Differences between revisions 39 and 58 (spanning 19 versions)
Revision 39 as of 2016-07-15 13:21:53
Size: 3709
Editor: MarkBarton
Comment:
Revision 58 as of 2016-08-17 21:00:25
Size: 3732
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san ordered and received wire for the BS and RM (will be cleaned 7/19).
  * Hirata-san received remachined locking parts for the IM (will be cleaned 7/19).
  * Hirata-san ordered additional Misumi parts to be used with the IM locking parts.
  * Fabian and Hirata-san weighed the masses that they've been constructing in the cleanroom and found a 600 g discrepancy from the Inventor (too light) for the IM. Although the density assumed in the Inventor agrees with spec sheet values, it doesn't match the parts. Adjusting the density to match a few key parts reduces the discrepancy to 60 g. More investigation is planned.
  * Hirata-san ordered a medium-capacity scale to weigh the individual parts more precisely and help locate the discrepancy.
  * Hirata-san organized to do a fit/function test of the BS winches and training session with Ikenoue-san of ATC on 7/25.
  * Hirose-san and his team successfully removed the misglued prisms from the dummy BS.
  * Fabian travelled to Kashiwa and removed most of the glue from the face of the dummy BS (where the flags had been). There is still some adhesive remaining on both the face and barrel, which will require more work in a second trip.
  * Shoda-san took a suitable segment of geophone noise data for analysis. Fabian will track down the calibration factors.
  * Hirata-san worked on 2D drawings for the PI cable clamps and the magnetic damper for the lower breadboard.
  * Hirata-san worked on the 3D assembly for SR2.
 * Type B Past Week Summary - week of 8/8
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
  * Hirata-san measured another standard filter and cleaned various parts for people.
  * Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs.
  * Fabian worked on the payload assembly procedure.
 * Type B Past Week Summary - week of 8/15
  * Hirata-san shipped the fasteners to Kamioka, and they arrived Tuesday.
  * Hirata-san shipped a large load of Type A and Type B items, which Mark and Fabian received on Thursday 8/18.
  * Akutsu-san shipped the first 7 OSEMs.
  * Hirata-san and Ikenoue-san did a successful function test of the BS winches with the new clamp parts for the thicker wires.
  * Mark, Fabian and Zhao-kun did a major cleanup and reorganization of the BS clean booth at Kamioka, putting PR2 stuff in boxes, vacuuming and wiping, and making space.
  * Mark, Fabian and Zhao-kun set the crossbeams of the assembly frame to their correct positions and installed the EQ stop ring on top, ready to receive the IM. This is the first actual installation activity for Type B.
  *
Line 19: Line 23:
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Longer cables for BF->PI and SF->PI still not received, Takahashi-san to check status.
Line 26: Line 26:
   * Breadboard springs (in manufacture, expected end of July)
Line 29: Line 28:
 * To-do list during Mark's vacation
  * Apply grease to jacks for assembly frame (Takahashi) - DONE
  * Finish assembly of BS IM, RM and IRM (Fabian) - DONE
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Remove prism from dummy BS (Hirose, Fabian?) - DONE
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Buy wire for BS and RM (Hirata) - DONE
  * Clean wire for BS and RM (Hirata) - 7/19
  * Do fit/function test of winches (Fabian/Hirata) - ORGANIZED for 7/25
  * Ship winches to Kamioka (Hirata/Fabian)
 * Longer term to-do list
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
Line 43: Line 33:
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - just started.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
Line 49: Line 35:
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.   * Redesign SRx IM wire clamps for larger prisms, remachined RMs
Line 52: Line 38:
  * Check SR RM machining test progress (Hirata)
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary - week of 8/8
    • Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
    • Mark wrote up the gluing procedure as a new document E1605505. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)

    • Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
    • Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
    • Hirata-san measured another standard filter and cleaned various parts for people.
    • Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
    • Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs.
    • Fabian worked on the payload assembly procedure.
  • Type B Past Week Summary - week of 8/15
    • Hirata-san shipped the fasteners to Kamioka, and they arrived Tuesday.
    • Hirata-san shipped a large load of Type A and Type B items, which Mark and Fabian received on Thursday 8/18.
    • Akutsu-san shipped the first 7 OSEMs.
    • Hirata-san and Ikenoue-san did a successful function test of the BS winches with the new clamp parts for the thicker wires.
    • Mark, Fabian and Zhao-kun did a major cleanup and reorganization of the BS clean booth at Kamioka, putting PR2 stuff in boxes, vacuuming and wiping, and making space.
    • Mark, Fabian and Zhao-kun set the crossbeams of the assembly frame to their correct positions and installed the EQ stop ring on top, ready to receive the IM. This is the first actual installation activity for Type B.
  • Type B ongoing issues
    • Longer cables for BF->PI and SF->PI still not received, Takahashi-san to check status.

    • Lower breadboard stuff
      • Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
    • Documents
  • Longer term to-do list
    • Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of main assembly procedure (Mark) - ONGOING
    • Work on BS simulation (Fabian)
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)