* Type B Past Week Summary * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B. * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending). * Hirata-san washed remachined locking parts for the IM and screws for jacks. * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking. (, ) * Hirata-san worked on the Inventor 3D assembly of the SR2. * The scale for checking the masses of the IM parts was received. * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them. * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot. * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8) * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found. * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors. * Remove glue from dummy BS face (Fabian) - partly done. * Reglue flags and prisms (Tatsumi, Fabian) * Clean wire for BS and RM (Hirata) - DONE * Get new winch parts for new wire diameters - design received from Ikenoue-san * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING. * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
=== Type B (Mark) === ==== Report for week of 7/23 ==== * We finished adding cable clamps to the SR2 PI and SF. * We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF. * We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments. * We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side. * We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.) * We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution. * With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters. * Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces. * Mark did inventory of the BIO stuff for the WD and of the OL parts. ==== Plan for week of 7/30 ==== * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon. ===== SR3 ===== * Finalize optic pitch, OSEM alignment. * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only). * Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator). ===== SR2 ===== * Fix issue with PI/SS/chain alignment. * Put magnets on SR damper ring (2 Cu segment pattern). * Remove PI-SF rod temporarily, install Cu segments and damper ring. * Do vertical height budget; choose optimum F0 keystone height. * Add estimated final ballast mass. * Do PI cable routing. * Adjust ballast/trim mass, with reserve for cables. ===== SRM ===== * Set up filter tuning area. * Tune F0 for SRM. * Add LBB blade units, cable clamps etc. * Check PI coil connections, IP LVDT magnets. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== * Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 7/23
- We finished adding cable clamps to the SR2 PI and SF.
- We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF.
We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments.
- We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side.
- We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.)
- We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution.
- With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters.
- Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces.
- Mark did inventory of the BIO stuff for the WD and of the OL parts.
Plan for week of 7/30
- Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
- Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.
SR3
- Finalize optic pitch, OSEM alignment.
- Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
- Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator).
SR2
- Fix issue with PI/SS/chain alignment.
- Put magnets on SR damper ring (2 Cu segment pattern).
- Remove PI-SF rod temporarily, install Cu segments and damper ring.
- Do vertical height budget; choose optimum F0 keystone height.
- Add estimated final ballast mass.
- Do PI cable routing.
- Adjust ballast/trim mass, with reserve for cables.
SRM
- Set up filter tuning area.
- Tune F0 for SRM.
- Add LBB blade units, cable clamps etc.
- Check PI coil connections, IP LVDT magnets.