3106
Comment:
|
2030
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B. * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending). * Hirata-san washed remachined locking parts for the IM and screws for jacks. * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking. (, ) * Hirata-san worked on the Inventor 3D assembly of the SR2. * The scale for checking the masses of the IM parts was received. * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them. * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot. * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8) * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found. * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors. * Remove glue from dummy BS face (Fabian) - partly done. * Reglue flags and prisms (Tatsumi, Fabian) * Clean wire for BS and RM (Hirata) - DONE * Get new winch parts for new wire diameters - design received from Ikenoue-san * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING. * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
=== Type B (Mark) === ==== Report for week of 9/17 ==== * Monday 9/17 was holiday. * We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico. * We set the SF damper gap to 6 mm. * We set the SR2 pitch with the optic lever, aligned the IRM and set all the OSEMs to have good clearance and midrange output. * We locked the SR2 suspension (except for the SF) and craned it into the tank. * We moved the vacuum feedthroughs over to the tank. * With help from Ohishi-san, we removed the First Contact from SR2. * Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc. * Mark did an inventory of some thin arc weights and finalized the number to order (8*38 mm + 9*10 mm). * Panwei copied control filters over from the SR3. ==== Plan for week of 9/24 ==== * Monday 9/17 is holiday (Respect for the Aged Day). * Enzo on vacation. * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. ===== SR2 ===== * Remove First Contact. * Move SR2 in-air cables. * Unlock and realign suspension. ===== SRM ===== * Set pitch of SRM and RM, tighten clamps, remove winch system. * Weigh IM/... section. * Build up SS to BF level. * Add BF. ==== Plan for week of 9/24 ==== * Monday 9/24 is holiday (Autumn Equinox). * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. * Suspend IM and tweak height/balance. ===== SRM ===== * Cable/test BF. * Install IRM. * Install/cable/test IM OSEMs. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark: 9/10-14 (job interview in US). * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 9/17
- Monday 9/17 was holiday.
- We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
- We set the SF damper gap to 6 mm.
- We set the SR2 pitch with the optic lever, aligned the IRM and set all the OSEMs to have good clearance and midrange output.
- We locked the SR2 suspension (except for the SF) and craned it into the tank.
- We moved the vacuum feedthroughs over to the tank.
- With help from Ohishi-san, we removed the First Contact from SR2.
- Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
- Mark did an inventory of some thin arc weights and finalized the number to order (8*38 mm + 9*10 mm).
- Panwei copied control filters over from the SR3.
Plan for week of 9/24
- Monday 9/17 is holiday (Respect for the Aged Day).
- Enzo on vacation.
- Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
SR2
- Remove First Contact.
- Move SR2 in-air cables.
- Unlock and realign suspension.
SRM
- Set pitch of SRM and RM, tighten clamps, remove winch system.
- Weigh IM/... section.
- Build up SS to BF level.
- Add BF.
Plan for week of 9/24
- Monday 9/24 is holiday (Autumn Equinox).
- Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
- Suspend IM and tweak height/balance.
SRM
- Cable/test BF.
- Install IRM.
- Install/cable/test IM OSEMs.
To-Do Lists, Schedule
Vacation Info
- Mark: 9/10-14 (job interview in US).
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.