Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending).
  * Hirata-san washed remachined locking parts for the IM and screws for jacks.
  * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking. (, )
  * Hirata-san worked on the Inventor 3D assembly of the SR2.
  * The scale for checking the masses of the IM parts was received.
  * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them.
  * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):
 * We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.
 * We put the service port covers back on at the BF level of the BS tank.
 * We used the PI jacks to center the bottom of the security structure around the RM.
 * We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
 * We used the IP FRs to center the IP.
 * We set the gains on the IP LVDT driver.
 * We tested the picos and most of the steppers. The picos and IP steppers all work nicely. The PI FR and yaw steppers have jamming issues. We haven't tested the BF and SF FR steppers.
 * We debugged an issue with one of the geophones (#1) which has a DC offset. We did cable swaps and determined that the issue is internal to the geophone pod. A second geophone (#2) saturates at a suspiciously small voltage on the negative side. Again the issue is internal.
 * Fabian designed an improvement to the PI yaw stepper driver mount to stop the stepper jamming.
 * Fabian worked on a plan to measure the load capacity of the SR PIs.
 * Hirata-san did 2D drawings of the PI for the SR, and of SF2 and SRM in their vacuum chambers.
 * Hirata-san did drawings if the SR LBB damper rings and asked for quotes.
 * Hirata-san asked for quotes for SR secondary wire breakers and SR IM/IRM lock screws
 * Hirata-san ordered SR IM wire clamps.
 * Hirata-san worked on parts lists for SR cable clamps.

==== Plan for week of 10/2 ====
 * Design ballast for LBB.
 * Design improved PI yaw adjustment.
 * SR procurement.

==== Plan for week of 10/10 ====
Kamioka: Mark, Fabian, Enzo, Ohishi-san, Kozu-kun.
Mitaka: Hirata-san
Holiday Mon 10/9, Open Day prep Fri 10/13.<<BR>>
 * Tune IP, do LVDT/stepper calibration.
 * Remove First Contact, try OL.
 * TFs, final preparation for alignment in week of 10/16.

==== Plan for week of 10/16 ====
Kamioka: all but Mark
 * Work with alignment team.

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):

  • We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.

  • We put the service port covers back on at the BF level of the BS tank.
  • We used the PI jacks to center the bottom of the security structure around the RM.
  • We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
  • We used the IP FRs to center the IP.
  • We set the gains on the IP LVDT driver.
  • We tested the picos and most of the steppers. The picos and IP steppers all work nicely. The PI FR and yaw steppers have jamming issues. We haven't tested the BF and SF FR steppers.
  • We debugged an issue with one of the geophones (#1) which has a DC offset. We did cable swaps and determined that the issue is internal to the geophone pod. A second geophone (#2) saturates at a suspiciously small voltage on the negative side. Again the issue is internal.
  • Fabian designed an improvement to the PI yaw stepper driver mount to stop the stepper jamming.
  • Fabian worked on a plan to measure the load capacity of the SR PIs.
  • Hirata-san did 2D drawings of the PI for the SR, and of SF2 and SRM in their vacuum chambers.
  • Hirata-san did drawings if the SR LBB damper rings and asked for quotes.
  • Hirata-san asked for quotes for SR secondary wire breakers and SR IM/IRM lock screws
  • Hirata-san ordered SR IM wire clamps.
  • Hirata-san worked on parts lists for SR cable clamps.

Plan for week of 10/2

  • Design ballast for LBB.
  • Design improved PI yaw adjustment.
  • SR procurement.

Plan for week of 10/10

Kamioka: Mark, Fabian, Enzo, Ohishi-san, Kozu-kun. Mitaka: Hirata-san Holiday Mon 10/9, Open Day prep Fri 10/13.

  • Tune IP, do LVDT/stepper calibration.
  • Remove First Contact, try OL.
  • TFs, final preparation for alignment in week of 10/16.

Plan for week of 10/16

Kamioka: all but Mark

  • Work with alignment team.

Vacation Info

Mark: 10/16-24