 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san ordered and received wire for the BS and RM (will be cleaned 7/19).
  * Hirata-san received remachined locking parts for the IM (will be cleaned 7/19).
  * Hirata-san ordered additional Misumi parts to be used with the IM locking parts.
  * Fabian and Hirata-san weighed the masses that they've been constructing in the cleanroom and found a 600 g discrepancy from the Inventor (too light) for the IM.
  * Hirata-san ordered a medium-capacity scale to weigh the masses of the individual parts more precisely.
  * Hirose-san and his team successfully removed the misglued prisms from the dummy BS.
  * Fabian travelled to Kashiwa and removed most of the glue from the face of the dummy BS (where the flags had been). There is still some adhesive remaining on both the face and barrel, which will require more work and a second trip.
  * Shoda-san took a suitable segment of geophone noise data for analysis. Fabian will track down the calibration factors.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi)
  * Finish assembly of BS IM, RM and IRM (Fabian).
  * Weigh IM/RM/IRM (Fabian, Hirata)
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Mark, Shoda)
  * Remove glue from dummy BS face (Fabian)
  * Remove prism from dummy BS (Hirose, Fabian?)
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata)
  * Clean wire for BS and RM (Hirata)
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
  * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for week of 4/9 ====
 * Mark glued prisms and magnet/standoff assemblies on the SR3. The SR3 needed to be raised in the box by 0.7 mm to make the prisms go on at the right height, which was done using M4 washers under the PEEK feet.
 * Mark glued ferromagnetic disks on the last 5 IM flags. This completes 2 sets, for SR3 and SRM.
 * Mark configured two pico motor drivers ordered by Takahashi-san as SR3-IM and SRM-BF.
 * Enzo and Kozu-kun finished preparing and calibrating the SF and BF for SR3 and almost entirely finished with those for SRM.
 * Hirata-san worked on building two IMs for SR3 and SRM. The SR3 one just needs to have flags attached and to be weighed; the SRM needs another few hours work.
 * Shoda-san worked on the design of the metal SRM, on the LBB ballast mass, and on the plans for testing the BS in bKAGRA Phase 1.

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Tanioka-san at Kamioka Tue-Thu
 * Others at Kamioka full week
 * --
 * Move SF and BF for SRM out of the way.
 * Check results of gluing.
 * Build 1xRM
 * Calibrate OSEMs.
 * Start SR3 Hang
  * Reset assembly frame crossbars to correct heights.
  * Center the optical table.
  * Align the assembly frame vertically.
  * Install IM ring and IM.
  * Hang optic.
  * Hang RM.
  * Cable RM OSEMs.

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Continue SR3 hang.

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/9

  • Mark glued prisms and magnet/standoff assemblies on the SR3. The SR3 needed to be raised in the box by 0.7 mm to make the prisms go on at the right height, which was done using M4 washers under the PEEK feet.
  • Mark glued ferromagnetic disks on the last 5 IM flags. This completes 2 sets, for SR3 and SRM.
  • Mark configured two pico motor drivers ordered by Takahashi-san as SR3-IM and SRM-BF.
  • Enzo and Kozu-kun finished preparing and calibrating the SF and BF for SR3 and almost entirely finished with those for SRM.
  • Hirata-san worked on building two IMs for SR3 and SRM. The SR3 one just needs to have flags attached and to be weighed; the SRM needs another few hours work.
  • Shoda-san worked on the design of the metal SRM, on the LBB ballast mass, and on the plans for testing the BS in bKAGRA Phase 1.

Plan for week of 4/16

  • Shoda-san at Mitaka
  • Tanioka-san at Kamioka Tue-Thu
  • Others at Kamioka full week
  • --
  • Move SF and BF for SRM out of the way.
  • Check results of gluing.
  • Build 1xRM
  • Calibrate OSEMs.
  • Start SR3 Hang
    • Reset assembly frame crossbars to correct heights.
    • Center the optical table.
    • Align the assembly frame vertically.
    • Install IM ring and IM.
    • Hang optic.
    • Hang RM.
    • Cable RM OSEMs.

Plan for week of 4/23

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka?
  • Mark, Enzo at Kamioka
  • Hirata-san at Mitaka
  • Tanioka-san at Mitaka?
  • --
  • Clean parts (cable clamp bases, etc, etc).
  • Observe KAGRA Phase 1 operations, assist if problems arise.
  • Continue SR3 hang.

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Fabian vacation, 3/26-4/27 (then gone).