Differences between revisions 48 and 351 (spanning 303 versions)
Revision 48 as of 2016-08-03 13:23:13
Size: 2829
Editor: MarkBarton
Comment:
Revision 351 as of 2018-12-01 20:05:47
Size: 3540
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Akutsu-san provided a set of cleanroom gear (shoes only slightly too tight!) for use by Mark this week. And Sakamoto-san sent another set from Kamioka to Kashiwa.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror.
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
   * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test NEARLY DONE. The part looks good and will be used but the ones for SR3 and SRM will be made from scratch.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - from 8/1.
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 11/19 ====
 * BS
  * Fabian did some debugging on the BS and found that the calibration for the F0 LVDT was off due to an Excel error, and that the sag wasn't quite the 7 mm originally observed, but still enough to cause the suspension to touch down. Enzo tried applying LVDT actuation at the GAS filters and got it to lift off far enough to get sensible TFs, but the required BF offset was enough to put the IM OSEMs at the very edge of their usable range, so this is not a good long-term solution. We can probably raise the F0 keystone during the vent by removing mass and/or installing an auxiliary spring, which will then allow us to return the BF keystone to nominal height.
  * While working on the BS, Enzo noticed that one of the stepper drivers was not responding. It turned out to be water damaged from the rain issues earlier in the year. Enzo and Fujii-kun opened the rest of the BS chassises on the second floor but they seem to be OK. Tanaka-san had made a third driver chassis as a spare, so we reserved that and will install it in the week of 12/10.
 * SRM
  * The SRM-W optic arrived and we installed it in place of the SRM-M in the metal mass, taking care to use 1.4 mm shims as recommended by Hirose-san. The weight of the new assembly was within 1 g of the old and did not disturb the height of the payload. There was a very small change in pitch which we corrected with the IM picos.
  * We installed the shelf for the OL receiver.
  * We added the arc weights and geophones and went through several rounds of improving the centering of the IP and then realigning the security structure back to vertical.
  * We calibrated the F0 LVDT, and checked the F0 and IP actuation signs.
  * We adjusted the SF trim masses to set the SF pitch and roll, did an inventory of the trim mass and set the damper gap.
  * We did a final alignment of the whole chain and left the suspension ready for TFs during the f2f week. There is only a few hours of work left before we can install and we hope to do that on Monday 12/10.
 * SR2
  * Enzo replaced the geophones and cables that had been borrowed for calibration and did several rounds of optimization of the IP frequency. He got as low as 46 mHz but with poor Q and so backed off a bit to 55 mHz and may back off a tiny bit more.
  * I derived updated IP matrices for the BS and SR, with more precise geometry data provided by Hirata-san, and published them as T1707205 and T1807663.
  * I created a CENTERING screen for the IP, with large panel meters for the LVDT signals and the derived L, T and Y signals.
  * Enzo confirmed that the fancy stepper control screen created by Shoda-san worked.
  * We installed a modified LPCD as IM-V for testing.
 * SR3
  * We moved HPCDs from BS and SR2 to replace the ones that had been stolen from SR3, so as to create a working suspension with an OL for Kozu-kun.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]


==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.
==== Plan for week of 12/10 ====
 * Crane SRM into tank.
 * Install new F0 yaw mechanisms on SRs.
 * Remove First Contact from SRM, unlock and realign.
 * Move SRM in-air cables over.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 11/19

  • BS
    • Fabian did some debugging on the BS and found that the calibration for the F0 LVDT was off due to an Excel error, and that the sag wasn't quite the 7 mm originally observed, but still enough to cause the suspension to touch down. Enzo tried applying LVDT actuation at the GAS filters and got it to lift off far enough to get sensible TFs, but the required BF offset was enough to put the IM OSEMs at the very edge of their usable range, so this is not a good long-term solution. We can probably raise the F0 keystone during the vent by removing mass and/or installing an auxiliary spring, which will then allow us to return the BF keystone to nominal height.
    • While working on the BS, Enzo noticed that one of the stepper drivers was not responding. It turned out to be water damaged from the rain issues earlier in the year. Enzo and Fujii-kun opened the rest of the BS chassises on the second floor but they seem to be OK. Tanaka-san had made a third driver chassis as a spare, so we reserved that and will install it in the week of 12/10.
  • SRM
    • The SRM-W optic arrived and we installed it in place of the SRM-M in the metal mass, taking care to use 1.4 mm shims as recommended by Hirose-san. The weight of the new assembly was within 1 g of the old and did not disturb the height of the payload. There was a very small change in pitch which we corrected with the IM picos.
    • We installed the shelf for the OL receiver.
    • We added the arc weights and geophones and went through several rounds of improving the centering of the IP and then realigning the security structure back to vertical.
    • We calibrated the F0 LVDT, and checked the F0 and IP actuation signs.
    • We adjusted the SF trim masses to set the SF pitch and roll, did an inventory of the trim mass and set the damper gap.
    • We did a final alignment of the whole chain and left the suspension ready for TFs during the f2f week. There is only a few hours of work left before we can install and we hope to do that on Monday 12/10.
  • SR2
    • Enzo replaced the geophones and cables that had been borrowed for calibration and did several rounds of optimization of the IP frequency. He got as low as 46 mHz but with poor Q and so backed off a bit to 55 mHz and may back off a tiny bit more.
    • I derived updated IP matrices for the BS and SR, with more precise geometry data provided by Hirata-san, and published them as T1707205 and T1807663.
    • I created a CENTERING screen for the IP, with large panel meters for the LVDT signals and the derived L, T and Y signals.
    • Enzo confirmed that the fancy stepper control screen created by Shoda-san worked.
    • We installed a modified LPCD as IM-V for testing.
  • SR3
    • We moved HPCDs from BS and SR2 to replace the ones that had been stolen from SR3, so as to create a working suspension with an OL for Kozu-kun.

To-Do Lists, Schedule

Plan for week of 12/3

  • f2f Meeting at NAOJ - no Kamioka work.

Plan for week of 12/10

  • Crane SRM into tank.
  • Install new F0 yaw mechanisms on SRs.
  • Remove First Contact from SRM, unlock and realign.
  • Move SRM in-air cables over.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)