Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Fabian went to Kashiwa to clean up glue residue on the dummy BS and do a fit/function test of Tatsumi-san's modified tooling.
   * Most of the remaining glue came off with soaking in acetone, but there is still some in the machining grooves in the Al surface. Probably more work is required.
   * A set of cleanroom shoes borrowed from the ATC disintegrated when worn (the plastic had perished from age), which put small pieces of foam all over the floor in Hirose-san's cleanroom and required a lot of clean-up with a sticky roller! Cleanroom suits and shoes for use by Type B team at Mitaka/Kashiwa have been ordered, but will take another week to arrive.
   * The flag holding parts are now much easier to place and remove, much reducing the risk of breaking flags after gluing.
   * The sapphire and metal prisms from both the first BS gluing and the PR3 hanging test mirror were brought back to Mitaka for ultrasonic cleaning to remove glue, so they can be reused.
   * We arranged with Hirose-san to collect the dummy BS and mirror box next Thursday 8/4. (This is conditional on the new clean suits arriving.) Further work will be done at Mitaka.
   * Hirata-san arranged to borrow the NAOJ Hi-Ace van for the trip.
  * Hirata-san found the SR versions of the screws for immobilizing the IM and IRM. These fit much better than the BS ones (despite being the same design) and will be used for the BS.
  * Fabian worked on design of the extra 600 g of trim mass that will be needed for the IM.
  * Fabian updated the geophone noise plot with a more accurate calibration.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
 * We debugged an issue with the actuation (the real-time model needed rebooting).
 * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
 * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
 * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
 * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
 * We cabled all the PI items through to the rack and did very basic testing.
 * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
 * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
 * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
 * We put the magnets on the LBB damper ring using the template.
 * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
 * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.

==== Plan for week of 9/19 ====
No work Mon 9/18 (敬老の日)<<BR>>
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun
 * Double check BS pitch with OL.
 * Adjust SF damper ring to correct gap.
 * Install lock nuts on F0 GAS FR at TBD positions.
 * Lock BF and F0 keystones (but ''not'' SF keystone).
 * Lock RM to BS and IRM to IM.
 * Lock RM, IRM and BF (but not SF) to security structure.
 * Lock IP.
 * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
 * Attach lifting fixture.
 * Remove BF- and SF-level crossbars.
 * Remove geophones for craning.
 * Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
 * Attach lifting plates.
 * Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20).
 * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
 * Crane tank lid off.
 * Crane LBB damper rings to top of tank and suspend.
 * Crane suspension out of assembly frame.
 * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
 * Crane suspension into tank and connect upper rods to LBB Cu ring.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Measure required ballast for LBB.
 * Unlock suspension and readjust.
 * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).

==== Plan for week of 9/25 ====
TBD

 * Debug cabling.
 * Run TFs.
 * Install LSOL?

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
  • We debugged an issue with the actuation (the real-time model needed rebooting).
  • We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
  • We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
  • We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
  • We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
  • We cabled all the PI items through to the rack and did very basic testing.
  • We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
  • We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
  • We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
  • We put the magnets on the LBB damper ring using the template.
  • We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
  • We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.

Plan for week of 9/19

No work Mon 9/18 (敬老の日)
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun

  • Double check BS pitch with OL.
  • Adjust SF damper ring to correct gap.
  • Install lock nuts on F0 GAS FR at TBD positions.
  • Lock BF and F0 keystones (but not SF keystone).

  • Lock RM to BS and IRM to IM.
  • Lock RM, IRM and BF (but not SF) to security structure.
  • Lock IP.
  • Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
  • Attach lifting fixture.
  • Remove BF- and SF-level crossbars.
  • Remove geophones for craning.
  • Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
  • Attach lifting plates.
  • Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20).
  • Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
  • Crane tank lid off.
  • Crane LBB damper rings to top of tank and suspend.
  • Crane suspension out of assembly frame.
  • Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
  • Crane suspension into tank and connect upper rods to LBB Cu ring.
  • Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
  • Install LBB lower rods and hook LBB.
  • Measure required ballast for LBB.
  • Unlock suspension and readjust.
  • Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).

Plan for week of 9/25

TBD

  • Debug cabling.
  • Run TFs.
  • Install LSOL?

Vacation Info

Mark: 10/16-24