Size: 3106
Comment:
|
Size: 1679
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
* Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B. * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending). * Hirata-san washed remachined locking parts for the IM and screws for jacks. * Hirata-san liaised with Ikenoue-san of ATC to get winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking. (, ) * Hirata-san worked on the Inventor 3D assembly of the SR2. * The scale for checking the masses of the IM parts was received. * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were too tight in the holes and adjusting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them. * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot. |
* Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. |
Line 15: | Line 19: |
* OSEMs * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8) * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found. * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors. * Remove glue from dummy BS face (Fabian) - partly done. * Reglue flags and prisms (Tatsumi, Fabian) * Clean wire for BS and RM (Hirata) - DONE * Get new winch parts for new wire diameters - design received from Ikenoue-san * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) |
* Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. |
Line 36: | Line 26: |
* Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING. * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list |
|
Line 42: | Line 28: |
* Redesign SRx IM wire clamps for larger prisms, remachined RMs. | * Redesign SRx IM wire clamps for larger prisms, remachined RMs |
Line 45: | Line 31: |
* Check SR RM machining test progress (Hirata) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
- Hung RM.
- Did permanent routing of RM OSEM cables to IM.
- Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
- Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
- Did temporary routing of RM OSEMs to PR2 rack (4 channels).
- Hirata-san:
- Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
- Started 3D CAD for SRM.
- Checked flag design.
- Assembled a bottom filter (ongoing).
- Cleaned maraging rods.
- Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
- Type B ongoing issues
- Longer term to-do list
- Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
- Part "disk security" top has to be modified - screw positions do not match.
- Write more of payload assembly procedure (Fabian) - ONGOING
Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING
- Lower breadboard installation to be incorporated into the procedure document.
- Work on BS simulation (Fabian)
- Do BS Simulink model (Mark, Kokeyama)
- Do 2D drawings of SR2 parts (Hirata)
- Redesign SRx IM wire clamps for larger prisms, remachined RMs
- Order SRM/PRM parts (Hirata/Shoda)
- Order SRx fasteners (Hirata)
- Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.