 * Type B Past Week Summary
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san wiped one set each of wires for the BS and RM (addition sets pending).
  * Hirata-san washed remachined locking parts for the IM and screws for jacks.
  * Hirata-san liaised with Ikenoue-san of ATC to get new winch parts designed for the new wire thicknesses. Ikenoue-san provided updated designs for checking.
  * Hirata-san worked on the Inventor 3D assembly of the SR2.
  * The scale for checking the masses of the IM parts was received.
  * Fabian and Hirata-san identified an issue with the lock screws between the IM and IRM. The screws were slightly too large, and correcting the size with a die caused large flakes of the black coating to come off. (These screws were ordered before the current screw policy was instituted.) Hirata-san will order better screws from Misumi and have additional machining done on them.
  * Fabian tracked down the calibration factors for the geophones and generated a calibrated plot.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for the week of 4/1 ====
 * Support of Type Bp
  * Hirata-san procured the jigs for PRs and Takahashi-san tested one at TAMA.
  * Hirata-san cleaned up the flags for PR2 and Mark did the one for PRM.
  * Fabian helped Fujii-kun and Takashashi-san to reglue the flags.
 * Mark did a lot of maintenance on the MEDM screens:
  * Made the name of the suspension more obvious (no yellow text!).
  * Added rack temperature indicators.
  * Fixed the labels in the ADC screen (to reflect the LEN OL moving from ADC#0 to #1).
  * Fixed broken links.
  * Committed files to the SVN.
 * Mark did maintenance on the Guardian to make it give more helpful messages in the TRIGGER state. Formerly it only checked the user model watchdog and the coil driver watchdog, not the DACKILL, and gave the same generic notification for both. Now it checks all three and tells the user which need attention.
 * Mark tidied up the cables in the SR2 rack and returned a large pile of no-longer-used cables to the tent.
 * Mark started a !HealthCheck page on the Operation Manual wiki.
Fabian and Mark
==== Plan for week of 4/8 ====
 * Mark, Fabian at Kamioka Mon-Fri.
 * Help with Type Bp.
 * Health checks on Type B.
 * Monitor pumpdown.
 * Work on Type B paper.
 * Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
 * Tidy up.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.

==== Plan for week of 4/15 ====
 * Mark at Mitaka 4/15, Kamioka 4/16-18, f2f 4/19.
 * Fabian at Kamioka 4/15-18, f2f 4/19.

==== Vacation/Travel Info ====
 * Mark at Mitaka 4/15.
 * f2f 4/19 (Friday), 4/20, 4/21.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's vacation from about 5/22 to 6/11.
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 4/1

  • Support of Type Bp
    • Hirata-san procured the jigs for PRs and Takahashi-san tested one at TAMA.
    • Hirata-san cleaned up the flags for PR2 and Mark did the one for PRM.
    • Fabian helped Fujii-kun and Takashashi-san to reglue the flags.
  • Mark did a lot of maintenance on the MEDM screens:
    • Made the name of the suspension more obvious (no yellow text!).
    • Added rack temperature indicators.
    • Fixed the labels in the ADC screen (to reflect the LEN OL moving from ADC#0 to #1).
    • Fixed broken links.
    • Committed files to the SVN.
  • Mark did maintenance on the Guardian to make it give more helpful messages in the TRIGGER state. Formerly it only checked the user model watchdog and the coil driver watchdog, not the DACKILL, and gave the same generic notification for both. Now it checks all three and tells the user which need attention.
  • Mark tidied up the cables in the SR2 rack and returned a large pile of no-longer-used cables to the tent.
  • Mark started a HealthCheck page on the Operation Manual wiki.

Fabian and Mark

Plan for week of 4/8

  • Mark, Fabian at Kamioka Mon-Fri.
  • Help with Type Bp.
  • Health checks on Type B.
  • Monitor pumpdown.
  • Work on Type B paper.
  • Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
  • Tidy up.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.

Plan for week of 4/15

  • Mark at Mitaka 4/15, Kamioka 4/16-18, f2f 4/19.
  • Fabian at Kamioka 4/15-18, f2f 4/19.

Vacation/Travel Info

  • Mark at Mitaka 4/15.
  • f2f 4/19 (Friday), 4/20, 4/21.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's vacation from about 5/22 to 6/11.
  • Mark's final day 6/28.