Line 6: Line 6:
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending).
  * Hirata-san washed remachined locking parts for the IM and screws for jacks.
  * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses.
  * Hirata-san worked on the Inventor 3D assembly of the SR2.
  * The scale for checking the masses of the IM parts was received.
  * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them.
  * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Replaced the thrust bearing in the BF with a stainless version. While replacing the picomotor spring, they found several issues with screws.
   * Removed the sheet metal cable clamp on the bottom of the BF and installed a redesigned one.
   * They installed the "flying saucer" cable clamp on the maraging rod between the IM and BF, and attached the cables. There was an issue with the cables from the bottom OSEMs, which are too short by about 300 mm.
   * Ruspended the IM. Relative to the mass budget, about 700 g of trim mass had to be taken off to get good balance. There was also a problem with rubbing. It turned out that the keystone and the attached central PEEK coil former for the LVDT were at an angle, and the inside of the coil former was fouling on the outside of the pole piece for the magnets. It's not yet clear why the keystone was misaligned.
  * Hirata-san:
   * Made drawings of (revised) stub flag gluing jigs.
   * Worked on BS full-assembly drawings for Saito-sensei.
   * (For other groups)
    * Made a 3D model of maraging wires.
    * Finished making drawings of PRM inner frame.
    * Worked on re-setting up PC after crash.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
Line 36: Line 25:
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
Line 42: Line 26:
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.   * Redesign SRx IM wire clamps for larger prisms, remachined RMs
Line 45: Line 29:
  * Check SR RM machining test progress (Hirata)
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Fabian, Mark and Liu-kun did BS installation at Kamioka:
      • Replaced the thrust bearing in the BF with a stainless version. While replacing the picomotor spring, they found several issues with screws.
      • Removed the sheet metal cable clamp on the bottom of the BF and installed a redesigned one.
      • They installed the "flying saucer" cable clamp on the maraging rod between the IM and BF, and attached the cables. There was an issue with the cables from the bottom OSEMs, which are too short by about 300 mm.
      • Ruspended the IM. Relative to the mass budget, about 700 g of trim mass had to be taken off to get good balance. There was also a problem with rubbing. It turned out that the keystone and the attached central PEEK coil former for the LVDT were at an angle, and the inside of the coil former was fouling on the outside of the pole piece for the magnets. It's not yet clear why the keystone was misaligned.
    • Hirata-san:
      • Made drawings of (revised) stub flag gluing jigs.
      • Worked on BS full-assembly drawings for Saito-sensei.
      • (For other groups)
        • Made a 3D model of maraging wires.
        • Finished making drawings of PRM inner frame.
        • Worked on re-setting up PC after crash.
  • Longer term to-do list
    • Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
      • Part "disk security" top has to be modified - screw positions do not match.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING

    • Lower breadboard installation to be incorporated into the procedure document.
    • Work on BS simulation (Fabian)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)