Line 2: Line 2:
Line 5: Line 4:
 * Type B Past Week Summary
  * Mark and Fabian went to Kashiwa to clean up glue residue on the dummy BS and do a fit/function test of Tatsumi-san's modified tooling.
   * Most of the remaining glue came off with soaking in acetone, but there is still some in the machining grooves in the Al surface. Probably more work is required.
   * A set of cleanroom shoes borrowed from the ATC disintegrated when worn (the plastic had perished from age), which put small pieces of foam all over the floor in Hirose-san's cleanroom and required a lot of clean-up with a sticky roller! Cleanroom suits and shoes for use by Type B team at Mitaka/Kashiwa have been ordered, but will take another week to arrive.
   * The flag holding parts are now much easier to place and remove, much reducing the risk of breaking flags after gluing.
   * The sapphire and metal prisms from both the first BS gluing and the PR3 hanging test mirror were brought back to Mitaka for ultrasonic cleaning to remove glue, so they can be reused.
   * We arranged with Hirose-san to collect the dummy BS and mirror box next Thursday 8/4. (This is conditional on the new clean suits arriving.) Further work will be done at Mitaka.
   * Hirata-san arranged to borrow the NAOJ Hi-Ace van for the trip.
  * Hirata-san found the SR versions of the screws for immobilizing the IM and IRM. These fit much better than the BS ones (despite being the same design) and will be used for the BS.
  * Fabian updated the [[attachment:Geophone_Kamioka.png|geophone noise plot]] with a more accurate calibration and also plotted the [[attachment:Geophone_Kamioka_noise_ratio.png|S/N over readout noise]].
  * Fabian identified 210 g of the 600 g deficiency in the IM mass as due to SS parts on the outside. However identifying the rest would require time-consuming disassembly of the IM, and it's not worth it because whatever the cause, the fix is to design and add more trim mass.
  * Hirata-san measured another filter, and worked on buying various small items.
  * Mark moved most of the contents of a bunch of older Dropbox and OneDrive shared folders into a new /Subsystems/VIS/TypeB folder on the KAGRA Dropbox.
  * Mark worked on a list of considerations for locating the BS rack, in preparation for discussions with Miyakawa-san et al.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test NEARLY DONE. The part looks good and will be used but the ones for SR3 and SRM will be made from scratch.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - from 8/1.
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for the week of 4/8 ====
 * Support of Type Bp
  * Mark made lots of Guardian improvements:
   * Used Guardian's timer functionality to drastically reduce the number of notifications during ramping.
   * Added new requestable states DCCTRL_ONLY and NEUTRAL (and associated transitional states) to facilitate testing.
   * Tidied up the code to use tabs consistently throughout for indentation.
   * Disabled the test for the IM-H coil driver WD (to work around the fact that only the relay in the chassis has been disabled, not the WD signals going to the BIO).
 * We opened the BS tank lid and offloaded a large IM-Y offset to F0-Y with manual adjustment of the broken yaw mechanism).
 * We opened the SR2 side doors and adjusted the V1 OSEM to mid-range.
 * Mark offloaded a large SR2 IM-Y offset to F0-Y.
 * Mark did health checks for BS, SR2 and SR3.
 * Fabian offloaded yaw from SRM and did the SRM health check.
 * Fabian updated the Python code for the stepper driver MEDM screen to reflect that two stepper drivers have different mappings to work around dead channels.
 * Fabian monitored pumpdown on Friday afternoon and will continue on Saturday.

==== Plan for week of 4/15 ====
 * Mark, Hirata-san at Kamioka Tue-Thu.
 * Fabian at Kamioka Mon-Wed.
 * All at f2f Meeting 4/19-21.
 * Post-pumpdown health checks.
 * Teach Hirata-san about the computer systems and control theory.
 * Work with Lucia to do blending of the IP LVDTs and geophones.
 * More Guardian improvements.
  * Update vistools.py (formerly LIGO sustools.py) for Type B and KAGRA, and have the TYPEB.py Guardian use it where appropriate.
  * Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
 * Work on Type B paper.
 * Tidy up.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.

==== Vacation/Travel Info ====
 * Mark at Mitaka 4/15.
 * f2f 4/19 (Friday), 4/20, 4/21.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's US vacation from 5/22 to 6/11.
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 4/8

  • Support of Type Bp
    • Mark made lots of Guardian improvements:
      • Used Guardian's timer functionality to drastically reduce the number of notifications during ramping.
      • Added new requestable states DCCTRL_ONLY and NEUTRAL (and associated transitional states) to facilitate testing.
      • Tidied up the code to use tabs consistently throughout for indentation.
      • Disabled the test for the IM-H coil driver WD (to work around the fact that only the relay in the chassis has been disabled, not the WD signals going to the BIO).
  • We opened the BS tank lid and offloaded a large IM-Y offset to F0-Y with manual adjustment of the broken yaw mechanism).
  • We opened the SR2 side doors and adjusted the V1 OSEM to mid-range.
  • Mark offloaded a large SR2 IM-Y offset to F0-Y.
  • Mark did health checks for BS, SR2 and SR3.
  • Fabian offloaded yaw from SRM and did the SRM health check.
  • Fabian updated the Python code for the stepper driver MEDM screen to reflect that two stepper drivers have different mappings to work around dead channels.
  • Fabian monitored pumpdown on Friday afternoon and will continue on Saturday.

Plan for week of 4/15

  • Mark, Hirata-san at Kamioka Tue-Thu.
  • Fabian at Kamioka Mon-Wed.
  • All at f2f Meeting 4/19-21.
  • Post-pumpdown health checks.
  • Teach Hirata-san about the computer systems and control theory.
  • Work with Lucia to do blending of the IP LVDTs and geophones.
  • More Guardian improvements.
    • Update vistools.py (formerly LIGO sustools.py) for Type B and KAGRA, and have the TYPEB.py Guardian use it where appropriate.
    • Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
  • Work on Type B paper.
  • Tidy up.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.

Vacation/Travel Info

  • Mark at Mitaka 4/15.
  • f2f 4/19 (Friday), 4/20, 4/21.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's US vacation from 5/22 to 6/11.
  • Mark's final day 6/28.