Differences between revisions 43 and 324 (spanning 281 versions)
Revision 43 as of 2016-07-27 11:08:35
Size: 3207
Editor: MarkBarton
Comment:
Revision 324 as of 2018-09-13 15:33:31
Size: 3776
Editor: EnzoTapia
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian went to Kashiwa to clean up glue residue on the dummy BS and do a fit/function test of Tatsumi-san's modified tooling.
   * Most of the remaining glue came off with soaking in acetone, but there is still some in the machining grooves in the Al surface. Probably more work is required.
   * A set of cleanroom shoes borrowed from the ATC disintegrated when worn (the plastic had perished from age), which put small pieces of foam all over the floor in Hirose-san's cleanroom and required a lot of clean-up with a sticky roller! Cleanroom suits and shoes for use by Type B team at Mitaka/Kashiwa have been ordered, but will take another week to arrive.
   * The flag holding parts are now much easier to place and remove, much reducing the risk of breaking flags after gluing.
   * The sapphire and metal prisms from both the first BS gluing and the PR3 hanging test mirror were brought back to Mitaka for ultrasonic cleaning to remove glue, so they can be reused.
  * Hirata-san found the SR versions of the screws for immobilizing the IM and IRM. These fit much better than the BS ones (despite being the same design) and will be used for the BS.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Report for week of 9/10 ====
 * We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
 * We checked all the motors, like:
       *the IM picos, BF picos.
 * We checked the BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
 * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
 * We reset the IP FRs to midrange.
 * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
 * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
 * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

=== Type B (Mark) ===
==== Report for week of 9/3 ====
 * We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
 * We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
 * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
 * We reset the IP FRs to midrange.
 * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
 * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
 * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

==== Plan for week of 9/10 ====
 * Monday 9/10 is scheduled power outage.
 * Mark in US (job interview).
 * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
 * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
===== Etc =====
 * Recover from power outage.
===== SR2 =====
 * Calibrate F0 LVDTs.
 * Calibrate IP LVDTs.
 * Cable geophones and any other remaining PI items.
 * Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
 * Do basic go/no-go test of electronic items.
 * Check SF keystone height and offload with FR as necessary.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Set SF damper magnet ring height.
 * Check/tweak optic pitch.
 * TFs.
==== Plan for week of 9/17 ====
 * Monday 9/17 is holiday (Respect for the Aged Day).
 * Enzo on vacation.
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
===== SR2 =====
 * Crane SR2 into tank.
 * Move SR2 in-air cables.
 * Remove First Contact.
 * Unlock and realign suspension.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.

==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
 * Suspend IM and tweak height/balance.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark: 9/10-14 (job interview in US).
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 9/10

  • We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
  • We checked all the motors, like:
    • the IM picos, BF picos.
  • We checked the BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
  • We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
  • We reset the IP FRs to midrange.
  • We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
  • We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
  • We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

Type B (Mark)

Report for week of 9/3

  • We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
  • We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
  • We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
  • We reset the IP FRs to midrange.
  • We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
  • We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
  • We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

Plan for week of 9/10

  • Monday 9/10 is scheduled power outage.
  • Mark in US (job interview).
  • Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
  • Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.

Etc
  • Recover from power outage.

SR2
  • Calibrate F0 LVDTs.
  • Calibrate IP LVDTs.
  • Cable geophones and any other remaining PI items.
  • Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
  • Do basic go/no-go test of electronic items.
  • Check SF keystone height and offload with FR as necessary.
  • Adjust ballast/trim mass of SF, with reserve for yaw stepper.
  • Set SF damper magnet ring height.
  • Check/tweak optic pitch.
  • TFs.

Plan for week of 9/17

  • Monday 9/17 is holiday (Respect for the Aged Day).
  • Enzo on vacation.
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.

SR2
  • Crane SR2 into tank.
  • Move SR2 in-air cables.
  • Remove First Contact.
  • Unlock and realign suspension.

SRM
  • Set pitch of SRM and RM, tighten clamps, remove winch system.
  • Weigh IM/... section.
  • Build up SS to BF level.
  • Add BF.

Plan for week of 9/24

  • Monday 9/24 is holiday (Autumn Equinox).
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
  • Suspend IM and tweak height/balance.

SRM
  • Cable/test BF.
  • Install IRM.
  • Install/cable/test IM OSEMs.

To-Do Lists, Schedule

Vacation Info

  • Mark: 9/10-14 (job interview in US).
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)