 * Type B Past Week Summary
  * Akutsu-san provided a set of cleanroom gear (shoes only slightly too tight!) for use by Mark this week. And Sakamoto-san sent another set from Kamioka to Kashiwa.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
   * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test NEARLY DONE. The part looks good and will be used but the ones for SR3 and SRM will be made from scratch.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - from 8/1.
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 7/30 ====
===== SR3 =====
 * We undid the accidental misalignment of the SR3. We also switched off the BF GAS offset we had been using, let the IM rise until near zero on the BF LVDT, and adjusted the IM vertical OSEMs back to mid-range.
 * We closed control loops for the SR3 GAS filters.
 * Terrence set up the LED and TILT QPD for the final OL, and did a new calibration.
===== SR2 =====
 * We installed the SR2 SF damper magnet ring but found that the magnet pattern didn't match the Cu segments due to a different in the caps between SR3 and SR2. We raised the ring but left it suspended, clamped the template to the underside and rearranged the magnets.
 * We did a vertical height budget of the SR2. It turns out to have a very similar issue to the SR3: the chain is about 5 mm longer than the CAD, with about 3 mm of that between the SF and BF. We decided to do the same fix and operate with the F0 keystone 5 mm higher. We chose an total amount of ballast to give that keystone height and secured most of it to the SF, keeping a reserve for cables and the yaw stepper.
 * We routed most (all?) of the SF/... cabling up to the PI.

===== SRM =====
 * We moved the SRM assembly frame into its final position, reset it to the initial configuration, double-checked the heights of the crossbars, and lowered the optical table by 3 mm (to give margin for the optic to rise during hanging, which we had kept forgetting to do). We cleaned it up with the airgun and wet-wipes. We installed the IM ring and IM.
 * We assembled the SRM metal mass. Hirata-san made a jig from a plate with 4 screws which could safely hold the delicate front Sol-Black-coated ring upside down while the rest of the components were mounted on it.
 * We moved the metal mass to the mirror box and added the prisms and magnet standoffs. We applied the EP30 on Friday morning, but probably won't be able to check the result until after Obon.

==== Plan for week of 8/13 ====
 * KAGRA closed Mon, Tue.
 * Mark on vacation Mon-Thu, then Mitaka on Friday.
 * Enzo, Fabian, Terrence, Panwei, Rikako at Kamioka Wed-Fri. Probably no tunnel work.
 * Hirata-san on vacation all week.
 * TFs with new OL.
 * Controls work.
 * Tune SR3 IP?

==== Plan for week of 8/20 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Thu, then f2f.
 * Kozu-kun works at Mozumi Mon.

===== SR3 =====
 * Hook LBB, add ballast mass.
 * Tune IP.

===== SR2 =====
 * Adjust ballast/trim mass, with reserve for yaw stepper.
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Set damper height.
 * Add arc weights, adjust IP.
 * Stage LBB damper rings in tank.
 
===== SRM =====
 * Check gluing result - redo if necessary.
 * Assemble RM.
 * Add IM ballast masses (we forgot this before).
 * Get parts from AOL and set up new pitch-setting OL.
 * Hang metal mass.
 * Hang RM.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark: 8/13-16.
 * Hirata-san: 8/13-17
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/30

SR3
  • We undid the accidental misalignment of the SR3. We also switched off the BF GAS offset we had been using, let the IM rise until near zero on the BF LVDT, and adjusted the IM vertical OSEMs back to mid-range.
  • We closed control loops for the SR3 GAS filters.
  • Terrence set up the LED and TILT QPD for the final OL, and did a new calibration.

SR2
  • We installed the SR2 SF damper magnet ring but found that the magnet pattern didn't match the Cu segments due to a different in the caps between SR3 and SR2. We raised the ring but left it suspended, clamped the template to the underside and rearranged the magnets.
  • We did a vertical height budget of the SR2. It turns out to have a very similar issue to the SR3: the chain is about 5 mm longer than the CAD, with about 3 mm of that between the SF and BF. We decided to do the same fix and operate with the F0 keystone 5 mm higher. We chose an total amount of ballast to give that keystone height and secured most of it to the SF, keeping a reserve for cables and the yaw stepper.
  • We routed most (all?) of the SF/... cabling up to the PI.

SRM
  • We moved the SRM assembly frame into its final position, reset it to the initial configuration, double-checked the heights of the crossbars, and lowered the optical table by 3 mm (to give margin for the optic to rise during hanging, which we had kept forgetting to do). We cleaned it up with the airgun and wet-wipes. We installed the IM ring and IM.
  • We assembled the SRM metal mass. Hirata-san made a jig from a plate with 4 screws which could safely hold the delicate front Sol-Black-coated ring upside down while the rest of the components were mounted on it.
  • We moved the metal mass to the mirror box and added the prisms and magnet standoffs. We applied the EP30 on Friday morning, but probably won't be able to check the result until after Obon.

Plan for week of 8/13

  • KAGRA closed Mon, Tue.
  • Mark on vacation Mon-Thu, then Mitaka on Friday.
  • Enzo, Fabian, Terrence, Panwei, Rikako at Kamioka Wed-Fri. Probably no tunnel work.
  • Hirata-san on vacation all week.
  • TFs with new OL.
  • Controls work.
  • Tune SR3 IP?

Plan for week of 8/20

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Thu, then f2f.
  • Kozu-kun works at Mozumi Mon.

SR3
  • Hook LBB, add ballast mass.
  • Tune IP.

SR2
  • Adjust ballast/trim mass, with reserve for yaw stepper.
  • Cable/test PI items (LVDTs, steppers, geophones).
  • Set damper height.
  • Add arc weights, adjust IP.
  • Stage LBB damper rings in tank.

SRM
  • Check gluing result - redo if necessary.
  • Assemble RM.
  • Add IM ballast masses (we forgot this before).
  • Get parts from AOL and set up new pitch-setting OL.
  • Hang metal mass.
  • Hang RM.

To-Do Lists, Schedule

Vacation Info

  • Mark: 8/13-16.
  • Hirata-san: 8/13-17
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.