* Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B. * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending). * Hirata-san washed remachined locking parts for the IM and screws for jacks. * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses. * Hirata-san worked on the Inventor 3D assembly of the SR2. * The scale for checking the masses of the IM parts was received. * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them. * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot. * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found. * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors. * Remove glue from dummy BS face (Fabian) - partly done. * Reglue flags and prisms (Tatsumi, Fabian) * Clean wire for BS and RM (Hirata) - DONE * Get new winch parts for new wire diameters - design received from Ikenoue-san * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING. * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
* Mark * Updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]: * Added information on the binary IO. * Renamed channels to conform to Okutomi-kun's new scheme. * Made the ADC/DAC channel assignment consistent and more logical. * Updated the stepper motor sections with info about the new driver chassis. * Worked on schedule. * Updated the installation procedure with lessons learned from the last few weeks. * Downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board. * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.) * Hirata-san * Updated the BS 3D Assembly with the new rods and receptacles. * Made 2D drawings of SR2 and SR3 (ongoing). * Made SRM 3D assembly (ongoing) * Asked for and got quotes for hexagon cable clamps. Takahashi-san ordered the PEEK components. Next week Hirata-san will look for parts that should already be at Kamioka. * Washed screws for hexagon cable clamps and shim rings for Fabian. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Mark
Updated the BS circuit diagram D1503600:
- Added information on the binary IO.
- Renamed channels to conform to Okutomi-kun's new scheme.
- Made the ADC/DAC channel assignment consistent and more logical.
- Updated the stepper motor sections with info about the new driver chassis.
- Worked on schedule.
- Updated the installation procedure with lessons learned from the last few weeks.
- Downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.
- Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
- Hirata-san
- Updated the BS 3D Assembly with the new rods and receptacles.
- Made 2D drawings of SR2 and SR3 (ongoing).
- Made SRM 3D assembly (ongoing)
- Asked for and got quotes for hexagon cable clamps. Takahashi-san ordered the PEEK components. Next week Hirata-san will look for parts that should already be at Kamioka.
- Washed screws for hexagon cable clamps and shim rings for Fabian.
- Mark