 g discrepancy from the Inventor.
  * Hirata-san ordered a medium-capacity scale to help check the masses of the parts.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi)
  * Finish assembly of BS IM, RM and IRM (Fabian).
  * Weigh IM/RM/IRM (Fabian, Hirata)
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Mark, Shoda)
  * Remove glue from dummy BS face (Fabian)
  * Remove prism from dummy BS (Hirose, Fabian?)
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata)
  * Clean wire for BS and RM (Hirata)
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
 * Type B Past Week Summary, weeks of 9/19 and 9/26
  * Fabian, Mark and Kuwahara-kun did BS installation at Kamioka:
   * The BS clean booth was modified 9/20-21 to allow crane access. The area was fairly clean when Fabian inspected it on 9/26, but there were lots of metal flakes stuck to tape holding foil over the slit in the top of the clean bag.
   * Mark created a new Type B rtcds model and MEDM screens for the BS, adapting the TypeBb/PR3.
   * Mark and Kokeyama-san debugged the new model, fixing several issues.
   * Kuwahara-kun derived OSEM2EUL and EUL2OSEM matrices.
   * Mark set up OSEMINF filters using measured OSEM calibration data to return outputs in µm.
   * Mark took free-swing data on the TM stage to get the pendulum mode frequencies for comparison to the SUMCON model.
   * Mark and Fabian debugged the coil output to the OSEMs. (At first the coil drive was not giving output because it did not have BIO inputs and so was reading the test input, not the main input. And for a while output failed because of a loose cable to the sat amp.)
   * Mark took fixed-sine TFs to check the polarity of the coil-magnet combinations.
  * Hirata-san:
   * Finished 3D CAD of SRM in tanks (but some work was lost due to a hard disk crash).
   * Did 3D and 2D for new maraging rods, stub flags for PR/SR (ditto re hard disk).
   * Measured/tested Type A BF #8 and started assembling #9.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
Line 36: Line 26:
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
  * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
Line 43: Line 28:
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.   * Redesign SRx IM wire clamps for larger prisms, remachined RMs
Line 46: Line 31:
  * Check SR RM machining test progress (Hirata)
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary, weeks of 9/19 and 9/26
    • Fabian, Mark and Kuwahara-kun did BS installation at Kamioka:
      • The BS clean booth was modified 9/20-21 to allow crane access. The area was fairly clean when Fabian inspected it on 9/26, but there were lots of metal flakes stuck to tape holding foil over the slit in the top of the clean bag.
      • Mark created a new Type B rtcds model and MEDM screens for the BS, adapting the TypeBb/PR3.
      • Mark and Kokeyama-san debugged the new model, fixing several issues.
      • Kuwahara-kun derived OSEM2EUL and EUL2OSEM matrices.
      • Mark set up OSEMINF filters using measured OSEM calibration data to return outputs in µm.
      • Mark took free-swing data on the TM stage to get the pendulum mode frequencies for comparison to the SUMCON model.
      • Mark and Fabian debugged the coil output to the OSEMs. (At first the coil drive was not giving output because it did not have BIO inputs and so was reading the test input, not the main input. And for a while output failed because of a loose cable to the sat amp.)
      • Mark took fixed-sine TFs to check the polarity of the coil-magnet combinations.
    • Hirata-san:
      • Finished 3D CAD of SRM in tanks (but some work was lost due to a hard disk crash).
      • Did 3D and 2D for new maraging rods, stub flags for PR/SR (ditto re hard disk).
      • Measured/tested Type A BF #8 and started assembling #9.
  • Longer term to-do list
    • Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
      • Part "disk security" top has to be modified - screw positions do not match.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING

    • Lower breadboard installation to be incorporated into the procedure document.
    • Work on BS simulation (Fabian)
    • Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)