Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san ordered and received wire for the BS and RM (will be cleaned 7/19).
  * Hirata-san received remachined locking parts for the IM (will be cleaned 7/19).
  * Hirata-san ordered additional Misumi parts to be used with the IM locking parts.
  * Fabian and Hirata-san weighed the masses that they've been constructing in the cleanroom and found a 600 g discrepancy from the Inventor (too light) for the IM. Although the density assumed in the Inventor agrees with spec sheet values, it doesn't match the parts. Adjusting the density to match a few key parts reduces the discrepancy to 60 g. More investigation is planned.
  * Hirata-san ordered a medium-capacity scale to weigh the individual parts more precisely and help locate the discrepancy.
  * Hirata-san organized to do a fit/function test of the BS winches and training session with Ikenoue-san of ATC on 7/25.
  * Hirose-san and his team successfully removed the misglued prisms from the dummy BS.
  * Fabian travelled to Kashiwa and removed most of the glue from the face of the dummy BS (where the flags had been). There is still some adhesive remaining on both the face and barrel, which will require more work in a second trip.
  * Shoda-san took a suitable segment of geophone noise data for analysis. Fabian will track down the calibration factors.
  * Hirata-san worked on 2D drawings for the PI cable clamps and the magnetic damper for the lower breadboard.
  * Hirata-san worked on the 3D assembly for SR2.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi) - DONE
  * Finish assembly of BS IM, RM and IRM (Fabian) - DONE
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Remove prism from dummy BS (Hirose, Fabian?) - DONE
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata) - DONE
  * Clean wire for BS and RM (Hirata) - 7/19
  * Do fit/function test of winches (Fabian/Hirata) - ORGANIZED for 7/25
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - just started.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for week of 7/23 ====
 * We finished adding cable clamps to the SR2 PI and SF.
 * We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF.
 * We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments.
 * We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side.
 * We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.)
 * We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution.
 * With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters.
 * Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces.
 * Mark did inventory of the BIO stuff for the WD and of the OL parts.

==== Plan for week of 7/30 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
 * Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator).

===== SR2 =====
 * Fix issue with PI/SS/chain alignment.
 * Put magnets on SR damper ring (2 Cu segment pattern).
 * Remove PI-SF rod temporarily, install Cu segments and damper ring.
 * Do vertical height budget; choose optimum F0 keystone height.
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 
===== SRM =====
 * Set up filter tuning area.
 * Tune F0 for SRM.
 * Add LBB blade units, cable clamps etc.
 * Check PI coil connections, IP LVDT magnets.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/23

  • We finished adding cable clamps to the SR2 PI and SF.
  • We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF.
  • We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments.

  • We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side.
  • We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.)
  • We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution.
  • With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters.
  • Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces.
  • Mark did inventory of the BIO stuff for the WD and of the OL parts.

Plan for week of 7/30

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

SR3
  • Finalize optic pitch, OSEM alignment.
  • Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
  • Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator).

SR2
  • Fix issue with PI/SS/chain alignment.
  • Put magnets on SR damper ring (2 Cu segment pattern).
  • Remove PI-SF rod temporarily, install Cu segments and damper ring.
  • Do vertical height budget; choose optimum F0 keystone height.
  • Add estimated final ballast mass.
  • Do PI cable routing.
  • Adjust ballast/trim mass, with reserve for cables.

SRM
  • Set up filter tuning area.
  • Tune F0 for SRM.
  • Add LBB blade units, cable clamps etc.
  • Check PI coil connections, IP LVDT magnets.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)