 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san ordered and received wire for the BS and RM (will be cleaned 7/19).
  * Hirata-san received remachined locking parts for the IM (will be cleaned 7/19).
  * Hirata-san ordered additional Misumi parts to be used with the IM locking parts.
  * Fabian and Hirata-san weighed the masses that they've been constructing in the cleanroom and found a 600 g discrepancy from the Inventor (too light) for the IM.
  * Hirata-san ordered a medium-capacity scale to weigh the masses of the individual parts more precisely.
  * Hirose-san and his team successfully removed the misglued prisms from the dummy BS.
  * Fabian travelled to Kashiwa and removed most of the glue from the face of the dummy BS (where the flags had been). There is still some adhesive remaining on both the face and barrel, which will require more work and a second trip.
  * Shoda-san took a suitable segment of geophone noise data for analysis. Fabian will track down the calibration factors.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi)
  * Finish assembly of BS IM, RM and IRM (Fabian).
  * Weigh IM/RM/IRM (Fabian, Hirata)
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Mark, Shoda)
  * Remove glue from dummy BS face (Fabian)
  * Remove prism from dummy BS (Hirose, Fabian?)
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata)
  * Clean wire for BS and RM (Hirata)
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata)
  * Apply vacuum grease to jacks for BS assembly frame (Takahashi)
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for week of 11/14 ====
 * SRM
  * We locked the suspension and craned it into the tank. This is the last Type B tank installation!
  * While inspecting the O-ring between the service ring and the lower section of the tank, Hirata-san found a small nick, so he replaced it. (This will hopefully be the last time that flange is closed, so it needs to be left ready for Mirapro to tighten.)
  * Hirata-san and Fabian removed the First Contact, but found that a tiny piece was left behind. With advice from Hirose-san, they managed to remove it via several rounds of dabbing with an acetone-soaked lens tissue.
  * They removed the IM-RM safety bar, unlocked the lower half of the suspension, and got it reasonably well aligned by eye.
  * They moved the vacuum feedthroughs and in-air cabling over, and reconnected nearly all the electronics. (The in-air cabling will need some tidying later, but
 * SR2
  * Enzo worked on diagonalizing the IP and modeling of the whole suspension. He created Foton filters representing the response of the system in slots FM6-8 of the various filter banks.
  * Enzo and Mark set up the the SR2 OL. We may need to steal the LED back temporarily to do pitch setting on SRM, but we can take some interesting TFs on SR2 over the weekend.
 * SR3
  * Enzo configured a new stepper driver for SR3_IP and returned the one that had been borrowed from SRM. (The original SR3_IP had been used to replace a water-damaged unit on the BS.)
 * Etc
  * Mark got three more MPCDs (M = "medium" or "modified") from AEL and moved coil drivers around until all Type B suspensions had a driver in every position, with MPCDs for IM-H and HPCDs everywhere else. He returned the unused LPCDs.
  * Mark did an inventory of all the Type B electronics and got the various JGW Doc electronic items lists up to date - see [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7276|E1707276]]. This included opening all the LVDT drivers to check that they had the original cards - BS, SR3 and SRM did, but SR2 had both input cards new. We let AEL know.
  * Hirata-san helped Furuta-san with floor repair.
  * Fabian changed the PR3 thermometer battery.
  * Mirapro installed a bellows on the -Y side of SR3.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 12/17 ====
 * Final alignment of SRM payload, plus BF and SF GAS.
 * (Time permitting) unlocking/centering/tuning of IP.
 * Installation of Enomoto-kun's beam target on SRM (if available).
 * Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
 * Installation of viewports on SRM.

==== Plan for week of 12/24 ====
 * Most of team on holidays - no Kamioka work.

==== Vacation/Etc Info ====
 * Mark: 12/24 - 1/4.
 * Hirata-san: 12/24 - 1/4.
 * Fabian: TBD but similar.
 * Enzo: TBD but similar.
 * Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 11/14

  • SRM
    • We locked the suspension and craned it into the tank. This is the last Type B tank installation!
    • While inspecting the O-ring between the service ring and the lower section of the tank, Hirata-san found a small nick, so he replaced it. (This will hopefully be the last time that flange is closed, so it needs to be left ready for Mirapro to tighten.)
    • Hirata-san and Fabian removed the First Contact, but found that a tiny piece was left behind. With advice from Hirose-san, they managed to remove it via several rounds of dabbing with an acetone-soaked lens tissue.
    • They removed the IM-RM safety bar, unlocked the lower half of the suspension, and got it reasonably well aligned by eye.
    • They moved the vacuum feedthroughs and in-air cabling over, and reconnected nearly all the electronics. (The in-air cabling will need some tidying later, but
  • SR2
    • Enzo worked on diagonalizing the IP and modeling of the whole suspension. He created Foton filters representing the response of the system in slots FM6-8 of the various filter banks.
    • Enzo and Mark set up the the SR2 OL. We may need to steal the LED back temporarily to do pitch setting on SRM, but we can take some interesting TFs on SR2 over the weekend.
  • SR3
    • Enzo configured a new stepper driver for SR3_IP and returned the one that had been borrowed from SRM. (The original SR3_IP had been used to replace a water-damaged unit on the BS.)
  • Etc
    • Mark got three more MPCDs (M = "medium" or "modified") from AEL and moved coil drivers around until all Type B suspensions had a driver in every position, with MPCDs for IM-H and HPCDs everywhere else. He returned the unused LPCDs.
    • Mark did an inventory of all the Type B electronics and got the various JGW Doc electronic items lists up to date - see E1707276. This included opening all the LVDT drivers to check that they had the original cards - BS, SR3 and SRM did, but SR2 had both input cards new. We let AEL know.

    • Hirata-san helped Furuta-san with floor repair.
    • Fabian changed the PR3 thermometer battery.
    • Mirapro installed a bellows on the -Y side of SR3.

To-Do Lists, Schedule

Plan for week of 12/17

  • Final alignment of SRM payload, plus BF and SF GAS.
  • (Time permitting) unlocking/centering/tuning of IP.
  • Installation of Enomoto-kun's beam target on SRM (if available).
  • Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
  • Installation of viewports on SRM.

Plan for week of 12/24

  • Most of team on holidays - no Kamioka work.

Vacation/Etc Info

  • Mark: 12/24 - 1/4.
  • Hirata-san: 12/24 - 1/4.
  • Fabian: TBD but similar.
  • Enzo: TBD but similar.
  • Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.