Differences between revisions 40 and 415 (spanning 375 versions)
Revision 40 as of 2016-07-22 10:37:42
Size: 2937
Editor: MarkBarton
Comment:
Revision 415 as of 2019-05-16 16:03:54
Size: 2401
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Line 5: Line 4:
 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending).
  * Hirata-san washed remachined locking parts for the IM and screws for jacks.
  * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses.
  * Hirata-san worked on the Inventor 3D assembly of the SR2.
  * The scale for checking the masses of the IM parts was received.
  * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them.
  * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for Golden Week ====
 * Mark monitored vent and pumpdown, and worked on vistools.py.

==== Report for the week of 5/6 ====
 * Lucia and Terrence got the blending working for the IP LVDTs and geophones.
 * Terrence and Mark modified the models and MEDM screens to add a new IP block, IDAMP, for damping using the blended signal with inertial information, and a new DAMPMODE block for ramping smoothly between IDAMP and the old DAMP.
 * Mark worked on vistools.py, improving the support for cdsMuxMatrix blocks (e.g., OSEM2EUL) and adding support for cdsRampMuxMatrix blocks (e.g., the newly introduced DAMPMODE). He also created two sets of unit tests, unittest.py and unittest.sh, for the two modes of use (as a Python module in other Python programs, and as a command-line utility in bash).

==== Report for week of 5/13 ====
 * Terrence and Mark looked at the velocity and angular velocity noise of the SR2 as reported by the LEN OL. The Y signal was fairly clean and the Y RMS angular velocity requirement was met. However the L signal was quite noisy, and was also contaminating the P signal due to the large cross terms in the diagonalization matrix. The RMS L from 5 Hz down with damping on was around 10 µm/s, which is 10 times the requirement. However little of this was due to pendulum resonances - most of the noise was featureless and broadband. In displacement units the noise was flat up to about 1 Hz and then smoothly rolled off to f^-2. The noise in the raw P and Y signals (not yet divided by the sum) was about 10 times the noise in the SUM
 * We tried improving the noise with different whitening settings. Increasing the overall gain, increasing it at the QPD but reducing it at the whitening filter, and switching off the 1-10Hz boost whitening filter (and compensating software filter) had no effect. Blocking the beam reduced the noise by about 2 orders and brought the raw P and Y in line with the SUM, suggesting that the problem was before the QPD.
 * Mark swapped in an improved version of `vistools.py`, debugged a few small issues, and simplified the `TYPEB.py` Guardian.

==== Vacation/Travel Info ====
 * Terrence's next visit from 4/18 to 7/27.
 * Mark's US vacation from 5/22 to 6/11.
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for Golden Week

  • Mark monitored vent and pumpdown, and worked on vistools.py.

Report for the week of 5/6

  • Lucia and Terrence got the blending working for the IP LVDTs and geophones.
  • Terrence and Mark modified the models and MEDM screens to add a new IP block, IDAMP, for damping using the blended signal with inertial information, and a new DAMPMODE block for ramping smoothly between IDAMP and the old DAMP.
  • Mark worked on vistools.py, improving the support for cdsMuxMatrix blocks (e.g., OSEM2EUL) and adding support for cdsRampMuxMatrix blocks (e.g., the newly introduced DAMPMODE). He also created two sets of unit tests, unittest.py and unittest.sh, for the two modes of use (as a Python module in other Python programs, and as a command-line utility in bash).

Report for week of 5/13

  • Terrence and Mark looked at the velocity and angular velocity noise of the SR2 as reported by the LEN OL. The Y signal was fairly clean and the Y RMS angular velocity requirement was met. However the L signal was quite noisy, and was also contaminating the P signal due to the large cross terms in the diagonalization matrix. The RMS L from 5 Hz down with damping on was around 10 µm/s, which is 10 times the requirement. However little of this was due to pendulum resonances - most of the noise was featureless and broadband. In displacement units the noise was flat up to about 1 Hz and then smoothly rolled off to f^-2. The noise in the raw P and Y signals (not yet divided by the sum) was about 10 times the noise in the SUM
  • We tried improving the noise with different whitening settings. Increasing the overall gain, increasing it at the QPD but reducing it at the whitening filter, and switching off the 1-10Hz boost whitening filter (and compensating software filter) had no effect. Blocking the beam reduced the noise by about 2 orders and brought the raw P and Y in line with the SUM, suggesting that the problem was before the QPD.
  • Mark swapped in an improved version of vistools.py, debugged a few small issues, and simplified the TYPEB.py Guardian.

Vacation/Travel Info

  • Terrence's next visit from 4/18 to 7/27.
  • Mark's US vacation from 5/22 to 6/11.
  • Mark's final day 6/28.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)