Differences between revisions 40 and 81 (spanning 41 versions)
Revision 40 as of 2016-07-22 10:37:42
Size: 2937
Editor: MarkBarton
Comment:
Revision 81 as of 2016-11-04 11:08:28
Size: 1472
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending).
  * Hirata-san washed remachined locking parts for the IM and screws for jacks.
  * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses.
  * Hirata-san worked on the Inventor 3D assembly of the SR2.
  * The scale for checking the masses of the IM parts was received.
  * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them.
  * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
  * Mark
   * Updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]:
    * Added information on the binary IO.
    * Renamed channels to conform to Okutomi-kun's new scheme.
    * Made the ADC/DAC channel assignment consistent and more logical.
    * Updated the stepper motor sections with info about the new driver chassis.
   * Worked on schedule.
   * Updated the installation procedure with lessons learned from the last few weeks.
   * Downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.
   * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
  * Hirata-san
   * Updated the BS 3D Assembly with the new rods and receptacles.
   * Made 2D drawings of SR2 and SR3 (ongoing).
   * Made SRM 3D assembly (ongoing)
   * Asked for and got quotes for hexagon cable clamps. Takahashi-san ordered the PEEK components. Next week Hirata-san will look for parts that should already be at Kamioka.
   * Washed screws for hexagon cable clamps and shim rings for Fabian.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark
      • Updated the BS circuit diagram D1503600:

        • Added information on the binary IO.
        • Renamed channels to conform to Okutomi-kun's new scheme.
        • Made the ADC/DAC channel assignment consistent and more logical.
        • Updated the stepper motor sections with info about the new driver chassis.
      • Worked on schedule.
      • Updated the installation procedure with lessons learned from the last few weeks.
      • Downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.
      • Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
    • Hirata-san
      • Updated the BS 3D Assembly with the new rods and receptacles.
      • Made 2D drawings of SR2 and SR3 (ongoing).
      • Made SRM 3D assembly (ongoing)
      • Asked for and got quotes for hexagon cable clamps. Takahashi-san ordered the PEEK components. Next week Hirata-san will look for parts that should already be at Kamioka.
      • Washed screws for hexagon cable clamps and shim rings for Fabian.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)