 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san ordered and received wire for the BS and RM (will be cleaned 7/19).
  * Hirata-san received remachined locking parts for the IM (will be cleaned 7/19).
  * Hirata-san ordered additional Misumi parts to be used with the IM locking parts.
  * Fabian and Hirata-san weighed the masses that they've been constructing in the cleanroom and found a 600 g discrepancy from the Inventor (too light) for the IM. Although the density assumed in the Inventor agrees with spec sheet values, it doesn't match the parts. Adjusting the density to match a few key parts reduces the discrepancy to 60 g. More investigation is planned.
  * Hirata-san ordered a medium-capacity scale to weigh the individual parts more precisely and help locate the discrepancy.
  * Hirata-san organized to do a fit/function test of the BS winches and training session with Ikenoue-san of ATC on 7/25.
  * Hirose-san and his team successfully removed the misglued prisms from the dummy BS.
  * Fabian travelled to Kashiwa and removed most of the glue from the face of the dummy BS (where the flags had been). There is still some adhesive remaining on both the face and barrel, which will require more work in a second trip.
  * Shoda-san took a suitable segment of geophone noise data for analysis. Fabian will track down the calibration factors.
  * Hirata-san worked on 2D drawings for the PI cable clamps and the magnetic damper for the lower breadboard.
  * Hirata-san worked on the 3D assembly for SR2.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi) - DONE
  * Finish assembly of BS IM, RM and IRM (Fabian) - DONE
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Remove prism from dummy BS (Hirose, Fabian?) - DONE
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata) - DONE
  * Clean wire for BS and RM (Hirata) - 7/19
  * Do fit/function test of winches (Fabian/Hirata) - ORGANIZED for 7/25
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - just started.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for the week of 3/4 ====
 * On Monday, Mark helped Aso-san with PR3, and Monday, Tuesday and Wednesday, Fabian helped Fujii-kun with PRM.
 * Mark and Terrence attempted to offload some BS IM/IRM yaw adjustments that had been done by Enomoto-san last Friday. They rezeroed the OL and then opened the tank lid and did a compensating adjustment to the F0 yaw stepper, then undid the IM/IRM yaw with the pico. However this did not have the desired effect, probably because the buoyancy correction had not been cancelled when Enomoto-san was working and the BF keystone was very high, with the IM-V OSEMs way too far in and possibly touching. We did our best to back out all the adjustments but the roll TFs were still messy and there were signs that the IM was not free in yaw (the IM/IRM Y varied oppositely to IP Y, indicating that the IMR was free and the IM wasn't). We ended up deciding to have Mirapro remove the ducts on the ±X sides of the tank so we could go in and inspect.
 * Terrence tuned the SR3 LEN OL to be free of yaw cross-coupling.
 * Terrence and Enzo did a full set of filters and a Guardian for SR2 and SR3.
 * Terrence did health checks on SR2 and SR3.
 * Enzo measured mode Qs.

==== Plan for week of 3/11 =====
 * Mark at Kamioka full week.
 * Enzo at Kamioka Mon, Tue, then JPS.
 * Hirata-san at Kamioka from Monday lunchtime through Friday.
 * Fix BS.
 * Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
 * Install/test hardware watchdogs.
 * Continue monitoring SRM yaw drift.
 * More mode Q measurements.
 * Work on Type B paper.


==== Vacation/Travel Info ====
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/4

  • On Monday, Mark helped Aso-san with PR3, and Monday, Tuesday and Wednesday, Fabian helped Fujii-kun with PRM.
  • Mark and Terrence attempted to offload some BS IM/IRM yaw adjustments that had been done by Enomoto-san last Friday. They rezeroed the OL and then opened the tank lid and did a compensating adjustment to the F0 yaw stepper, then undid the IM/IRM yaw with the pico. However this did not have the desired effect, probably because the buoyancy correction had not been cancelled when Enomoto-san was working and the BF keystone was very high, with the IM-V OSEMs way too far in and possibly touching. We did our best to back out all the adjustments but the roll TFs were still messy and there were signs that the IM was not free in yaw (the IM/IRM Y varied oppositely to IP Y, indicating that the IMR was free and the IM wasn't). We ended up deciding to have Mirapro remove the ducts on the ±X sides of the tank so we could go in and inspect.
  • Terrence tuned the SR3 LEN OL to be free of yaw cross-coupling.
  • Terrence and Enzo did a full set of filters and a Guardian for SR2 and SR3.
  • Terrence did health checks on SR2 and SR3.
  • Enzo measured mode Qs.

==== Plan for week of 3/11 =====

  • Mark at Kamioka full week.
  • Enzo at Kamioka Mon, Tue, then JPS.
  • Hirata-san at Kamioka from Monday lunchtime through Friday.
  • Fix BS.
  • Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
  • Install/test hardware watchdogs.
  • Continue monitoring SRM yaw drift.
  • More mode Q measurements.
  • Work on Type B paper.

Vacation/Travel Info

  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.