 * Type B Past Week Summary
  * Mark and Fabian went to Kashiwa to clean up glue residue on the dummy BS and do a fit/function test of Tatsumi-san's modified tooling.
   * Most of the remaining glue came off with soaking in acetone, but there is still some in the machining grooves in the Al surface. Probably more work is required.
   * A set of cleanroom shoes borrowed from the ATC disintegrated when worn (the plastic had perished from age), which put small pieces of foam all over the floor in Hirose-san's cleanroom and required a lot of clean-up with a sticky roller! Cleanroom suits and shoes for use by Type B team at Mitaka/Kashiwa have been ordered, but will take another week to arrive.
   * The flag holding parts are now much easier to place and remove, much reducing the risk of breaking flags after gluing.
   * The sapphire and metal prisms from both the first BS gluing and the PR3 hanging test mirror were brought back to Mitaka for ultrasonic cleaning to remove glue, so they can be reused.
   * We arranged with Hirose-san to collect the dummy BS and mirror box next Thursday 8/4. (This is conditional on the new clean suits arriving.) Further work will be done at Mitaka.
   * Hirata-san arranged to borrow the NAOJ Hi-Ace van for the trip.
  * Hirata-san found the SR versions of the screws for immobilizing the IM and IRM. These fit much better than the BS ones (despite being the same design) and will be used for the BS.
  * Fabian updated the [[attachment:Geophone_Kamioka.png|geophone noise plot]] with a more accurate calibration and also plotted the [[attachment:Geophone_Kamioka_noise_ratio.png|S/N over readout noise]].
  * Fabian identified 210 g of the 600 g deficiency in the IM mass as due to SS parts on the outside. However identifying the rest would require time-consuming disassembly of the IM, and it's not worth it because whatever the cause, the fix is to design and add more trim mass.
  * Hirata-san measured another filter, and worked on buying various small items.
  * Mark moved most of the contents of a bunch of older Dropbox and OneDrive shared folders into a new /Subsystems/VIS/TypeB folder on the KAGRA Dropbox.
  * Mark worked on a list of considerations for locating the BS rack, in preparation for discussions with Miyakawa-san et al.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test NEARLY DONE. The part looks good and will be used but the ones for SR3 and SRM will be made from scratch.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - from 8/1.
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 11/12 ====
 * BS
  * Kozu-kun noticed the BS OL was out of range, and Fabian and Fujii-kun investigated. It turns out that the temperature has risen by over 2°C, so all the GAS filters have sagged and several stages are touching. Miyoki-san and Furuta-san are looking at what can be done.
 * SRM
  * We did the vertical height survey and found that as with SR2 and SR3, the chain is longer than the CAD, this time by ≈7 mm, and again mostly between the SF and BF.
  * The final SRM small glass mirror became available, so we had Hirose-san ship it to us so we can install it while the suspension is still on the assembly frame. Hirata-san ordered shims to make up the new recommended thickness of 1.4 mm and a micrometer to check the combination, which should arrive on Monday 11/26.
 * SR2
  *
 
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 11/19 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo and Fabian at Kamioka Mon-Thu.
 * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
===== SRM =====
 * Go/no-go test of all electronics items, especially SF/... section.
 * Finish vertical height check and adjust SF trim mass as required.
 * Unlock IP and center roughly.
 * Check/adjust alignment of SS.
 * Calibrate IP LVDTs.
 * Add arc weights and geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Disconnect cables at feedthroughs, lock suspension.
 * Crane into tank.
===== SR2 =====
 * Assist MIF team with pico cables and LBB breadboard ballast.
 * Install SR2 OL pillar and shelf (with AOL supervision)?

==== Plan for week of 11/26 ====
 * Move SRM in-air cables over to tank.
 * Remove First Contact.
 * Unlock and align SRM.
 * Hook and roughly ballast LBB.

==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.

==== Vacation/Event Info ====
 * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 11/12

  • BS
    • Kozu-kun noticed the BS OL was out of range, and Fabian and Fujii-kun investigated. It turns out that the temperature has risen by over 2°C, so all the GAS filters have sagged and several stages are touching. Miyoki-san and Furuta-san are looking at what can be done.
  • SRM
    • We did the vertical height survey and found that as with SR2 and SR3, the chain is longer than the CAD, this time by ≈7 mm, and again mostly between the SF and BF.
    • The final SRM small glass mirror became available, so we had Hirose-san ship it to us so we can install it while the suspension is still on the assembly frame. Hirata-san ordered shims to make up the new recommended thickness of 1.4 mm and a micrometer to check the combination, which should arrive on Monday 11/26.
  • SR2

To-Do Lists, Schedule

Plan for week of 11/19

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo and Fabian at Kamioka Mon-Thu.
  • Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).

SRM
  • Go/no-go test of all electronics items, especially SF/... section.
  • Finish vertical height check and adjust SF trim mass as required.
  • Unlock IP and center roughly.
  • Check/adjust alignment of SS.
  • Calibrate IP LVDTs.
  • Add arc weights and geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Disconnect cables at feedthroughs, lock suspension.
  • Crane into tank.

SR2
  • Assist MIF team with pico cables and LBB breadboard ballast.
  • Install SR2 OL pillar and shelf (with AOL supervision)?

Plan for week of 11/26

  • Move SRM in-air cables over to tank.
  • Remove First Contact.
  • Unlock and align SRM.
  • Hook and roughly ballast LBB.

Plan for week of 12/3

  • f2f Meeting at NAOJ - no Kamioka work.

Vacation/Event Info

  • Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).