* Type B Past Week Summary * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B. * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending). * Hirata-san washed remachined locking parts for the IM and screws for jacks. * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking. (, ) * Hirata-san worked on the Inventor 3D assembly of the SR2. * The scale for checking the masses of the IM parts was received. * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them. * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot. * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8) * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found. * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors. * Remove glue from dummy BS face (Fabian) - partly done. * Reglue flags and prisms (Tatsumi, Fabian) * Clean wire for BS and RM (Hirata) - DONE * Get new winch parts for new wire diameters - design received from Ikenoue-san * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING. * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): * Craned in the PI. * Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.) * Hooked the SF and lowered the jacks under the SF to suspend the SF/... section. * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two). * Built and installed three LBB blade units. * Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly. ==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. Week of 5/1: * No activity (Golden Week). Week of 5/8: * Work from Tuesday. * Remove PI temporarily. * Add magnets to upper SF damper ring. * Reinstall PI with damper ring. * Reinstall PI-SF rod, this time with hex cable clamp. * Install PI yaw stepper. * Wire up PI yaw and vertical steppers. * Route cables from SF to PI (may involve removing part of Cu damper). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
- Craned in the PI.
- Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.)
- Hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).
- Built and installed three LBB blade units.
- Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly.
Plan for coming weeks
For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.
Week of 5/1:
- No activity (Golden Week).
Week of 5/8:
- Work from Tuesday.
- Remove PI temporarily.
- Add magnets to upper SF damper ring.
- Reinstall PI with damper ring.
- Reinstall PI-SF rod, this time with hex cable clamp.
- Install PI yaw stepper.
- Wire up PI yaw and vertical steppers.
- Route cables from SF to PI (may involve removing part of Cu damper).