* Type B Past Week Summary * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B. * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending). * Hirata-san washed remachined locking parts for the IM and screws for jacks. * Hirata-san liaised with Ikenoue-san of ATC to get new winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking. * Hirata-san worked on the Inventor 3D assembly of the SR2. * The scale for checking the masses of the IM parts was received. * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were slightly too large, and correcting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them. * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot. * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8) * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found. * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors. * Remove glue from dummy BS face (Fabian) - partly done. * Reglue flags and prisms (Tatsumi, Fabian) * Clean wire for BS and RM (Hirata) - DONE * Get new winch parts for new wire diameters - design received from Ikenoue-san * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING. * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
* Hirata-san: * Received many parts from i-ject for BFRM (took pictures and took them into ATC cleanroom). * got quotes for PRM/SRM payload from i-ject. * Checked quotes and asked for some modifications.) * Washed parts (parts for type-A, small hexagons, screws, etc\) * Wiped 9 piano wires and sent to Kamioka for PR. * pdated Fabian's EQstop parts for BS recoilmass and updated EQstop assy drawings. * Fabian * Worked out geometry for blade adjustment. * Designed additional ballast masses for BS BF (and SR). * Mark and Enzo (at Kamioka) * Did two rounds of adjustment of the blades with help from Takahashi-san (one for position, one for frequency) * Surveyed the position of the rod using the vertical mode of the bubble level. * Got apparent improvement as judged at the IRM-IM EQ stops (but still not perfect). * Did one more round of blade adjustments (without Takahashi-san) * Got good agreement with IRM-IM EQ stops, so put BF cap on and raised the whole system to check for balance. * Found balance still fairly bad: about the same on the -X,+Y diagonal and about half on the +X,+Y diagonal (70 and 30 mm worth of motion of a single trim mass respectively; previous a bit over 70 mm each). * From the imbalance torques, calculated the offset of rod as 2.3 mm in the direction 22 degrees to the +X side of -Y. * Calculated the blade adjustments required: {-0.325194, -1.79175, 2.11695} mm * Prepared to apply adjustments (removed cap etc). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Hirata-san:
- Received many parts from i-ject for BFRM (took pictures and took them into ATC cleanroom).
- got quotes for PRM/SRM payload from i-ject.
- Checked quotes and asked for some modifications.)
- Washed parts (parts for type-A, small hexagons, screws, etc\)
- Wiped 9 piano wires and sent to Kamioka for PR.
- pdated Fabian's EQstop parts for BS recoilmass and updated EQstop assy drawings.
- Fabian
- Worked out geometry for blade adjustment.
- Designed additional ballast masses for BS BF (and SR).
- Mark and Enzo (at Kamioka)
- Did two rounds of adjustment of the blades with help from Takahashi-san (one for position, one for frequency)
- Surveyed the position of the rod using the vertical mode of the bubble level.
- Got apparent improvement as judged at the IRM-IM EQ stops (but still not perfect).
- Did one more round of blade adjustments (without Takahashi-san)
- Got good agreement with IRM-IM EQ stops, so put BF cap on and raised the whole system to check for balance.
- Found balance still fairly bad: about the same on the -X,+Y diagonal and about half on the +X,+Y diagonal (70 and 30 mm worth of motion of a single trim mass respectively; previous a bit over 70 mm each).
- From the imbalance torques, calculated the offset of rod as 2.3 mm in the direction 22 degrees to the +X side of -Y.
- Calculated the blade adjustments required: {-0.325194, -1.79175, 2.11695} mm
- Prepared to apply adjustments (removed cap etc).