Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending).
  * Hirata-san washed remachined locking parts for the IM and screws for jacks.
  * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking. (, )
  * Hirata-san worked on the Inventor 3D assembly of the SR2.
  * The scale for checking the masses of the IM parts was received.
  * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them.
  * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
 * Activity report for weeks of 12/26 and 1/2

{{{Dear Mark,

I did for Type-B as below,
・modified parts list and screw list for Payload.
・sent lists to i-ject and asked for quotes.
(But we need to send latest list again.)
・made drawings for some jigs and some parts for payload.

For PR
・searched glueing jigs.
・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
・washed additional masses for IM and sent them to Kamioka.

For others
・washed IMMT plate and send them to Kamioka.

Best regards,
Hirata
}}}
{{{Hello,

Succinctly, it is as follows:

1. Mechanical design:

    a. Pull down system to fix the power recycling IM to the EQ stop.
    b. EQ stop for the BS recoil mass.

2. Checked assembly PR/SR drawings. There were few corrections/changes.

3. Checked fastener list. There were few corrections/changes.

4. Checked component list for the manufacture order. There were few corrections/changes.

5. I helped in searching for the PR mirror box missing pieces at Mitaka.

Regards,

Fabian
}}}

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Activity report for weeks of 12/26 and 1/2

{{{Dear Mark,

I did for Type-B as below, ・modified parts list and screw list for Payload. ・sent lists to i-ject and asked for quotes. (But we need to send latest list again.) ・made drawings for some jigs and some parts for payload.

For PR ・searched glueing jigs. ・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka. ・washed additional masses for IM and sent them to Kamioka.

For others ・washed IMMT plate and send them to Kamioka.

Best regards, Hirata }}} {{{Hello,

Succinctly, it is as follows:

1. Mechanical design:

  1. Pull down system to fix the power recycling IM to the EQ stop. b. EQ stop for the BS recoil mass.

2. Checked assembly PR/SR drawings. There were few corrections/changes.

3. Checked fastener list. There were few corrections/changes.

4. Checked component list for the manufacture order. There were few corrections/changes.

5. I helped in searching for the PR mirror box missing pieces at Mitaka.

Regards,

Fabian }}}