 * Type B Past Week Summary
  * Akutsu-san provided a set of cleanroom gear (shoes only slightly too tight!) for use by Mark this week. And Sakamoto-san sent another set from Kamioka to Kashiwa.
  * Fabian did a fit test of the winches onto the IM.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
  * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Fabian worked on the payload assembly procedure.
  * Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Enzo):
 * Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
 * Enzo worked on the final cabling plan for BS and SRx.
 * Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).

At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):
 * We glued magnets into their holders.
 * We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
 * We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
 * Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
 * We practiced putting sapphire prisms on the BS but didn't apply glue.
 * We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
 * We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
 * Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
 * We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
 * Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.

==== Plan for weeks of 7/10, 7/17 ====
Mark, Enzo mostly at Kamioka.
 * More TFs.
 * Receive BS at Kamioka, do gluing if possible.
 * Learn how Miyo-kun's pico driver software works and make fixes/improvements.
 * Test picos and steppers more fully.
 * Finish tidying rack and labeling cables.
Line 16: Line 32:
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - NEW TRIM MASS ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata) - DONE
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
   Fabian, Hirata-san at Mitaka.
 * Do new 3D CAD (Hirata-san):
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
  * Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
   * In-tank version.
 * Solve arc weight versus magic wand problem.
 * Do mass budget for LBB - design ballast masses (Fabian)
 * Run TFs, make improvements to real-time model (Mark, Enzo).
 * Design SR assembly frame.
 * Inventory for SR.
==== Plan for week of 7/10 ====
Mark and Enzo at Kamioka:
Fabian and Hirata-san at Mitaka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Enzo):

  • Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
  • Enzo worked on the final cabling plan for BS and SRx.
  • Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).

At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):

  • We glued magnets into their holders.
  • We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
  • We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
  • Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
  • We practiced putting sapphire prisms on the BS but didn't apply glue.
  • We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
  • We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
  • Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
  • We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
  • Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.

Plan for weeks of 7/10, 7/17

Mark, Enzo mostly at Kamioka.

  • More TFs.
  • Receive BS at Kamioka, do gluing if possible.
  • Learn how Miyo-kun's pico driver software works and make fixes/improvements.
  • Test picos and steppers more fully.
  • Finish tidying rack and labeling cables.

Fabian, Hirata-san at Mitaka.

  • Do new 3D CAD (Hirata-san):
    • SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
    • Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
      • On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
      • In-tank version.
  • Solve arc weight versus magic wand problem.
  • Do mass budget for LBB - design ballast masses (Fabian)
  • Run TFs, make improvements to real-time model (Mark, Enzo).
  • Design SR assembly frame.
  • Inventory for SR.

Plan for week of 7/10

Mark and Enzo at Kamioka: Fabian and Hirata-san at Mitaka.