Line 5: Line 5:
 * Type B Past Week Summary
  * Akutsu-san provided a set of cleanroom gear (shoes only slightly too tight!) for use by Mark this week. And Sakamoto-san sent another set from Kamioka to Kashiwa.
  * Fabian did a fit test of the winches onto the IM.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
  * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Fabian worked on the payload assembly procedure.
  * Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
 
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - NEW TRIM MASS ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata) - DONE
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 4/2 ====

 * We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
 * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
 * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
 * Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs.
 * Fujii-kun and Yamamoto-kun got the SR3 real time model running.
 * Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
 * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Finish IMs and IRMs
 * Glue SR3 mirror

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Build 1xRM
 * Start SR3 Hang
  * Align assembly frame.

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/2

  • We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
  • We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
  • Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
  • Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs.
  • Fujii-kun and Yamamoto-kun got the SR3 real time model running.
  • Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
  • Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Finish IMs and IRMs
  • Glue SR3 mirror

Plan for week of 4/16

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Build 1xRM
  • Start SR3 Hang
    • Align assembly frame.

Plan for week of 4/23

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka?
  • Mark, Enzo at Kamioka
  • Hirata-san at Mitaka
  • Tanioka-san at Mitaka?
  • --
  • Clean parts (cable clamp bases, etc, etc).
  • Observe KAGRA Phase 1 operations, assist if problems arise.

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Fabian vacation, 3/26-4/27 (then gone).