Differences between revisions 51 and 219 (spanning 168 versions)
Revision 51 as of 2016-08-03 17:06:24
Size: 3279
Editor: MarkBarton
Comment:
Revision 219 as of 2018-01-26 11:14:26
Size: 1706
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Akutsu-san provided a set of cleanroom gear (shoes only slightly too tight!) for use by Mark this week. And Sakamoto-san sent another set from Kamioka to Kashiwa.
  * Fabian did a fit test of the winches onto the IM.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
  * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Fabian worked on the payload assembly procedure.
  * Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
=== Type B (Mark) ===
==== Report for week of 1/15 ====
 * We swapped in the other available BF, and it was rather better: only 0.3 mm of keystone tilt rather than 1.3 mm. We will use it for the SR2 and then think about whether we want to use or rebuild the original one.
 * We finished the preparation of the second BF, setting the yoke, adding the new-style cable clamps etc.
 * We changed the 1.6 mm sockets on the BF LVDT cable to 1.0 mm ones to match the pins on the LVDT wires. The specification of the cable in D1503901 was apparently wrong. We will update it (today) before doing the cable order for the SR3 and SRM.
 * We received, unpacked and temporarily stored a shipment of weights and other parts that will be used to check the load capacity of the top filters.
 * We updated the BS real-time model and screens, adding support for a damping filter common to both the OL-TM and OL-IM paths, per Izumi-san's suggestion in G1807653.
 * We set up the router for the SR2 rack and got the SR2_IM pico driver and both stepper motors on the network (the SR2_BF pico is still on order).
Line 16: Line 14:
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - NEW TRIM MASS ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata) - DONE
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

==== Plan for week of 1/29 ====
 * Enzo at Mitaka 1/29 and most of 1/30, then vacation.
 * Kozu-kun away.
 * All others at Kamioka.
 * Make in-air pico adapter cables.
 * Test IM picos and BF yaw pico.
 * Calibrate LVDT.
 * Install ballast mass in BF.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/15

  • We swapped in the other available BF, and it was rather better: only 0.3 mm of keystone tilt rather than 1.3 mm. We will use it for the SR2 and then think about whether we want to use or rebuild the original one.
  • We finished the preparation of the second BF, setting the yoke, adding the new-style cable clamps etc.
  • We changed the 1.6 mm sockets on the BF LVDT cable to 1.0 mm ones to match the pins on the LVDT wires. The specification of the cable in D1503901 was apparently wrong. We will update it (today) before doing the cable order for the SR3 and SRM.
  • We received, unpacked and temporarily stored a shipment of weights and other parts that will be used to check the load capacity of the top filters.
  • We updated the BS real-time model and screens, adding support for a damping filter common to both the OL-TM and OL-IM paths, per Izumi-san's suggestion in G1807653.
  • We set up the router for the SR2 rack and got the SR2_IM pico driver and both stepper motors on the network (the SR2_BF pico is still on order).

Plan for week of 1/29

  • Enzo at Mitaka 1/29 and most of 1/30, then vacation.
  • Kozu-kun away.
  • All others at Kamioka.
  • Make in-air pico adapter cables.
  • Test IM picos and BF yaw pico.
  • Calibrate LVDT.
  • Install ballast mass in BF.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)