* Type B Past Week Summary * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B. * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending). * Hirata-san washed remachined locking parts for the IM and screws for jacks. * Hirata-san liaised with Ikenoue-san of ATC to get new winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking. * Hirata-san worked on the Inventor 3D assembly of the SR2. * The scale for checking the masses of the IM parts was received. * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were slightly too large, and correcting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them. * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot. * Type B ongoing issues * OSEMs * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8) * Longer cables for BF->PI and SF->PI. * Connectors RECEIVED, cables being made. * SR machining test ongoing. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] * To-do list during Mark's vacation * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found. * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian). * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors. * Remove glue from dummy BS face (Fabian) - partly done. * Reglue flags and prisms (Tatsumi, Fabian) * Clean wire for BS and RM (Hirata) - DONE * Get new winch parts for new wire diameters - design received from Ikenoue-san * Do fit/function test of winches (Fabian/Hirata) * Ship winches to Kamioka (Hirata/Fabian) * Work on BS simulation (Fabian) * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING. * Write more of payload assembly procedure (Fabian) * Write more of main assembly procedure (Mark) * Longer term to-do list * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs. * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) * Check SR RM machining test progress (Hirata) |
=== Type B (Mark) === ==== Report for week of 1/29 ==== * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth. * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]). * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]). * We referred the BS OL. * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4073|4073]]). * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts. * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding. * Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods. * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop). ==== Plan for week of 2/5 ==== * Enzo on vacation; all others at Kamioka. * - * Make in-air pico adapter cables. * Calibrate LVDT. * Test IM picos and BF yaw pico. * Test FR. * Install ballast mass in BF. * Build IRM around IM. ==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日)<<BR>> * Enzo on vacation * Hirata-san at Mitaka Tue, Wed (to receive and wash parts). * All others at Kamioka. * - * Cable/test/adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. ==== Plan for week of 2/19 ==== * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Add Cu segments to SF cap. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. ==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30). * Fabian 4/2-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog 4058).
We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog 4061).
- We referred the BS OL.
We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog 4073).
- Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
- Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
- Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
- Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
Plan for week of 2/5
- Enzo on vacation; all others at Kamioka.
- -
- Make in-air pico adapter cables.
- Calibrate LVDT.
- Test IM picos and BF yaw pico.
- Test FR.
- Install ballast mass in BF.
- Build IRM around IM.
Plan for week of 2/13
No work Monday (建国記念の日の振替休日)
- Enzo on vacation
- Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
- All others at Kamioka.
- -
- Cable/test/adjust IM OSEMs.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Plan for week of 2/19
- Lift BF/... section and check total mass and balance.
- Cable and test BF picos.
- Add section of SS up to SF ring.
- Bring in SF.
- Add Cu segments to SF cap.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30).
- Fabian 4/2-4/27 vacation (then gone).