Differences between revisions 42 and 207 (spanning 165 versions)
Revision 42 as of 2016-07-22 10:45:04
Size: 3103
Editor: MarkBarton
Comment:
Revision 207 as of 2017-11-24 11:48:46
Size: 1396
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending).
  * Hirata-san washed remachined locking parts for the IM and screws for jacks.
  * Hirata-san liaised with Ikenoue-san of ATC to get new winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking.
  * Hirata-san worked on the Inventor 3D assembly of the SR2.
  * The scale for checking the masses of the IM parts was received.
  * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were slightly too large, and correcting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them.
  * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Past week report ====

 * Mark worked on SR2 planning.
 * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
 * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
 * Hirata-san ordered more disks for IM flags.
 * Hirata-san asked for quotes on SF LBB blades.
 * Hirata-san got a reduced quote for the LBB damper rings.
 * Hirata-san received and cleaned suspension wires for the SR.
 * Fabian worked on the SR mass budget.
 * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
 * Enzo and Kozu-kun worked on control filter design and installation.

==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
 * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
  * Mark from Mon lunchtime.
  * Kozu-kun from Mon lunchtime through Wed.
  * Mirror gluing.
  * SR2 rack setup.

==== Plan for week of 12/4 ====
 * All at Kamioka
  * IM assembly and pico test.
  * Assembly frame alignment and optical table centering.
  * OL setup.
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark worked on SR2 planning.
  • Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
  • Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
  • Hirata-san ordered more disks for IM flags.
  • Hirata-san asked for quotes on SF LBB blades.
  • Hirata-san got a reduced quote for the LBB damper rings.
  • Hirata-san received and cleaned suspension wires for the SR.
  • Fabian worked on the SR mass budget.
  • Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
  • Enzo and Kozu-kun worked on control filter design and installation.

Plan for week of 11/27

  • Fabian at commissioning workshop
  • Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
  • All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
    • Mark from Mon lunchtime.
    • Kozu-kun from Mon lunchtime through Wed.
    • Mirror gluing.
    • SR2 rack setup.

Plan for week of 12/4

  • All at Kamioka
    • IM assembly and pico test.
    • Assembly frame alignment and optical table centering.
    • OL setup.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)